Technical Exhibit 1

View the file

Other files for this federal contract opportunity

Other files attached to USASOC Range Control, newest first.
File Type Posted
Technical_Exhibit_4.docx DOCX document
Technical_Exhibit_6_-_Q&A_USASOC_Range_Control.docx DOCX document
W91247-18-R-0028_Amendment_01-ConformCopy.pdf PDF
W91247-18-R-0028_Amendment_01.pdf PDF
TECHNICAL_EXHIBIT_5.docx DOCX document
TECHNICAL_EXHIBIT_4.docx DOCX document
W91247-18-R-0028,_FINAL.pdf PDF
TECHNICAL_EXHIBIT_2.docx DOCX document
TECHNICAL_EXHIBIT_3.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL EXHIBIT 1

Performance Requirements Summary (PRS)

Performance Objective

Performance Standard

Acceptable Quality Level
Incentive or Disinvites % Deduction from monthly invoice for not meeting Performance Standards

1. The Contractor shall provide personnel who are physically capable of performing work in conditions of extreme temperatures (heat or cold), high humidity, precipitation, and blowing sand and dust. Aspects of this requirement involve lifting heavy objects in excess of 40lbs.

PWS Para 1.22.2.4.

All employees shall be physically capable of working in extreme conditions (to include lifting heavy objects in excess of 40 pounds).
Zero Deviation from performance standards identified in PWS 1.22.4.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

2. The contractor shall report all accidents.

PWS Para 1.9.2.

The Contractor shall report accidents immediately, but not later than sixty (60) minutes following the accident, to the Fort Bragg Range Control Room (910-432-1161) and KO during duty hours or to the Range Control Room after duty hours.
Zero Deviation from performance standards identified in PWS 1.9.2.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

3. Contractor will monitor and inspect ranges and training facilities to ensure and enforce compliance with FB Reg. 350-6.

PWS Para 5.1.1.3.

All ranges and training areas shall be constantly monitored and inspected for compliance with 350-6. Contractor must ensure each range or facility is inspected during or after use
Zero Deviation from performance standards identified in PWS 5.1.1.3.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

4. Contractor shall ensure all pre-firing and post-firing actions required by regulation have been completed. All targets and target frames are replaced and restocked from the warehouse when necessary. Simple target frames are required to be built from provided materials when needed.

PWS Para 5.1.1.8.

All pre-firing and post firing actions required by regulation shall be completed. All Target and target frames must be rebuilt as needed to ensure ranges are ready for the next occupying unit.
Zero Deviation from performance standards identified in PWS 5.1.1.8.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

5. The contractor shall insure that no property has been removed from the training facility or range.

PWS Para 5.1.1.10.

Contract personnel inspect each range or facility using the hand receipt for that facility/range and insure all property is accounted for Contractor must ensure each range or facility is inspected during or after use.

Zero Deviation from performance standards identified in PWS 5.1.1.10.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

6. Contractor shall ensure all debris has been removed from the range and adjacent training sites.

PWS Para 5.1.1.14.

Debris shall be removed before and after the immediate use of the ranges.
Zero Deviation from performance standards identified in PWS 5.1.1.14.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

7. Contractor shall insure ranges/facilities are not modified.

PWS Para 5.1.1.16.

Contractors shall insure that units do not modify ranges or facilities from their intended use IAW FB Reg. 350-6.

Contractor must ensure each range or facility is inspected during or after use.

Zero Deviation from performance standards identified in PWS 5.1.1.16.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

8. The contractor’s employees shall comply with all applicable range checklists to include, but not limited to, the checklist on clearing, inspecting, and setting up ranges. All checklists are prepared and disseminated to using units by Range Control. Contractor will collect completed checklists and each clearing unit with a customer survey sheet. Completed checklists and customer survey sheets will be turned in to Range operations on a daily basis.

PWS Para 5.1.1.20.

Checklists shall be followed by contractor's employees. Contractor will collect the checklist from using units along with a customer survey sheet and turn them in to Range Control daily.
Zero Deviation from performance standards identified in PWS 5.1.1.20.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

9. The contractor’s employees shall check all range structures, training equipment, and facilities for needed maintenance and basic cleanliness in order to restore range resources to their natural state prior to departing the area during clearing procedures.

PWS Para 5.1.2.1.

Clearing shall be completed within 30 minutes of range inspector notification that range is ready to be cleared.
Zero Deviation from performance standards identified in PWS 5.1.2.1.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

10. The contractor’s employees shall conduct range maintenance to include weed eating mowing grass using both mechanical/manual methods and power equipment, to include equipment maintenance, target construction and various other tasks necessary to facilitate unit training.

PWS Para 5.1.3.5.

Contractors shall perform maintenance in a professional and timely manner to ensure no unnecessary range downtime and unit training has no interference or delays.
Zero Deviation from performance standards identified in PWS 5.1.3.5.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

11. The contractor’s employees shall coordinate daily with the Live Fire Range Manager on what tasks need to be accomplished in order to facilitate unit training, coordinate between teams from other ranges when necessary to cover shifts when needed, and inform their perspective Live Fire Range Manager of assigned range of any and all changes to schedule that will exclude them of daily duties. (i.e. covering down for another facilitator, sick day….).

PWS Para 5.1.3.7.

Contractors shall conduct the necessary coordination to ensure all range and unit training requirements are meet with no delays.

Contractor shall conduct coordination with range manger, Contractor Lead, and other contractor employees to ensure shift coverage to ensure range maintenance and unit training are successful.

Zero Deviation from performance standards identified in PWS 5.1.3.7.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

12. The contractor’s employee shall clean and service target systems and positions to include trench lines, MOUT facilities, and SACON buildings as needed determined by the Live Fire Range Manager.

PWS Para 5.1.3.10.

Contractors shall clean and service all required targetry to ensure range is safe and operational, and targetry is operational.
Zero Deviation from performance standards identified in PWS 5.1.3.10.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

13. The contractor’s employee shall operate a hand held remote device or a computer to control target systems used for training under the guidance of unit personnel or the Live Fire Range Manager and traverse uneven train wearing PPE to facilitate multiple iterations of maneuver training while traveling with the unit.

PWS Para 5.1.3.11.

Contractor shall operate and control target systems under the guidance of the training unit or range manager while wearing 100% of required PPE to ensure unit training success.
Zero Deviation from performance standards identified in PWS 5.1.3.11.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

14. Conduct up keep of range facilities to include towers, AAR buildings and break areas.

PWS 5.1.3.14.

Contractors shall clean and service all required facilities.
Zero Deviation from performance standards identified in PWS 5.1.3.14.
Contractor compliance rate shall be utilized as objective evidence of contract compliance and documented into the CPAR System.

Note: Government surveillance of contractor performance is not limited to the Performance Objectives as outlined in this PRS. The Government reserves the right to conduct compliance surveillance of any contractual requirement of this acquisition.