Questions and Answers.pdf
PDF 106 KB Posted
- Attached to
- Hensley Lake Vegetation Reduction
- Solicitation number
- W9123825Q0008
About this file
This is a Questions and Answers document for a vegetation reduction services contract at Hidden Dam, Hensley Lake in Raymond, California. The document clarifies that services are required twice per year, with pricing required for both the base year and four option years. The lowest-priced offeror for the total contract value will receive the award, and option years must be priced as binding terms that the government can exercise unilaterally.
Key details include: the incumbent contractor is CLASS CONTRACTING LLC; Service Contract Act Wage Determination 11210 applies with an $18.20/hr minimum labor rate plus $5.36/hr health and welfare benefits; payments are made within 30 days of accepted invoices; only price will be evaluated for award per Clause 52.212-2; and offerors must submit signed proposals to Antonina.Beal@usace.army.mil and Raymond.R.Greenheck@usace.army.mil. The Performance Work Statement sections on Pre-Work Meeting, Contractor's Quality Control Plan, and Security contain additional required certifications and licenses beyond the General B and C-12 License mentioned by a prospective bidder.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment D Maps.pdf | ||
| W9123825Q0008 Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A
Q1. We currently hold a General B and C-12 License. Would we need additional licenses or certifications for this project?
A1. See Performance Work Statement section Pre-Work Meeting for the list of required items as well as section Contractor’s Quality Control Plan (QCP), and Security section. No other licenses and certificates are required for this project.
Q2. Is there a current contractor for this project?
A2. Yes
Q3. Is there an engineer’s projected estimate for this project?
A3. No.
Q4. Is service per week, month, year?
A4. There are two (2) services per year. See the Performance Work Statement (PWS) in the solicitation for details.
Q5. Do you need a total breakdown for each year of service or just the first year of service?
A5. Yes, breakdown for the base year and four (4) option years. Award will be made to the lowest priced offeror for the total contract value (base and all option years). Each option year is to be priced, and these prices are binding. The Government will exercise option years unilaterally as needed. If you don’t price each CLIN your offer will be deemed non-responsive and not eligible for award.
Q6. did not see a list of items to submit, I have previously submitted bid packages with the quote amount and work plan. Was there a specific format or layout that you prefer?
A6. See Clause 52.212-2 for items to include with your quote. In this case it is just the price we will be evaluating for award, no other items are needed with your quote. Please read all page of solicitation, acknowledge every amendment issued for the solicitation, and solicitation by signing, and submit together with your offer to Antonina.Beal@usace.army.mil and Raymond.R.Greenheck@usace.army.mil
Q7. We plan on using Wage Determination of 11210 Labor, Grounds Maintenance on page 68 of $18.20/ hr as a minimum labor rate plus health and welfare benefits of $5.36/ hr. I do not see and want to confirm that there is not a prevailing wage requirement beyond what is published in the Solicitation Wage Determinations per the executive order.
A7. Service Contract Act Wage Determinations issued with solicitation is what is required and nothing else is beyond that.
Q8. Can we get the total cost of the maintenance for the last years and the name of the landscape Company who did the work?
A8. The previous contractor is CLASS CONTRACTING LLC. We will not share the total cost of the maintenance for the last years.
Q9. When can we expect to be paid after work is complete?
A9. See Performance Work Statement sections Payment and Invoices and Contract Payments.
Payments are made within 30 days of accepted invoices.