Reynolds Creek Water Line Site Visit Minutes.pdf
PDF 143 KB Posted
- Attached to
- Replace Waterlines at Reynolds Creek Park
- Solicitation number
- W9126G22B0007
About this file
The document contains minutes from a site visit for the Replace Waterlines at Reynolds Creek Park federal contract opportunity. Key details include that the worksite has extremely rocky soil that will require contractors to install waterlines in conglomerate rock. While no hard date for award was provided, bids will be opened on July 20th and award is usually made within a couple weeks thereafter. The scope of work involves replacing aging waterlines and abandoning the existing lines in place. Contractors should expect the soil conditions to require following manufacturer installation standards. The Corps of Engineers district will provide applicable as-built drawings but notes the records may not be complete. Disposal of excess material must occur off-site in accordance with specifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reynolds Creek Water Minutes
1. Contractors shall be prepared for rocky soil, broken rock, and conglomerate rock during waterline placement. Worksite has extremely rocky geological makeup.
2. Is there a hard date for Award? Contractors expecting long lead times for multiple materials, anticipating Oct start date. No hard date for award. Bids will be opened July 20th. Award is usually not more than a couple weeks after that.
3. Security Requirements are in 1.2.2, it is written incorrectly on the notes.
4. Are there any known gas lines or other buried utilities? No know gas lines. There is electrical run underground from distribution panels to individual campsites.
5. Is there Geotech information for the area? None provided by the Corps.
6. Will the old line be abandoned in place? In the SOW (section 01 11 00) in sub-sections 1.3.1 and 1.3.2 it is stated that all existing old line and equipment shall be abandoned in place.
7. Are there depth requirements for road crossings? The same depth requirements for the rest of the line.
Not less than 18 inches.
8. Are all the roads that will be crossed paved? Yes
9. Is the linear footage in the contract considering a certain percentage plus or minus? The linear footage listed in the contract specs is higher than the measurement of waterline in the maps/appendices to allow for some deviation from that path in the event of unforeseen obstacles.
10. How will daily reports be submitted? Emailed to the COR
11. Is embedment required? There is no specific requirement for Embedment; however, section 33 11 00 subsection 3.2 requires all pipe be installed in accordance with the manufacturer’s recommendations and any applicable referenced standards.
12. Is any brush clearing required? Most of the waterline layout falls within the mowed area. Any needed brush clearing would be at contractors discretion for better work access.
13. What are the branch line materials? HDPE, PVC, Galvanized? PVC and Galvanized
14. Will possible detour around culverts be a modification? Additional footage has been factored into the contract scope to allow for some variation. A detour would only result in a mod if it put the total footage over that specified within the contract or ran in to an issue that qualified as a differing site condition.
15. Is there a size requirement of the size of rock during cleanup? There is no specific size requirements;
however, section 33 11 00 subsection 3.2 requires all pipe be installed in accordance with the manufacturer’s recommendations and any applicable referenced standards. Anything not considered usable by those standards may not be used.
16. Will debris from cleanup be disposed of off-site or on site? Section 31 00 00 sub-section 3.5 states that all unsuitable material shall be disposed of off site.
17. Can the Corps post as-builts of current utilities? The corp’s will provide any applicable as-builts it has, but these will probably not be complete.
18. What are the trench width and compaction requirements? section 01 11 00 subsection 1.3.1 and 1.3.2 requires contractor meet manufacturer’s compaction requirements. There is no trench width requirement.
19. Is there a required distance from the road shoulder for the main line? No, however no line can be uncased within 18 in. of the roads footprint.
20. Do road crossings require a certified casting? No
21. Are electrical service lines all overhead, buried, or combination? Distribution lines are run overhead.
Power then drops to breaker panels and is run underground to service each individual campsite.