AMENDMENT_04_-_Document.pdf
PDF 88 KB Posted
- Attached to
- Renovate Education Center Federal contract opportunity
- Solicitation number
- W9124M-16-B-0013
About this file
Amendment 04
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ABSTRACT-BUILDING_128_-_.pdf | ||
| Amendment_04_-_Conformed_Document.pdf | ||
| 1874_DRAWINGS__REV3.pdf | ||
| AMENDMENT__03-_Conformed.pdf | ||
| AMENDMENT__03-_Document.pdf | ||
| SITE_VISIT_SIGN-IN_SHEET1.pdf | ||
| Results_of_Asbestos_Insepction.pdf | ||
| SF_30_Form_for__AMENDMENT_02_-_Document.pdf | ||
| RFI_Questions.pdf | ||
| ACM_REPORT_.pdf | ||
| SOLICITATION_AMENDMENT_-_SITE_VISIT_INFORMATION_-_SECTION_L_of_Solicitation_1_.pdf | ||
| DRAWINGS_-_REVISED_-_0013.pdf | ||
| DRAWING_-_Building_128.pdf | ||
| SOLICITATION_-_W9124M-16-B-0013.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0010866123 FN-6-2J
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
a. The purpose of this Amendment is to add Questions, Answ ers, and Revised Draw ings 3.
b. The Bid Opening date is: Monday, 19 September 2016. Please disregard date on Amendment 03 that states 26 September 2016 that w as a typo.
b. See Summary of Changes.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-Sep-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124M-16-B-0013
X 9B. DATED (SEE ITEM 11)
12-Aug-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Sep-2016
CODE
MISSION & INSTALLATION CONTRACTING CMND
MICC-FORT STEWART
ATTN: SEBRENA M. BUTLER
976 WILLIAM H WILSON AVE STE 100 (BUILDING 62
FORT STEWART GA 31314-3425
W9124M 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9124M-16-B-0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
DRAWINGS - H-1874
Amendment to Drawings Drawings: H -1874 REVISION 3 Dated: 9-12-2016 Drawings: For Constuction Date: 4-25-2016 Revision shown on Sheets E-5, E-6, E-8, E-9, E-10, E-11, H-0 AND H-3 of the Drawings.
Sebrena M. Butler Contract Specialist 912-767-9033
Mary L. Hightower Contract Officer 912-767-8472
QUESTIONS AND ANSWERS
Renovate Bldg. 128 – Questions from the contractors
1. What is the size of the Cable Tray shown on Sheet E‐8?
Answer:
Varies, see Amendment 4.
2. EF 1 and EF 2 are shown on the Mechanical Drawings but the Electrical Circuits are not shown on the
Electrical Drawings. Please clarify where these circuits should originate from.
See Amendment 4.
3. VAVs (58 ea.) are shown on the Mechanical Drawings but the Electrical Circuits are not shown on the
Electrical Drawings. Please clarify these circuits.
W9124M-16-B-0013
4. Is the Lab Casework Government furnished or contractor furnished? If the casework is contractor furnished, please provide a specification section and details. If the casework is Government furnished, where will the electrical termination be at each unit?
Lab Casework (Furniture) will be Government Furnished – Government Installed (GF-GI) Furniture and Equipment.
Electrical terminations shall be made at electrical junction blocks, final tie in shall be made by others.
5. On sheet E‐7 it shows horn‐strobes and speaker‐strobes in the same area. This is not fire code compliant.
Please let me know if I need to change all of the horn‐strobes to speaker‐strobes?
Check Legend for device types. Design is correct, provide devices as indicated.
(End of Summary of Changes)