SOLICITATION_-_W9124M-16-B-0013.pdf

PDF 799 KB Posted

Attached to
Renovate Education Center Federal contract opportunity
Solicitation number
W9124M-16-B-0013
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Stewart

About this file

Renovate Education Center Bldg 128. Hunter Army Airfield GA 31409

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Education Center, newest first.
File Type Posted
ABSTRACT-BUILDING_128_-_.pdf PDF
Amendment_04_-_Conformed_Document.pdf PDF
1874_DRAWINGS__REV3.pdf PDF
AMENDMENT_04_-_Document.pdf PDF
AMENDMENT__03-_Conformed.pdf PDF
AMENDMENT__03-_Document.pdf PDF
SITE_VISIT_SIGN-IN_SHEET1.pdf PDF
Results_of_Asbestos_Insepction.pdf PDF
SF_30_Form_for__AMENDMENT_02_-_Document.pdf PDF
RFI_Questions.pdf PDF
ACM_REPORT_.pdf PDF
SOLICITATION_AMENDMENT_-_SITE_VISIT_INFORMATION_-_SECTION_L_of_Solicitation_1_.pdf PDF
DRAWINGS_-_REVISED_-_0013.pdf PDF
DRAWING_-_Building_128.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0010866123

PROJECT NO: FN-5-2J

PROJECT TITLE: Renovate Education Center, Bldg 128

PROJECT LOCATION: Hunter Army Airfield Georgia

SET ASIDE: 100% HUBZone

NAICS CODE: 236220 Commercial and Institutional Building Construction

SIZE STANDARD: $36.5 Million

MAGNITUDE OF CONSTRUCTION PROJECT: The estimated value of the proposed w ork is betw een $1,000,000 and $5,000,000

All w ork shall be completed per Scope of Work, Terms, Conditions, Provisions, Clauses, Draw ings and Specifications.

BONDS: Bid Bond, Payment Bond, and Performance Bonds shall all be required.

PREBID MEETING/SITE VISIT: Thursday, 18 August 2016.

DUE DATE FOR ALL QUESTIONS: Monday, 22 August 2016.

BID OPENING: Wednesday, 14 September 2016.

X

SEBRENA M. BUTLER (912)767-9033

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

12-Aug-2016

(RFP)

(IFB)

CALL:

Renovate Education Center Bldg 128

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________14 Sep 2016 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

MISSION & INSTALLATION CONTRACTING CMND

MICC-FORT STEWART

976 WILLIAM H WILSON AVE SUITE 100

FORT STEWART GA 31314-3425

W9124M

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

FN-6-2J

8. ADDRESS OFFER TO (If Other Than Item 7)

(912)767-2966FAX:TEL: (912)767-8420 TEL: FAX:

W9124M-16-B-0013 214

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section A - Solicitation/Contract Form

SPECIAL INSTRUCTIONS

PROPOSAL BREAKDOWN K, L & M Work

FN-6-2J Division of Work Description

K ‐ Renovation L ‐ New Work M ‐ Furniture/Equipment

Civil K work – Remove existing asphalt pavement adjacent to building 128: the parking lot and driveway north of the building, a section of service road east of the building, and a section of William Barksdale Circle south and east of the building. Remove roadbed in these locations to a point 4” below the original surface elevation. Remove concrete curb where indicated on the plans. Remove concrete loading dock at the south end of the building, and also some miscellaneous slabs on the site. Remove 8” of existing gravel parking lot and soil west of building 128. Remove soil necessary for installation of new asphalt parking lot and driveway.

Install 10” of aggregate base and 2” of asphalt pavement for the new asphalt parking lot and driveway. Install pavement markings and roadway signs.

Civil L work – Remove trees in front of building. Install silt fence and a construction exit for erosion control. Bring in structural fill as required. Compact soil before installing pavement or gravel. Install concrete wheel stops in new gravel parking lot. Install new sidewalk with detectable warning tiles as indicated on plans. Install concrete parking lot access control island, drop arm gates, card reader, and vehicle detection devices. Install topsoil as indicated on plans, fine grade soil, and install grass sod.

General K work – All demolition and construction performed within the boundary(perimeter)of the existing building 128 shell as indicated on the plans.

General L work – All building construction performed to the northwest of the existing building 128 shell(building addition)as indicated on the plans.

Mechanical K work – All mechanical work in the original building rooms 1 through 38 and rooms 44 through 58 as shown on mechanical drawing H‐1. This includes HVAC, Plumbing and Fire Protection. Note room numbers on H‐1 are different from the Architectural drawings.

Mechanical L work – All mechanical work in the addition Northwest side of the building;

Including rooms 39 through 43 and AHU‐6, as shown on the Mechanical drawing H‐1. . This includes HVAC, Plumbing and Fire Protection. Note room numbers on H‐1 are different from the Architectural drawings.

Electrical K Work ‐

All electrical items demolished within the footprint of the original building are categorized as K Work. This work includes lighting and associated circuits/controls, panelboards and feeders, wiring devices and associated circuits, fire alarm and associated circuits, and data system components. Reference Electrical Drawing E‐4.

Demolition of non‐utility electrical service items is Electrical K Work.

New Electrical K Work shall comprise those systems within the footprint of the original building that replace those demolished, eg. lighting and associated circuits and controls, panelboards and feeders, wiring devices and associated circuits, new fire alarm and mass notification systems as well as associated circuits, and telecommunications systems infrastructure.

Reference Electrical Drawings E‐5 thru E‐8.

Electrical L Work ‐

New Electrical L work shall comprise those systems within the footprint of the building addition performed to the northwest of the existing Building 128 shell as indicated on Electrical Drawings E‐5 thru E‐8. New systems include lighting and associated circuits and controls, panelboards and feeders, wiring devices and associated circuits, new fire alarm and mass notification systems as well as associated circuits, and telecommunications systems infrastructure. Reference Electrical Drawings E‐5 thru E‐8.

New Electrical L work shall also include new conduit and service laterals for a new power company pad mounted transformer (not in this contract), power to new powered entrance gates, and electrical underground ducts for new data, telephone, and CATV services. Note that interior and exterior wiring for the data, telephone, and CATV systems is not part of the Electrical L Work.

Electrical M Work ‐

New Electrical M Work for data, telephone, and CATV shall include low voltage wiring, jacks, cover plates, racks, rack electronics, trunk and backbone cables and fibers both interior and exterior, as well as miscellaneous telecommunications wiring. Testing of the aforementioned systems is also considered Electrical M Work. The prospective Contractor shall take note that infrastructure items such as conduit sleeves, cable trays, j‐hooks, bridle rings, device boxes, power circuits for telecommunications items, etc., are NOT a part of the Electrical M Work.

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Reno Bldg 128 - K Work

FFP

Please see Proposal Breakdown Sheet - Section A for description of K work.

FOB: Destination

PURCHASE REQUEST NUMBER: 0010866123

NET AMT

0002 1 Job Civil Work & Grassing Bldg 128 - L Work

FFP

Please see Proposal Breakdown Sheet - Section A for description of L work.

0003 1 Job Reno Bldg 128 - M Work

FFP

Please see Proposal Breakdown Sheet - Section A for description of M work.

0004 1 Job OPTION "L" Work (Addition) Reno Bldg 128 SAF

FFP

Please see Proposal Breakdown Sheet - Section A for description of L work.

All building construction performed to the northwest of the exisiting building 128 shell (Building Addition) as indicated on the plans.

"Subject to the Availability of Funds." (SAF)

0005 1 Job Contract Manpower Reporting (CMR)

FFP

The contractor will report All contractor labor hours (Including subcontractor labor hours) required for performance of services provided under this contract for the Department of the Army via a secure data collection site - See Section H.

Section C - Descriptions and Specifications

STATEMENT OF WORK

TECHNICAL PROVISIONS

GENERAL

Renovation of Bldg 128 into the Army Education Center

IJO NO FN-6-

2J H-1874

1. DESCRIPTION OF WORK:

1.1 Work to be Done: The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with “Renovation of Bldg 128 into the Army Education Center” complete in strict accordance with specifications and drawings. The work includes, but is not necessarily restricted to, the following items.

1.1.1 The renovation of building 128 consists of the demolition of most of the existing interior building components, windows, doors and roofing/roof decking of the 17,226 s.f. building leaving only the structural skeleton.

The building will be reconstructed and additional square footage will be added. Upon completion the new facility will be approximately 20,932 s.f. and will house the Army Continuing Education System/Army Career and Alumni Program. In addition to the classroom spaces, computer labs, testing labs and offices, there will be office suites for four local college representatives.

1.1.2 The work includes, but is not necessarily restricted to, the following items.

1.1.4 SITE / CIVIL

1.1.4.1 Replace deteriorated sidewalks and add new as required.

1.1.4.2 Remove deteriorated asphalt parking lot at rear of existing building and provide a new paved parking lot.

1.1.4.3 Provide and install new lift gate parking lot control mechanism with card reader capabilities for existing rear parking lot.

1.1.4.4 Provide and install new “crush & run” gravel to existing parking area across the street from facility and rework parking lot entrances.

Regrade parking area as necessary to provide proper rain water fall off.

1.1.4.5 Demolish all unused mechanical/fuel systems located at rear of building.

1.1.4.6 Provide and install new electric service, telephone service, data and cable television service.

1.1.5 STRUCTURAL

1.1.5.1 Add new bar joists to existing roof structure to compensate for load imposed by new rooftop HVAC units.

1.1.5.2 Provide and install footings, c.m.u. walls and steel bar joists for new building addition.

1.1.6 GENERAL CONSTRUCTION

1.1.6.1 An ACM survey has been conducted by FS Environmental Division. The survey indicates that ACM is present in building materials throughout the existing building. A supplemental survey shall be performed to pinpoint hot locations and an ACM remediation plan shall be developed.

1.1.6.1.1 All ACM shall be removed, bagged, transported and dumped as prescribed by law. All FS Environmental Division procedures shall be followed and all requirements shall be met. See 4.4.3.1 below for further requirements

1.1.6.2 Construct new metal stud/gypsum wall board walls throughout existing and new building shells to create classrooms, computer labs, testing labs, offices and other associated spaces. Existing and new c.m.u. walls shall be finished with gypsum wall board, rigid insulation board and metal furring on the interior side.

1.1.6.3 Interior finishes throughout facility shall be VCT flooring, carpet tile flooring, ceramic tile flooring/wainscot, rubber cove base, painted walls, gypsum wall board ceilings and acoustical tile ceilings.

1.1.6.4 Exterior doors/frames shall be painted galvanized H.M. Interior doors shall be stained S.C. wood with painted H.M. frames. Some doors shall have glass sidelights. Main entrance doors shall be aluminum storefront/glass.

1.1.6.5 Windows shall be fixed aluminum tube frames with insulated glass and shall meet the minimum blast mitigation requirements.

1.1.6.6 Existing and new exterior c.m.u. wall surfaces shall be painted and sealed.

1.1.6.7 Provide and install a new metal fascia on part of the facility. The fascia shall consist of metal stud under framing with aluminum composite panels over.

1.1.6.8 Provide and install a new rubber roofing system over rigid insulation board and metal roof deck on entire facility.

1.1.7 FIRE PROTECTION

1.1.7.1 Provide and install a new Fire Sprinkler System.

1.1.8 PLUMBING

1.1.8.1 All existing plumbing fixtures, kitchen equipment, boiler and domestic water lines shall be demolished. Existing sanitary lines shall be abandoned or reused as possible.

1.1.8.2 Install new domestic water distribution lines, sanitary lines, hot water heaters and plumbing fixtures as required by the construction documents.

1.1.9 MECHANICAL

1.1.9.1 Demolish all existing HVAC systems on roof, mechanical mezzanine, mechanical room, etc. Demolish all HVAC duct work, vents, piping, etc.

1.1.9.2 Provide and install (6) new rooftop package units throughout new facility complete with all necessary supply and return duct work, sensors and controls to provide a workable and balanced air tempering and distribution system.

1.1.9.3 Provide and install all necessary ventilation systems as required by code for restrooms, janitor’s closet, kitchen areas, etc.

1.1.10 ELECTRICAL

1.1.10.1 Demolish all existing wiring, controls, power points, lighting, sub-panels, lighting panels and main panels throughout building. All electrical components for new facility shall be new.

1.1.10.2 Provide and install a new MDP, step-down transformers and subpanels throughout facility as required per the construction documents.

1.1.10.3 Provide and install all new power distribution wiring throughout facility per the construction documents and code requirements.

1.1.10.4 Provide and install all new lighting and controls throughout facility per the construction documents, lighting level standards and code requirements.

1.1.10.5 Provide and install all new data (networking) cables and equipment racks throughout the facility per the construction documents, User’s requirements and the NEC’s standards.

1.1.10.6 Provide and install all new telephone lines throughout facility per the construction documents and the User’s requirements.

1.1.10.7 Provide and install all new wiring, controls and equipment throughout the facility to meet Life Safety requirements.

1.1.10.8 Provide and install all new wiring, controls and equipment throughout the facility necessary to meet the Installation Mass Notification requirements.

1.1.10.9 Provide and install all new wiring, controls and equipment throughout facility for a workable IDS. Contractor to coordinate work efforts/responsibilities with FS Physical Security Division.

1.2 ADDITIVES

1.2.1 N/A

1.3 Government Furnished – Government Installed (GF-GI) Furniture and

Equipment:

1.3.1 N/A

1.4 Government Furnished – Contractor Installed (GF-CI) Furniture and

1.4.1 N/A

1.5 Contractor Furnished – Contractor Installed (CF-CI) Furniture and

1.5.1 N/A

1.6 WORK BY OTHERS: The Contractor shall afford the Government and separate contractors’ reasonable opportunity for the introduction and storage of their materials and equipment and the execution of their work, and shall connect and coordinate his work with theirs as required by the Contract Documents.

1.7 DRAWINGS AND SITE VISITS

1.7.1 The drawings indicate the extent of the general location and arrangement of existing conditions. It is strongly recommended that the Contractor visit the site to determine the complexity of the work and the amount of m a t e r i a l required to perform this project. Field measurements may be necessary to determine the size and quantity of materials. Conditions which are obvious/visible or which should be reasonably anticipated by the Contractor on inspection will not be considered under the Differing Site Conditions provision of the contract.

2. CONSTRUCTION CONSTRAINTS

2.1. Time of Performance

2.1.1 Access to Buildings – All work requiring access to building interiors excluding attics, crawl spaces, etc. and all other work shall be performed between 7:30 a.m. and 4:00 p.m. excluding official holidays, unless otherwise indicated or approved by the Contracting Officer. Requests to work during other than these normal hours shall be made in writing at least 36 hours in advance. For example, a request to work on a Saturday should be made no later than noon on Thursday.

2.1.2 Work Requiring Outages – Work requiring outages of utilities or building systems will be accomplished in accordance with prior approved schedules.

2.2. Outages – The contractor’s work requiring outages of utility or building systems will require 15 day advance notice and will be subject to the approval of the Contracting Officer. Notice shall include type of outage, date, and time outage will commence and estimated duration of outage.

2.3. Continuity – All tools, labor, and materials required to complete any item of work within a given work area or requiring an outage of any building utility or system, shall be available at the site prior to commencement thereof.

Once work has commenced on an item of work said work shall be continuously and diligently performed to completion and acceptance.

2.4. Road and/or Railroad Closures – Road and/or railroad closures will require a 15-day advance written notice and be subject to the Contracting Officer’s approval. Notice shall state reason for closure, date and time closure will commence and estimated duration of closure. A sketch shall be provided showing location of closure area and placement of barricades and signs. Closures shall be limited to a maximum of 5 calendar days.

2.5. Fire Zone – The contractor is required to provide 72-hour notice to the

Contracting Officer prior to the final programming of the fire zone information at the main fire station.

3. CONSTRUCTION ACTIVITIES:

3.1 Contractor shall submit a Safety Plan and Construction Schedule to the

Contracting Officer’s Representative (COR) 10 days in advance of any construction activities to arrange specific schedule for performing work as required by this Contract.

4. FACTORS AFFECTING PERFORMANCE UNDER THIS CONTRACT:

4.1 The Contractor shall coordinate use of the site for access, staging, and parking with the Contracting Officer.

4.2 Contractor shall be responsible for limiting access of his employees and subcontractors to the area of work defined in the Contract. Contractor shall not have access to restrooms and amenities such as vending machines unless granted permission by the Contracting Officer.

4.3 Contractor shall maintain haul routes to and from the job sites and the borrow pits, to include the borrow pit. In addition it is the contractor’s responsibility to meet all Local, State and Federal regulations for the operation of a borrow pit. Contractor shall control runoff and erosion on all excavation and backfilling operations.

4.4 RECYCLING, SALVAGE, AND DISPOSAL OF MATERIALS FORT STEWART

AND HUNTER ARMY AIRFIELD

4.4.1 Disposal: All waste generated from construction, demolition, and renovation contracts must be disposed of off the installation in a permitted disposal facility and in accordance with all Federal, State, and Local rules and regulations unless otherwise stated in the contract. At the end of each month, the contactor will provide copies of all disposal weight/scale tickets to the Contracting Officer’s Representative (COR) showing the in, out, and tare weights of each load taken from the installation. The COR will provide copies of these tickets to the DPW Environmental Division, Solid Waste Management Section for tracking and regulatory reporting requirements.

4.4.1.1 Recycling/Salvage: Fort Stewart and Hunter Army Air Field has a mandatory recycling program. The Installation Command Policy Letter #30 and Command Recycling SOP can be accessed at http://www.stewart.army.mil/info/?id=443&p=1. All recyclable materials (listed in the recycling SOP) generated during the entire term of any construction, demolition, or renovation contract will be turned over to the Fort Stewart or HAAF Recycling Program. Contractors must contact the COR who will coordinate with the DPW Environmental Waste Management Section (912-767-2010) to arrange for turn-in of recyclable/salvageable materials. In areas where large amounts of scrap metal or cardboard will be generated, it is possible that a collection bin/container could be provided to the Contractor at no cost to deposit these materials. Salvage materials, unless otherwise specified, become the property of the contractor upon removal from the job site and should be taken into consideration in formulating bids.

4.4.1.2 Hauling/Transport Requirements: All vehicles and containers used to transport waste or recyclables on or off the Installations will meet all Federal and State DOT requirements. All waste or recyclable materials being transported will be loaded, tied, and covered in such a manner that will prevent any of the materials from leaking, spilling, falling or blowing from/off the vehicle or container. It is the contractor’s responsibility to ensure immediate pick-up/clean-up of any material that is accidentally dropped, spilled or blown from a vehicle or container while in transit on and off the Installation.

4.4.1.3 Custodial Contract: If this contract is for custodial services or will include a custodial service requirement, the Contractor shall empty or otherwise transfer the contents from the blue recycling containers located inside buildings/facilities to the nearest blue recycling dumpster located outside.

The contactor will ensure that all recycled paper products are first placed inside a clear plastic bag and the top is tied closed before it too is placed inside the nearest blue recycle dumpster.

4.4.1.4 Recycling, Salvage, and Disposal: If any of the conditions listed under the

Recycling, Salvage, and Disposal section are not met, it will be considered a failure to comply with the terms of the contract as discussed in the inspection clause herein.

4.4.1.5 Guidance/Question: Anyone requiring further guidance, recycling training for contractors, or has additional questions on this section should contact the DPW Environmental Division, Solid Waste Management Section at 912-767-2010.

4.4.2 Chillers, pumps, HVAC units, and similar equipment must be logged on an applicable inventory/certification document prior to turn-in to recycling yard (on DD Form 1348). The form will be used to track the removal of units from facilities, refrigerant removal certification (if applicable), and a chain of custody from removal technician thru supply manager to recycling technician. The serial number and facility number will be listed on each form and one form may contain more than one like item. Recycling Yard personnel will verify document to items turned in, sign the document, and retain a file copy. Contractor shall submit this form to the KO. Additionally, damaged HVAC system may be accepted as scrap metal at the FSGA Recycling Scrap Metal Yard, Building 1143, or the HAAF Recycling Yard, Building 728, provided any and all freon has been certified as being removed from the system.

4.4.3 Toxic Substances Control Act (TSCA) Requirements

4.4.3.1 Asbestos Containing Materials (ACM)

4.4.3.2 If ACM will either be disturbed or removed, the contractor must perform asbestos abatement, containment, disposal and a 10-day notification to the Georgia Environmental Protection Division (GA EPD), as required by the Georgia Asbestos Safety Act, Official Code of Georgia Annotated Section 12-12-1. The disposal of ACM must be in accordance with both the GA EPD and Occupational Safety and Health Administration regulations.

4.4.3.3 REQUIRED SUBMITTAL ITEM: The Installation TSCA POC (Craig

Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil) must be provided a copy of the 10-day notification at the time the contractor informs GA EPD of their intent to properly abate the ACM. A copy of the Georgia asbestos shipment record must also be provided to the TSCA POC.

4.4.3.3.1 Lead-Based Paint (LBP)

4.4.3.3.2 If survey results, as reviewed by the Installation TSCA POC (Craig Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil), indicate LBP removal is necessary, the contractor will be required to collect, contain, and dispose of the LBP off-Post in accordance with local, state, and Federal regulations. The contractor will be required to provide the disposal manifest to the TSCA POC.

4.4.4 REQUIRED SUBMITTAL ITEM: LBP survey must be provided to the TSCA

POC, as applicable. The LBP disposal manifest must be provided to the TSCA POC if LBP removal was determined necessary by the TSCA POC

4.4.4.1 Installing Storage Tanks on Fort Stewart and Hunter Army Airfield

4.4.4.2 Underground Storage Tank Moratorium.

4.4.4.3 The installation of any underground storage tank and associated piping for the purpose of containing regulated and/or hazardous substances is strictly prohibited in the case where at least 10% of the total volume (tank + piping) is below the surface of the ground. Similarly, tanks in vaults for the purpose of installing tanks below grade are not acceptable.

4.4.4.4 Design Requirements for Aboveground Storage Tanks

4.4.4.5 Provide appropriate secondary containment (40 CFR 112.8(c)(2)). All aboveground storage tanks used for the purpose of storing regulated and/or hazardous substances must be double-walled. In order for a tank to be considered double-walled, the interstitial space between the inner and outer wall must be able to be inspected visually or the interstitial space must be equipped with a sensor capable of alarming in case of liquid in the interstice (access to the interstice must also allow for the periodic removal of liquids).

4.4.4.6 Provide tertiary containment (in accordance with 40 CFR 112.8(c)(3)). All aboveground storage tanks must be placed on an impervious diked concrete housekeeping pad designed to catch spills caused from transferring substance to/from the tank. This housekeeping pad must come with a valve that allows for the discharge of rainwater from the diked pad after a visual inspection has been done to determine that the water is clean.

4.4.4.7 Provide Instrumentation (Provide good engineering practices to avoid unwanted discharges, 40 CFR 112.8(c)(8)))

1. All aboveground storage tanks must come with a high liquid level alarm that emits both an audible and visual signal to alert operators that the tank must be emptied before further use.

2. The tank must also be equipped with a level gauge that allows for determining the level of liquid in the tank.

3. In the case of any tank equipped with a pump for the purpose of dispensing of a stored substance, the pump must have an automatic cutoff to prevent overfilling of a container.

4.4.4.8 Provide Labeling. All above ground storage tanks should be labeled IAW all applicable local, state, federal laws, or industry standard. At a minimum, the tank should display an appropriate hazard warning, material ID, and storage capacity.

4.4.4.9 Removing Underground Storage Tanks (USTs) on Fort Stewart and Hunter

Army Airfield

4.4.4.10 Tank Removal.

Note to ENGINEER - The Georgia Underground Storage Tank Management Program (GA USTMP) requires the removal of tanks after they have fulfilled their useful purpose and have been out of service for a period of twelve (12) months. Be aware that some tanks do NOT meet current tank standards but have an exemption from those standards based on their current use (e.g, heating oil tanks). If the use changes, those exemptions may no longer apply and the tank must be removed and if still needed will require replacement with an above ground tank.

4.4.5 Removal must follow the standards for removal and closure of registered tanks as outlined in the Georgia Underground Storage Tank Management Program (GA USTMP) guidance document (ref GA Rules 391-3-15-.11).

As a minimum oil samples must be taken and analyzed from the excavated pit’s walls and floor. A groundwater sample must be taken if a soil sample is not possible from beneath the UST. Soil and groundwater samples must be tested for benzene, toluene, ethylbenzene and xylenes (BTEX), total petroleum hydrocarbons-diesel range organics (TPH-DRO), and polynuclear aromatic hydrocarbons (PAHs). The USTs and associated piping must be removed and triple rinsed with water. Rinse water must be containerized (in drums or a tank) and analytical testing conducted by a certified Georgia laboratory, so the product can be correctly coded/classified on a Non-hazardous Manifest signed by an authorized representative from the Installation DPW Environmental Division. Disposal of materials (soil/rinseate) must be coordinated with the Installation DPW Environmental Division. See 1.0 for Recycling of cut up tank.

4.4.5.1 REQURED SUBMITTAL ITEM: Contractor shall provide (a) 24- hour notice

(and a POC/telephone number) prior to UST removal activities to allow time for Installation DPW Environmental Division representation at the site during the time thetank(s) is being removed from the ground. Installation DPW Environmental POC: Algeana Stevenson at 912-315-5144; (b) All lab tests and manifests for disposal of any contaminated soil/rinseate (pre-coordination with Installation DPW Environmental Division is required).

Letter and photo documentation (hard copy and digital) of the UST removal process is required of the UST removal contractor; and (c) confirmation cut up tank was delivered to the Recycling Center.

4.4.5.2 Removing Aboveground Storage Tanks (ASTs) on Fort Stewart and Hunter

Army Airfield

4.4.5.3 Tank Removal.

4.4.6 The AST(s) and associated piping must be removed and triple rinsed with water. Rinse water must be containerized (in drums or a tank) and analytical testing conducted by a certified Georgia laboratory, so the product can be correctly coded/classified on a Non-hazardous Manifest signed by an authorized representative from the Installation DPW Environmental Division. Disposal of materials (soil/rinseate) must be coordinated with the Installation DPW Environmental Division. See 1.0 for Recycling of cut up tank.

4.4.6.1 REQURED SUBMITTAL ITEM: Contractor shall provide (a) 24- hour notice

(and a POC/telephone number) prior to AST removal activities to allow time for Installation DPW Environmental Division representation at the site during the time the tank(s) is being removed. Installation DPW Environmental Division POC: Veronica Frazier at 912-767-2400; (b) All lab tests and manifests for disposal of any contaminated soil/rinseate (pre-coordination with the Installation DPW Environmental Division is required);

and (c) confirmation cut up tank was delivered to the Recycling Center.

4.4.6.2 Potable Water Utility Environmental Compliance Requirements

4.4.6.3 REQUIRED SUBMITTAL ITEM: Extending a water main: The contractor must submit applications for GA EPD’s approval through the Installation

DPW Environmental Division POC: Stanley Thomas at 912-767-4139.-. At least 100 days prior to construction, the contractor must submit the following items to the Installation DPW Environmental Division:

a) Three copies of the design plans and specifications for the proposed water main extension.

b) Every sheet of the drawings must be stamped by a GA certified P.E.;

the cover page of the specifications must also be stamped with document bond.

c) Water Extension Submittal Forms will be required for any project that has more than one service connection or if the water line tapping off the main is at least 6 inches in diameter.

d) All water lines must be disinfected and sampled IAW the most current addition of AWWA’s C651

4.4.6.4 Wells and Water Storage Tanks

4.4.6.5 The contractor must follow the specific guidance as stated in the GA EPD’s

“Minimum Standards for Public Water Systems”. This document can be found on the GA EPD’s web site:

http://www.gaepd.org/Files_PDF/techguide/wpb/standards.pdf .

4.4.6.6 Additional guidance can be found in the following documents:

a) Water Storage Tanks: The latest edition of the AWWA’s D102 (Coating Steel Water-Storage Tanks) and M42 (Steel Water-Storage Tanks).

(b) Wells: AWWA’s C654 (Disinfections of Wells)

i. A well permit application must be submitted prior to constructing a well.

ii. Well d r i l l i n g l o g s , s o u r c e s a m p l i n g data, and P.E.

construction certification statement must be submitted upon completion of all wells

4.4.7 Lead Requirements

4.4.7.1 Reference the Safe Drinking Water Act (as amended 4 JAN 2014) regarding standard for the lead content in plumbing materials. Lead content in solder and flux will not exceed 0.2% and lead content in the wetted surface of pipes, pipe fittings, plumbing fittings, and fixtures used in public potable water systems will not exceed 0.25%.

4.4.7.2 Prior to building turnover (as a minimum this is inclusive of all youth occupied facilities-Elementary Schools, Child Development Centers, and Youth Activity Centers), the potable water system throughout the building shall be flushed IAW Technical Information Paper No. 31-010-0911, Guidance for Reducing Drinking Water Lead Levels in New Buildings.

4.4.7.3 Meters. All new water service connections must be metered. See specific water meter & meter data management system requirements below.

4.4.8 Electrical meters and instrument transformers shall meet or exceed the following minimum requirements:

a) Measure quantities. Electrical meter quantities measured are Power (kilowatt), average demand over 15 minute intervals and Energy (kilowatt-hours).

b) System Accuracy. System accuracy for the meter product devices including instrument transformers shall not exceed 1% as calculated using the Root Sum Square (RSS) method and assuming normal distribution.

c) Meter Accuracy:

i. For facilities with connected 1oads equal to or greater than one (1) mega volt-ampere (MVA), meter certification shall be NEMA/ANSI C12.20, Accuracy class 0.2%.

ii. For facilities with loads less than 1MVA, meter certification shall be IEEE/ANSI C12.16, Accuracy class 0.5%.

d) Communication Protocol. Meters shall communicate via either Modbus RTU or ANSI/CEA-709.1b (LonTalk) protocols or as otherwise specified.

e) Auxiliary data ports. Unless otherwise specified, electrical meters shall have a minimum of two pulse inputs for incorporation and transmission of other external meter data.

f) Surge Protection. IEEE/ANSI C37.90.1, Standard surge withstand capability (SWC) tests for relays and relay systems associated with electric power apparatus.

g) Current transformers (CTs) sized properly so that the meter secondary of the transformer shall output current to ensure at least a plus or minus 0.6% accuracy of current when measured between 10% and 90% of full amperage range.

i. CTs shall not exceed 5 amps on the secondary side.

ii. Burden on CTs shall not exceed rated burden for the accuracy class.

iii. CTs shall be provided in split core configuration. 1.7.4 CTs shall be provided in the appropriate ranges to meet the service entrance amperage requirements.

iv. For facilities with a connected load equal to or greater than 1MVA, CT certification shall be IEC 185 or ANSI/IEEE C57.13 for 0.3% accuracy class or better.

v. For facilities with a connected load less than 1MVA, CTs shall revenue grade and certified per IEEE/ANSI C57.13 or

IEC 185.

h) Current sensors shall be sized properly for the application and provide a voltage (normally 0-2 volts) to the meter that results in at least a plus or minus 0.6% accuracy of current when measured between 10% and 90% of full amperage range.

i) Voltage or Potential Transformers (PTs) sized properly so that the meter secondary of the transformer shall output voltage to ensure at least a plus or minus 0.6% accuracy of voltage when measured from zero to the IEEE/ANSI C57.13 or IEC 185 specified standard burden, at the specified standard burden power factor, and at any value from 90% to 110% of rated voltage.

i. For facilities with a connected load equal to or greater than 1MVA, PT certification shall be IEC 185 or IEEE/ANSI C57.13 for 0.3% accuracy class or better.

ii. For facilities with a connected load less than 1MVA, PTs shall be revenue grade and certified per IEEE/ANSI C57.13 or IEC 185.

iii. 1.9.3) Burden on PTs shall not exceed rated burden for accuracy class.

j) Data Storage. Unless otherwise specified, the meter must be capable of providing and storing required interval data for a minimum of 30 days.

k) Environmental Tolerances of Metering Devices.

i. Meters shall be installed in indoors/interior locations and rated for operation and storage from 0° - 50° C or better and 5 to 90% relative humidity (non condensing). Interior meters shall be provided with or installed within a NEMA 12 enclosure.

4.4.9 Advanced Metering Data Management System front end computer requirements are:

a) Data encapsulation format shall be Extensible Markup Language (XML) and Simple Object Access Protocol (SOAP) for future output to a remote centralized meter data management system.

b) Storage of metered data for at least 2 years.

c) Display:

i. Display of data upon request and selectable from 1 minute to 15 minutes for kW.

ii. Final install of front end equipment shall, at minimum, display accurate data readings for each meter in a text format. Customization of the user interface is not required. Two hardcopies and two electric copies (DVD or CD) of detailed instructions shall be provided for customization and integration of additional display features that are not prepared at the time of final install.

iii. Display capability shall include multiple graphical formats such as data vs.

time (minutes, hours, days, weeks, months, and year) comparison between metered data from two or more meters and other standard meter data.

b) System expansion capability of 50 times for incremental future growth of metered data to include water, gas and steam.

c) Data Transmission Media is LAN, Radio Frequency, or Power Lines for interface of metered data to the Advanced Metering Data Management System, whichever is most economical for the site.

4.4.10 Backflow Prevention Device. REQUIRED SUBMITTAL ITEM: The

Contractor shall submit through the COR to the Installation DPW Environmental Division (a) type of backflow device with make, model, manufacturer, serial number and GPS coordinates for the installed location of the device; and (b) certifications by a certified backflow prevention installer/tester of backflow testing performed for each testable backflow device. The certified installer/tester must be certified from an EPD-approved Georgia Backflow Prevention Training Program.

4.5.1 Water Conservation Requirements. IAW the Georgia Water Stewardship

Act (GWSA), Section 8, water fixtures will meet the following minimum water conservation standards (note – Section 8 of the GWSA can be found on the bottom of the Georgia Environmental Protection Division’s website:

http://www.gaepd.org/Documents/outdoorwater.html ):

a) Toilets will not exceed 1.28 gallons per flush.

b) Showerheads will not exceed an average of 2.5 gallons of water per minute at 60 pounds per square inch of pressure.

c) Urinals will not exceed 0.5 gallons per flush.

d) Lavatory faucets will not exceed 1.5 gallons per minute flow.

e) Kitchen faucets will not exceed 2.0 gallons per minute flow.

4.5.2 Sanitary Inspections Prior to Government acceptance, the Contractor, through the COR, must coordinate with Installation Environmental Health,

(912) 435-5721 or (912) 257-1220, for bacteriological testing to ensure drinking water lines (e.g. Drinking fountain, utility sink, etc.) have been super-chlorinated with positive chlorine residuals and are free of any bacteria.

4.5.3 Outdoor Sprinkler Systems

Sprinkler systems must be isolated from potable drinking water lines (no cross-connection) to allow for easy conversion to non-potable water sources in the future. If a non-potable water source is within 200 feet of the site at the time of construction, tying into the non-potable lines is required.

If connected to a potable water source, a backflow preventer is required.

The sprinkler system must include timers and rain gauges to ensure the system is not running while there is a rainstorm.

4.5.4 Fire Hydrants

Hydrants shall be disinfected IAW AWWA Standard C651-5. Prior to placing into service, the Contractor, through the COR, must coordinate with Installation Environmental Health, (912) 435-5721 or (912) 257-1220, for bacteriological testing to ensure potable water lines have been super-chlorinated with positive chlorine residuals and are free of any bacteria.

4.5.5 Hydrant models specified should be those equipped with an anti-terrorism device. Fire hydrants should be equipped with a resilient seated check valve. Valve shall be manufactured to all testing and performance standards of AWWA C508 AND AWWA C550. Valves shall be rated for 250 psi water working pressure and tested at 500 psi hydrostatic pressure. Valve shall be a standalone unit able to be positively restrained to any mechanical joint fire hydrant shoe. Check valve shall be ductile iron ASTM Standard A536 (70-50-05), with NSF approved fusion bonded epoxy coating (interior and exterior). The valve shall incorporate a stainless steel spring that hastens positive closure and prevents water hammer. The valve shall be lead free, with no exposed lead bearing surface. The check valve shall have an unobstructed waterway. No reduction of port or redirection of flow will be allowed. Valve shall incorporate integral positive restraint connections to maintain a restrained connection between the fire hydrant and the gate valve. All fasteners to be Type 304 stainless steel.

4.6 Demolition

4.6.1 Ensure all water service connections with discontinued service due to abandonment or demolition are properly and permanently capped and sealed to prevent the escape of potable water or possible contamination.

4.6.2 Remove all asbestos lines that are abandoned as a result of a project.

4.6.3 Wastewater Requirements

4.6.4 REQUIRED SUBMITTAL ITEM: If a new sewer main, septic tank, and/or lift station will be installed, it is required that the contractor submit applications for GA EPD approval through the Installation DPW Environmental Division. At least 100 days prior to construction, the Contractor must submit the following through the COR to the DPW Environmental Division, Prevention and Compliance Branch to the attention of the Wastewater Program Manager (912-767-4937 or 767-2010).

a) The contractor must submit three copies of the sewer main extensions, septic tank, and/or lift station drawings and specifications.

b) All drawings and specification shall be stamped by a GA certified P.E.

c) Sanitary Sewer Extension Submittal Forms or Underground Injection Control Non-Domestic Septic System Forms will be submitted for any project that extends the sanitary sewer main, includes installation of a lift station or installation of septic tank/ leach field or septic system.

4.6.5 Lift Stations. The following are required:

a) High level alarm (visual & audible).

b) Perimeter fencing.

c) A Supervisory Control and Data Acquisition (SCADA) System compatible with the current system used on the Installation (thermostat controlled panel heaters will need to be included on transmitter units).Emergency bypass.

d) Electric generator. The standby generator must be commissioned in accordance with applicable OSHA, EPA, NEC and NFPA 110 Section 16620 Sanitary Sewer Pump Station Emergency Pump Station Standards. If diesel fuel generators are used (rather than natural gas) the fuel storage tanks must be double walled ASTs.

4.6.6 Demolition

4.6.7 Ensure all sewer service connections are properly disconnected prior to demolition. Permanently cap and seal service connections to prevent the infiltration of groundwater or surface water into the sanitary collection system.

4.6.8 The contents of septic tanks will be pumped out and properly disposed of at a wastewater treatment plant. The septic tank will be removed from its current location and the tank must be either recycled or otherwise properly disposed. After removal, backfill will be placed and compacted. The leach field soil may remain in place to naturally attenuate after abandonment of the site.

4.6.9 Stormwater/Erosion and Sedimentation Control (E&S) Requirements

4.7 Requirements for Sites with Soil Disturbance Greater Than 0.75 Acres

4.7.1 A Notice of Intent (NOI) for coverage under the Georgia National Pollution

Discharge Elimination System (NPDES) Permit must be applied for through the DPW Environmental Office Stormwater POC (Russell Moncrief at 912- 767-0271). The land disturbance calculation must include project entrances /exits, material lay down areas, equipment storage areas, soil stockpile, fill, and muck out areas. The NOI package has a mandatory 14-day waiting period once mailed to the Georgia Environmental Protection Division (EPD).

Land disturbing activities cannot occur until the 14-day waiting period has ended.. The NOI package includes an Erosion & Sedimentation and Pollution Control (ESPC) Plan, fees in the amount of $80/acre, the fee form, and the NOI application. In addition to meeting those requirements under the Georgia Erosion and Sedimentation Control Act, the contractor must also follow Federal and local E&S control regulations. A summary of the applicable stormwater / E&S requirements are provided below:

a) E&S Control Best Management Practices (BMPs) will be identified in the ESPC Plan and must be utilized by the contractor. The ESPC Plan will include those requirements identified in the “Green Book” (Manual for Erosion & Sedimentation Control for the State of Georgia), the Coastal Stormwater Supplement, the Energy Independence and Security Act Section 438, the US Environmental Protection Agency (EPA) Technical Guidance (EPA 841-B-09-001 December 2009), the United Facilities Criteria (UFC) Manual for Low

Impact Design, and those additional applicable Federal and local requirements found at the following web link:

http://www.stewart.army.mil/info/?id=443&p=1 and a summary of how these materials apply is provided in the three sub-bullets below.

Reference DPW Stormwater Management Policy Letter #11 and the USACE Hydrology and Low Impact Development site:

https://mrsi.erdc.dren.mil/sustain/cx/lid is used to house official documents, planning and design tools for use in development of Army projects. Army LID implementation will be accomplished using Army LID guidance "Army Stormwater Management Using Low Impact Development" (this document), the Army Low Impact Development Technical User Guide (see Best Practices section of the mrsi site), and the Army's LID Planning Tool and LID Cost Planning Tool (see Design Tools section of Army Stormwater Management Using Low Impact Development the mrsi site).

b) The ESPC Plan must also include flow calculations demonstrating concentrated runoff flows from peak rain events will not impact (a) any existing stream, (b) upstream systems and (c) downstream systems of the site as required for Total…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .