B3_Amend-0002_W9126G-16-B-0014_(002).pdf

PDF 91 KB Posted

Attached to
SABINE-NECHES WATERWAY, TEXAS
Solicitation number
W9126G-16-B-0014
Issued by

About this file

PROJECT UNRESTRICTED PROCUREMENT SABINE-NECHES WATERWAY TEXAS JEFFERSON COUNTY TEXAS PORT ARTHUR CANAL JUNCTION AREA AND TAYLOR BAYOU - PIPELINE DREDGING

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W45VAK60297678

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT: SOLICITATION W9126G-16-B-0014, SABINE-NECHES WATERWAY, TEXAS, JEFFERSON COUNTY, TEXAS, PORT ARTHUR CANAL, JUNCTION AREA, AND TAYLOR BAYOU - PIPELINE DREDGING SEE THE ATTACHED PAGES.

1. CONTRACT ID CODE PAGE OF PAGES

J 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G-16-B-0014

X 9B. DATED (SEE ITEM 11)

26-Apr-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-May-2016

CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

2000 FORT POINT ROAD

GALVESTON TX 77550-1229

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

M3ECXMD3

Typewritten Text

M3ECXMD3

Typewritten Text

W9126G-16-B-0014

A0002-2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. The specifications for Solicitation No. W9126G-16-B-0014, Sabine-Neches Waterway, Texas, Port Arthur Canal, Junction and Taylors Bayou, in Jefferson County, Texas, Pipeline Dredging, are hereby amended as follows:

a) Specifications.

(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with Amendment No. 0001.

(2) SECTION 01 22 00.10, MEASUREMENT AND PAYMENT – The enclosed SECTION 01 22 00.10 entitled MEASUREMENT AND PAYMENT supersedes that issued with this Solicitation.

2. This amendment shall be attached to and become a part of the solicitation.

2 Encls:

1. SECTION 00 11 00.00 45, BID SCHEDULE

2. SECTION 01 22 00.10, MEASUREMENT AND PAYMENT

SWG FILE NO.:SN 103-375 SOLICITATION NO.:W9126G-16-B-0014

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 11 00.00 45

BID SCHEDULE

PART 1 GENERAL

1.1 1.1 BID SCHEDULE

1.1.1 Schedule No. 1

1.1.2 Option No. 1

1.1.3 Option No. 2

1.1.4 Option No. 3

1.1.5 Option No. 4

1.2 MODIFICATIONS (CESWG)

1.3 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0014)

SECTION 00 11 00.00 45

BID SCHEDULE

AMENDMENT NO. 0002

PART 1 GENERAL

1.1 1.1 BID SCHEDULE

BID SCHEDULE

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.1 Schedule No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization

1 JOB SUM $___________

0002 Pipeline Management 1 JOB SUM $___________

0003 Dredging Section No. 1 54,000 C.Y. $_________ $___________

0004 Dredging Section Nos. 4 and 5

854,000 C.Y. $_________ $___________

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.01 45 is for Schedule No.

1.

DOCUMENT 00 11 00.00 45 Page 2

BID SCHEDULE (CONT'D)

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.2 Option No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 1

0005 Dredging Section No. 2 100,000 C.Y. $_________ $___________

0006 Pipeline Management 1 JOB SUM $___________

TOTAL OPTION NO. 1 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________

NOTE: The Government may exercise Option No. 1 by written notice to the Contractor prior to completion of all authorized work. Award of Option No.

1 is contingent upon availability of funds. An additional time of 12 calendar days will be added to this contract for completion of Option No. 1.

DOCUMENT 00 11 00.00 45 Page 3

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.3 Option No. 2

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 2

0007 Dredging Section No. 3A (42'+1') 27,000 C.Y. $_________ $___________

0008 Dredging Section No. 3B (45'+1') 56,000 C.Y. $_________ $___________

0009 Pipeline Management 1 JOB SUM $___________

0010 Standby for Port of Port Arthur Dredging

72 HOUR $_________ $___________

TOTAL OPTION NO. 2 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1 AND 2 $___________

NOTE: The Government may exercise Option No. 2 by written notice to the Contractor prior to completion of all authorized work. Award of Option No.

2 is contingent upon availability of funds. An additional time of 13 calendar days will be added to this contract for completion of Option No. 2.

DOCUMENT 00 11 00.00 45 Page 4

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.4 Option No. 3

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 3

0011 Dredging Section No. 6 209,000 C.Y. $_________ $___________

0012 Pipeline Management 1 JOB SUM $___________

TOTAL OPTION NO. 3 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, AND 3 $___________

NOTE: The Government may exercise Option No. 3 by written notice to the Contractor prior to completion of all authorized work. Award of Option No.

3 is contingent upon availability of funds. An additional time of 20 calendar days will be added to this contract for completion of Option No. 3.

DOCUMENT 00 11 00.00 45 Page 5

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.5 Option No. 4

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 4

0013 Dredging Section No. 7 87,000 C.Y. $_________ $___________

0014 Pipeline Management 1 JOB SUM $___________

TOTAL OPTION NO. 4 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, 3, AND 4 $___________

NOTE: The Government may exercise Option No. 4 by written notice to the Contractor prior to completion of all authorized work. Award of Option No.

4 is contingent upon availability of funds. An additional time of 10 calendar days will be added to this contract for completion of Option No.4

DOCUMENT 00 11 00.00 45 Page 6

DOCUMENT 00 11 00.00 45 Page 7

(TO BE ATTACHED TO STANDARD FORM 1442)

1.2 MODIFICATIONS (CESWG)

If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment of each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.

1.3 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 8

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUBMITTALS

1.2 LUMP SUM PAYMENT ITEMS

1.2.1 Mobilization and Demobilization

1.2.1.1 Payment

1.2.1.2 Unit of Measure

1.2.2 Pipeline Management

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.3 UNIT PRICE PAYMENT ITEMS

1.3.1 Dredging

1.3.1.1 Payment

1.3.1.2 Dredging Partial Payment

1.3.1.3 Measurement

1.3.1.4 Electronic Positioning

1.3.1.5 Surveys During Progress of Work

1.3.1.6 Unit of Measurement

1.3.2 Standby for Port of Port Arthur Dredging

1.3.2.1 Payment

1.3.2.2 Measurement

1.3.2.3 Unit of Measure

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

SECTION 01 22 00.10 Page 1

SECTION 01 22 00.10

MEASUREMENT AND PAYMENT

AMENDMENT NO. 0002

06/14

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Surveys; G

Submit drawings of surveys during progress of work by soundings or sweepings.

1.2 LUMP SUM PAYMENT ITEMS

Payment items for the work of this Contract for which Contract lump sum payments will be made are listed in the BID SCHEDULE and specified below.

All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for which separate payment is not otherwise provided.

1.2.1 Mobilization and Demobilization

1.2.1.1 Payment

The Contract price for "Mobilization and Demobilization" in Schedule No. 1 will include the costs in connection with mobilization and demobilization of the plant necessary to perform work under the various bid items. The Contract price shall include transportation and other costs incidental to delivery of the plant and other equipment to the general work area in condition ready for operation and, after the completion of the work, for removal of the plant and equipment from the work site(s). Payment for mobilization and demobilization will be pursuant to the conditions of the

SECTION 00 723 00.01 45 CONTRACT CLAUSESSPECIAL CONTRACT REQUIREMENTS,

STANDARD, Paragraph: PAYMENT FOR MOBILIZATION AND DEMOBILIZATION.

1.2.1.2 Unit of Measure

Unit of measure: Job.

SECTION 01 22 00.10 Page 2

1.2.2 Pipeline Management

1.2.2.1 Payment

Payment for "Pipeline Management" in Schedule No. 1 and Option Nos. 1 through No. 4 will be made for costs associated with laying, handling of dredge pipelines, from the dredge to the Placement Area, procurement of materials, and for construction of ramps or installation of culvert pipes that may be necessary in connection with placing and removal of pipeline and final clean up of pipeline route. Monthly partial payments will be based on the estimates of work completed during the period up to 80 percent of the Contract price and the remaining 20 percent will be paid in the first monthly partial payment after removal of the pipeline and the final clean-up of the pipeline route.

1.2.2.2 Unit of Measure

Unit of measure: Job.

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work in this Contract on which the Contract unit price payments will be made are listed in the BID SCHEDULE and specified below. The unit price and payment made for each item listed shall constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for each of the unit price items.

1.3.1 Dredging

1.3.1.1 Payment

The contract unit price per cubic yard for "Dredging Section No. 1" and "Dredging Section Nos. 4 and 5" in Schedule No. 1; "Dredging Section No. 2" in Option No. 1; "Dredging Section No. 3A (42'+1')" and "Dredging Section No. 3B (45'+1')" in Option No. 2; "Dredging Section No. 6" in Option No. 3;

and "Dredging Section No. 7" in Option No. 4, will be made for costs associated with the removal of dredged material, transportation, and placement at the Placement Areas. The contract price for dredging shall also include the costs for maintenance of levees, spillways and ditches necessary to confine the material within the areas shown and cost for providing temporary access to the Placement Area drop-outlet structures.

1.3.1.2 Dredging Partial Payment

Partial payment will be based on approximate quantities determined by fathometer soundings or sweepings taken behind the dredge. The Contractor may use its own hydrographic surveys to determine quantities for pay requests, but final quantities will be based on Government Before-Dredging and After-Dredging surveys.

1.3.1.3 Measurement

The material removed will be measured by cubic yard in place, by means of soundings taken before and after dredging. The total quantity of dredged material will be the theoretical quantity between the bottom surface shown

SECTION 01 22 00.10 Page 3 by fathometer soundings of the last survey made "before-dredging" and the bottom surface shown by the fathometer soundings of a survey made "after-dredging", within the limits of the overdepth and side and end slopes, less deductions that may be required for misplaced material.

1.3.1.4 Electronic Positioning

The horizontal control points shown are the control points the Government will use to perform electronic surveys on the waterway. The Government does not guarantee permanent access to these control points, therefore, it may be necessary for the Contractor to establish its own network of survey points from these survey points or from other U.S. Coast and Geodetic Survey (USCGS) monuments. Location and description of the horizontal control points which the Government plans to use to perform electronic surveys on the channels are available at the Port Arthur Resident Office.

The Contractor shall be responsible for establishing its own reference line to conduct hydrographic surveys and dredging operations if electronic positioning equipment is not used.

1.3.1.5 Surveys During Progress of Work

Contract depth will be determined by surveys taken behind the dredge as work progresses. The Contractor shall take progress soundings or sweepings.

1.3.1.6 Unit of Measurement

Unit of measure: cubic yard.

1.3.2 Standby for Port of Port Arthur Dredging

1.3.2.1 Payment

(AM#2) Payment for standby time will be made at the Contract unit price for "Standby for Port of Port Arthur Dredging" in Option No. 2 which will include required standby time at the port docks associated with idle time for ships to move from the dock to allow for dredging. No separate payment will be made for standby or down time incurred while dredging the federal channels.Payment for standby time, to include time for removal of trash and debris from the cutterhead and pump, will be made at the contract unit price for "Standby for Port of Port Arthur Dredging" in Option No. 2, which will include the standby hours required at the Dock in Section Nos. 3A & 3B. If Option No. 2 is awarded, payment for standby incurred during this work will also be included in this item. No separate payment will be made for standby or down time incurred while dredging the federal channels.

1.3.2.2 Measurement

(AM#2) Standby time shall be measured to the nearest 0.250.01 hour and recorded in the daily report.

daily report.

1.3.2.3 Unit of Measure

Unit of measure: Hour

SECTION 01 22 00.10 Page 4

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section --

SECTION 01 22 00.10 Page 5

B3_Amendment_0002_Cover_Page_SABINE
Amend 0002 page-2
00 11 00.00 45
01 22 00.10

File details come from the government source that posted it. Updated .