W9123818R0025

Section 00 00 00 - Procurement and Contracting Requirements

STANDARDS OF CONDUCT

STANDARDS OF CONDUCT

Per FAR 3.101, 15.201(f) and 15.303(c), to preserve procurement integrity, all contacts shall go to either the Contracting Officer and/or Contract Specialist. Contacts to others regarding this solicitation may result in the disqualification of the offeror or cancellation of the solicitation. Disqualification will be the result of any communication that explicitly or implicitly, intentionally or unintentionally gives one prospective offeror a competitive advantage or the mere appearance of a competitive advantage over that of another

Section 00 01 10 - Table of Contents

Exhibit/Attachment Table of Contents

DOCUMENT TYPE
DESCRIPTION
PAGES
DATE
Attachment 01
Kings River Levee Breach Repair PLANS
5
28-MAR-2018
Attachment 02
Kings River Specifications
292
28-MAR-2018
Attachment 03
Davis Bacon Wage Determination
79
01-JUN-2018

Section 00 10 00 - Solicitation

SCHEDULE OF ITEMS

Task Order 0331: Kings River

Line Item No.
Description
Quantity
Unit of Measure
Unit Price
Total Price
0001
Mobilization and Demobilization
1
JOB
$ -
$ -
0002
SWPPP Development and Implementation
1
JOB
$ -
$ -

SubTotal

Line Item No.
Description
Quantity
Unit of Measure
Unit Price
Total Price
0005
Tree Removal
2
trees
$ -
$ -
0010
Excavate Existing Fill
1,840
CY
$ -
$ -
0014
Clearing, Stripping and Grubbing
292
SY
$ -
$ -
0016
Excavate Loose/Wet Material (Optional Item)
2,000
CY
$ -
$ -
0017
Dispose of Loose/Wet Material (Optional Item)
2,000
CY
$ -
$ -
0018
Dispose of Existing Fill
1,840
CY
$ -
$ -
0026
Levee Fill - Material, Haul, Place, and Compact (Stockpile)
1,840
CY
$ -
$ -
0027
Levee Fill - Material, Haul, Place, and Compact (Optional, Commercial)
1,840
CY
$ -
$ -
0028
Levee Fill - Material, Haul, Place, and Compact (Optional, if Placing Bridging Layer)
1,815
CY
$ -
$ -
0029
Minus 3/4-In Caltrans Class 2 Aggregate Base Course for Exploration Keyway - Material, Haul, Place and Compact (Optional)
8
CY
$ -
$ -
0030
Minus 3/4-In Caltrans Class 2 Aggregate Base Course for Levee Crown - Material, Haul, Place and Compact
62
CY
$ -
$ -
0032
Geotextile Fabric for Bridging Layer (Optional)
107
SY
$ -
$ -
0034
3" to 6" Rock for Bridging Layer - Material, Haul, Place and Compact (Optional)
14
CY
$ -
$ -
0038
Hydroseeding
544
SY
$ -
$ -
0042
Clearing, Stripping and Grubbing - Disposal of Material
1
JOB
$ -
$ -
0043
Excavate Additional Fill (Optional)
920
CY
$ -
$ -

SubTotal

TOTAL (BASE)

TOTAL (BASE + OPTIONS)

Section 00 21 00 - Instructions

CLAUSES INCORPORATED BY REFERENCE

52.204-7
System for Award Management
OCT 2016
52.204-16
Commercial and Government Entity Code Reporting
JUL 2016
52.204-18
Commercial and Government Entity Code Maintenance
JUL 2016
52.204-22
Alternative Line Item Proposal
JAN 2017
52.215-1
Instructions to Offerors--Competitive Acquisition
JAN 2017
52.215-16
Facilities Capital Cost of Money
JUN 2003
52.215-20
Requirements for Certified Cost or Pricing Data or Information Other Than Certified Cost or Pricing Data
OCT 2010
52.222-5
Construction Wage Rate Requirements--Secondary Site of the Work
MAY 2014
52.223-1
Biobased Product Certification
MAY 2012
52.225-10
Notice of Buy American Requirement--Construction Materials
MAY 2014
52.236-28
Preparation of Proposals--Construction
OCT 1997
252.204-7008
Compliance With Safeguarding Covered Defense Information Controls
OCT 2016
252.215-7008
Only One Offer
OCT 2013
252.225-7031
Secondary Arab Boycott Of Israel
JUN 2005

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm-fixed price contract resulting from this solicitation.

(End of provision)

52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. As used in this clause--

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is--

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4) such as agricultural products and petroleum products.

Component means an article, material, or supply incorporated directly into a construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means--

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if--

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

Foreign construction material means a construction material other than a domestic construction material.

United States means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1 Foreign construction material.... ........... ___ ........ ....... ………. ___ ................ ........ ___ Domestic construction material... ........ ___ ............... .............. ___ .................. ...... ___ Item 2 Foreign construction material.... ......... ___ ............. ........ ……. ___ ............... ......... ___ Domestic construction material... ....... ___ .................. ............. ___ ................. ....... ___ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).

List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.

Include other applicable supporting information.

(End of clause)

52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)

(a) “Irrevocable letter of credit” (ILC), as used in this clause, means a written commitment by a federally insured financial institution to pay all or part of a stated amount of money, until the expiration date of the letter, upon presentation by the Government (the beneficiary) of a written demand therefor. Neither the financial institution nor the offeror/Contractor can revoke or condition the letter of credit.

(b) If the offeror intends to use an ILC in lieu of a bid bond, or to secure other types of bonds such as performance and payment bonds, the letter of credit and letter of confirmation formats in paragraphs (e) and (f) of this clause shall be used.

(c) The letter of credit shall be irrevocable, shall require presentation of no document other than a written demand and the ILC (including confirming letter, if any), shall be issued/confirmed by an acceptable federally insured financial institution as provided in paragraph (d) of this clause, and--

(1) If used as a bid guarantee, the ILC shall expire no earlier than 60 days after the close of the bid acceptance period;

(2) If used as an alternative to corporate or individual sureties as security for a performance or payment bond, the offeror/Contractor may submit an ILC with an initial expiration date estimated to cover the entire period for which financial security is required or may submit an ILC with an initial expiration date that is a minimum period of one year from the date of issuance. The ILC shall provide that, unless the issuer provides the beneficiary written notice of non-renewal at least 60 days in advance of the current expiration date, the ILC is automatically extended without amendment for one year from the expiration date, or any future expiration date, until the period of required coverage is completed and the Contracting Officer provides the financial institution with a written statement waiving the right to payment. The period of required coverage shall be:

(i) For contracts subject to 40 U.S.C. chapter 31, subchapter III, Bonds, the later of--

(A) One year following the expected date of final payment;

(B) For performance bonds only, until completion of any warranty period; or

(C) For payment bonds only, until resolution of all claims filed against the payment bond during the one-year period following final payment.

(ii) For contracts not subject to the Miller Act, the later of--

(A) 90 days following final payment; or

(B) For performance bonds only, until completion of any warranty period.

(d)(1) Only federally insured financial institutions rated investment grade by a commercial rating service shall issue or confirm the ILC.

(2) Unless the financial institution issuing the ILC had letter of credit business of at least $25 million in the past year, ILCs over $5 million must be confirmed by another acceptable financial institution that had letter of credit business of at least $25 million in the past year.

(3) The Offeror/Contractor shall provide the Contracting Officer a credit rating that indicates the financial institutions have the required credit rating as of the date of issuance of the ILC.

(4) The current rating for a financial institution is available through any of the following rating services registered with the U.S. Securities and Exchange Commission (SEC) as a Nationally Recognized Statistical Rating Organization (NRSRO). NRSRO's can be located at the Web site http://www.sec.gov/answers/nrsro.htm maintained by the SEC.

(e) The following format shall be used by the issuing financial institution to create an ILC:

[Issuing Financial Institution's Letterhead or Name and Address]

Issue Date _ ___

IRREVOCABLE LETTER OF CREDIT NO. ___

Account party's name ___ _

Account party's address ___ _

For Solicitation No. ___ _(for reference only)

TO: [ ___ U.S. Government agency]

[ ___ U.S. Government agency's address]

1. We hereby establish this irrevocable and transferable Letter of Credit in your favor for one or more drawings up to United States $ ___ . This Letter of Credit is payable at [issuing financial institution's and, if any, confirming financial institution's] office at [ ___ issuing financial institution's address and, if any, confirming financial institution's address] and expires with our close of business on ___ , or any automatically extended expiration date.

2. We hereby undertake to honor your or the transferee's sight draft(s) drawn on the issuing or, if any, the confirming financial institution, for all or any part of this credit if presented with this Letter of Credit and confirmation, if any, at the office specified in paragraph 1 of this Letter of Credit on or before the expiration date or any automatically extended expiration date.

3. [This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.] It is a condition of this Letter of Credit that it is deemed to be automatically extended without amendment for one year from the expiration date hereof, or any future expiration date, unless at least 60 days prior to any expiration date, we notify you or the transferee by registered mail, or other receipted means of delivery, that we elect not to consider this Letter of Credit renewed for any such additional period. At the time we notify you, we also agree to notify the account party (and confirming financial institution, if any) by the same means of delivery.

4. This Letter of Credit is transferable. Transfers and assignments of proceeds are to be effected without charge to either the beneficiary or the transferee/assignee of proceeds. Such transfer or assignment shall be only at the written direction of the Government (the beneficiary) in a form satisfactory to the issuing financial institution and the confirming financial institution, if any.

5. This Letter of Credit is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International Chamber of Commerce Publication No. ___ -- (Insert version in effect at the time of ILC issuance, e.g., ``Publication 600, 2006 edition'') and to the extent not inconsistent therewith, to the laws of ___ --[State of confirming financial institution, if any, otherwise State of issuing financial institution].

6. If this credit expires during an interruption of business of this financial institution as described in Article 17 of the UCP, the financial institution specifically agrees to effect payment if this credit is drawn against within 30 days after the resumption of our business.

Sincerely, [ ___ Issuing financial institution]

(f) The following format shall be used by the financial institution to confirm an ILC:

___ [Confirming Financial Institution's Letterhead or Name and Address]

(Date) ___

Our Letter of Credit Advice Number ___

Beneficiary: ___ [U.S. Government agency]

Issuing Financial Institution: ___

Issuing Financial Institution's LC No.: ___

Gentlemen:

1. We hereby confirm the above indicated Letter of Credit, the original of which is attached, issued by ___ [name of issuing financial institution] for drawings of up to United States dollars ___ _/U.S. $ ___ and expiring with our close of business on ___ [the expiration date], or any automatically extended expiration date.

2. Draft(s) drawn under the Letter of Credit and this Confirmation are payable at our office located at ___ _.

3. We hereby undertake to honor sight draft(s) drawn under and presented with the Letter of Credit and this Confirmation at our offices as specified herein.

4. [This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.] It is a condition of this confirmation that it be deemed automatically extended without amendment for one year from the expiration date hereof, or any automatically extended expiration date, unless:

(a) At least 60 days prior to any such expiration date, we shall notify the Contracting Officer, or the transferee and the issuing financial institution, by registered mail or other receipted means of delivery, that we elect not to consider this confirmation extended for any such additional period; or

(b) The issuing financial institution shall have exercised its right to notify you or the transferee, the account party, and ourselves, of its election not to extend the expiration date of the Letter of Credit.

5. This confirmation is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International Chamber of Commerce Publication No. ___ -- (Insert version in effect at the time of ILC issuance, e.g., ``Publication 600, 2006 edition'') and to the extent not inconsistent therewith, to the laws of ___ --[State of confirming financial institution].

6. If this confirmation expires during an interruption of business of this financial institution as described in Article 17 of the UCP, we specifically agree to effect payment if this credit is drawn against within 30 days after the resumption of our business.

Sincerely, [Confirming financial institution]

(g) The following format shall be used by the Contracting Officer for a sight draft to draw on the Letter of Credit:

SIGHT DRAFT

[City, State]

(Date) ___

[Name and address of financial institution]

Pay to the order of ___ [Beneficiary Agency] ___ the sum of United States ___ This draft is drawn under Irrevocable Letter of Credit No. ___

___ [Beneficiary Agency]

By: ___

(End of clause)

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. Army Corps of Engineers, Sacramento District ATTN: Construction Contracting Officer, Room 878 1325 J Street Sacramento, California 95814

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Rick Hoelzel, 559-237-5567 ext. 130 Keith Seligman, 559-237-5567 ext. 120

See Section 00 00 00 – Standards of Conduct.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

N/A

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Department of Defense FAR Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of provision)

Section 00 21 16 - Instructions to Proposers

INSTRUCTIONS FOR PROPOSAL PREP

INSTRUCTIONS FOR PROPOSAL PREP

The following documents must be returned with your quote, bid, or offer:

--The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address.

--Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment.

Note: If the SF 1442 and/or the pricing schedule was changed by amendment, be sure to use the amended pages when submitting your quote, bid, or offer.

--The completed CLIN Schedule with your proposed contract line item prices inserted in the appropriate spaces. Prices must be proposed for all contract line items and priced sub-line items. Unit prices are to be extended to the actual “dollar and cents” amounts (i.e., to two decimal places). Do not round off extended prices to the nearest dollar. Check your pricing submission very carefully for mathematical and clerical errors prior to submission.

--Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00 45 00).

--Your Offer Guarantee (e.g., Standard Form 24, “Bid Bond”)

INQUIRIES:

Prospective offerors should submit inquiries related to this solicitation in accordance with the following (collect calls will not be accepted):

a. For information related to amendments, and the dates set for receipt of proposals, please check http://www.fedbizopps.gov

b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

1. To submit and review bid inquiry items, offerors will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the QUICK ADD link. Select agency as USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click continue. Fill in all required information and click Add User.

2. From this page you may view all bidder inquiries or add an inquiry.

3. Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.

4. The Solicitation Number is : W91238-18-R-0025 The Bidder Inquiry Key is: B8H88T-2ET76C

c. The Bidder Inquiry System will be unavailable for new inquiries 10 days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

g. The point of contact for this solicitation is:

Contract Specialist: Contract Specialist EMAIL: Greg.L.Treible@usace.army.mil

DIRECTIONS FOR SUBMITTING OFFERS:

Envelopes/packages containing offers must be sealed, marked and addressed as follows:

MARK ENVELOPES/PACKAGES:

Solicitation No. W9123818R0025 “PL84-99 Kings River Levee Breach Repair”

ADDRESS ENVELOPES/PACKAGES TO:

Department of the Army U.S. Army Engineer District, Sacramento ATTN: Contracting Division 1325 J Street Sacramento CA 95814-2922

SPECIAL INSTRUCTION PERTAINING TO HAND-CARRIED OFFERS:

Hand-carried offers must be delivered to: The Building Lobby at 1325 J Street, Sacramento, CA.

Due to security precautions, offerors may no longer hand-carry their offers directly to Contracting Division. Offers may NOT be turned-in at the Security Desk or left unattended elsewhere in the Lobby. Additionally, you are advised that there is no public parking in the Building.

The contracting representative will be in the Building Lobby 20 minutes prior to the closing time to accept hand-carried offers.

Offerors who desire to hand-deliver their offers at an earlier time must coordinate with the contract specialist in advance in order to arrange to be met in the Building Lobby by Contracting Division personnel.

Please ensure that all courier and delivery personnel are aware of these procedures.

CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY:

In order to determine a contractor's responsibility for purposes of contract award in accordance with FAR Part 9, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work (e.g., Preaward Survey). All offerors will complete and return the Preaward Survey as part of the Price/Cost proposal. Failure to submit the Preaward Survey in conjunction with the price proposal will not of itself render the offer unacceptable.

An affirmative determination of contractor responsibility will be completed in accordance with FAR 9.104-1.

If the contractor or subcontractor does not already have sufficient resources demonstrated in the completed Preaward Survey, acceptable evidence of "the ability to obtain" the required, adequate resources (all of the resources discussed in FAR 9.104-1) normally consists of a commitment or explicit arrangement that will be in existence at the time of contract award to rent, purchase or otherwise acquire the needed facilities, equipment, other resources, or personnel.

The Preaward Survey as a tool used by the Government in determining responsibility of the offeror is submitted as part of the Price/Cost proposal and is separate from any technical proposal's response to the technical evaluation criteria which may be required in this solicitation. Some of the information required from the offeror for completion of the Preaward Survey and the technical proposal may be duplicative but it is necessary that the information be provided in full in both places and that the Price/Cost proposal and the Technical proposal be separate documents. DO NOT state, for example, in the technical proposal, "See Price/Cost proposal for past performance information".

AVAILABILITY OF CORPS OF ENGINEERS PUBLICATIONS DESCRIPTIONS:

a. The internet URL for Corps of Engineers publications is:

http://www.publications.usace.army.mil/

b. Construction Criteria Base (CCB). The Construction Criteria Base (CCB) system available through the National Institute of Building Sciences includes copies of Corps of Engineers methods and specifications. Information about the CCB can be obtained from:

http://www.wbdg.org/ccb/ccb.php

FACSIMILE BIDS/OFFERS:

Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.

PERFORMANCE AND PAYMENT BONDS:

The bidder/offeror whose bid/offer is accepted will, within the time established in the contract, furnish performance and payment bonds in accordance with FAR 52.228-15.

INDIVIDUAL SURETIES IN SUPPORT OF BID BONDS:

Bidders/offerors utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the bid itself (see clause titled "Pledges of Assets," FAR 52.228-11).

Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate.

ACCEPTANCE OF OFFERS:

A written award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.

System for Award Management (SAM) Registration:

It is a requirement that any and all contractors that intend to do business with the government must be registered in the System for Award Management (SAM) database. No contract may be awarded by the government to any contractor who is not registered in SAM. If your company is not registered in SAM, you must register in order to be eligible for any government award.

The following link provides access to the SAM website:

https://www.sam.gov/portal/public/SAM/

If you have difficulties with or questions regarding the SAM registration, the following link has been set up by the Defense Logistics Agency (DLA) to assist contractors registering for CAGE codes for enrollment and navigation within SAM:

https://www.logisticsinformationservice.dla.mil/CAGETier3/

Section 00 22 00 - Supplementary Instructions

INSTRUCTIONS TO OFFERORS

INSTRUCTION TO OFFERORS

1. OVERVIEW

This is a "Best Value" solicitation for the construction of levee improvements the P.L. 84-99 Kings River Levee Breach Repair Sites along the Sacramento River, Kings County, CA. The Contracting Officer will award a firm fixed-price contract to that responsible Offeror whom the Source Selection Authority determined has the lowest evaluated price proposal and meets or exceeds the acceptability standards for non-cost factors as described in Section 2.2 below.

2. BASIS OF AWARD

2.1. ELIGIBILITY FOR CONTRACT AWARD

In accordance with the requirements of Part 9 of the Federal Acquisition Regulation (FAR), no contract shall be entered into unless the Contracting Officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award shall be made unless the Contracting Officer makes an affirmative determination of responsibility. To be determined responsible, a prospective contractor must meet the general standards in FAR Part 9 and any special standards set forth in the solicitation.

2.2. SOURCE SELECTION USING THE LOWEST PRICE TECHNICALLY ACCEPTABLE (LPTA) PROCESS

Lowest Price Technically Acceptable is a process used in competitive negotiated contracting where the best value is expected to result from selection of the technically acceptable proposal with the lowest evaluated price. See FAR 15.101-2.

a. After the due date/time for receipt of proposals, the Government will open proposals to identify the lowest priced offer.

b. Beginning with the lowest priced offer, the Government will evaluate the offeror’s technical proposal against the evaluation criteria contained herein in order to determine the proposal’s technical acceptability.

c. This process will continue until a technically acceptable proposal is identified. Once a technically acceptable proposal is identified, proposal evaluation will cease; and the Government will proceed to evaluate the technical acceptable offeror’s price proposal and upon the contracting officer’s affirmative determination of responsibility, the Government will proceed to award the contract.

2.3. EVALUATION OF THE PRICE PROPOSAL

a. Price to the Government will be evaluated and considered but will not be scored or combined with other aspects of the proposal evaluation. The proposed price will be analyzed for reasonableness. It may also be analyzed to determine whether it reflects a clear understanding of the requirements; and is consistent with the offeror’s Technical Proposal. Additionally, to the extent proposal evaluation is necessary, offers will be analyzed for unbalanced pricing.

b. The Price Evaluation Adjustment for Small Disadvantaged Businesses will not apply to this procurement as it is currently suspended for the Department of Defense.

c. Information required to be submitted in the Price Proposal volume in addition to the executed SF 1442 with acknowledgement of amendments and the completed CLIN schedule will be used to determine the offeror’s eligibility for contract award in accordance with paragraph 2.1 above (for example, the work breakdown structure, the offeror’s representations and certifications; the offer guarantee; and the offeror’s pre-award survey information). The Government may enter into exchanges with offerors about such information without it constituting discussions, subject to applicable FAR limitations, including FAR 15.306, Exchanges with offerors after receipt of proposals.

2.4. TECHNICAL EVALUATION FACTORS

The evaluation factors correlate directly to the main organizational tabs identified in the proposal submission instructions.

Technical Proposal

(1) Factor 1: Experience and Capability

(2) Factor 2: Past Performance

(3) Factor 3: Management and Technical Approach

2.5. GENERAL TECHNICAL EVALUATION CRITERIA

a. This Solicitation sets forth requirements for the proposals which include certain submissions and formatting. The offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation. Failure to comply with the formatting and/or submission requirements may support a contracting officer’s decision to reject a non-conforming proposal. However, in accordance with FAR 52.215-1, the Government may waive informalities and minor irregularities in proposals within reasonable discretion.

b. Technical proposals which do not provide the specified information in the specified location in accordance with the submission instructions may be considered Unacceptable. An offeror has the obligation to affirmatively demonstrate that its proposal will meet the government’s needs, where required to do so. The Government is under no obligation to search for information that is not in the specified location.

c. Any prescribed page and formatting limitations will be strictly adhered to and enforced by the Government. The Government will not evaluate any excess information resulting from the offeror’s failure to comply with the submission instructions. Examples: If an offeror were to submit three pages in response to an item with a two page limitation, the information on the first two pages would be evaluated but the information on the third page would not be evaluated. If an offeror were to submit a fold-out sheet (e.g. 11”x17”) in response to a one-page limitation where fold-out sheets were not authorized, only the information that could reasonably have been submitted on one 8-1/2 x 11 inch sheet would be evaluated. If an offeror were to submit three 8-1/2 x 11 inch pages in response to a one not-to-exceed 11 x 17 inch page limitation, only the information that could reasonably have been submitted on one 11 x 17 inch sheet would be evaluated. If an offeror submitted alternates that were not requested (e.g., key personnel), the information will not be evaluated.

d. A “deficiency” is a material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.

e. The Government cannot make award based on a deficient offer. Therefore, a rating of “Unacceptable” under any factor will render the proposal ineligible for award, unless the Government elects to enter into discussions with that offeror and all deficiencies are remedied in a revised proposal.

3 GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS.

3.1 GENERAL INSTRUCTIONS.

3.1.1 Media, Page Size, Margins, Fonts, and Page Limitations.

Submit only the hard-copy paper documents and electronic files specifically authorized elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. Do not include links to information on websites in lieu of incorporating the information physically into the proposal. Except where another size is specifically authorized for a specific submission, use only 8 1/2” x 11” paper. Use at least 1 inch margins, which may include headers and footers. Do not justify the right margin. Ensure that all text and graphics are clearly legible. Do not use a font size smaller than 10, unusual font styles such as script, or condensed fonts. For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, a foldout sheet will count as one page. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are excluded from page limitations.

3.1.2 Proposal Binding.

The preferred method for assembling proposals is a method that enables the rapid insertion or deletion of pages such as three ring binders. Ensure recommended capacity is not exceeded and that pages turn freely. Do not use spring clamps, spiral binding systems, or heat binding systems.

3.1.3 Conditioning of Offer.

Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal volumes. Inclusion of any standard company terms and conditions that conflict with the terms and conditions of the solicitation may result in a determination that the offer is unacceptable and thus ineligible for award. Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the offer; see “Inquiries”, located in Section 00 21 16, for points of contact. Notwithstanding the above, the offeror must clearly describe in the proposal cover sheet submitted with the volume any exceptions, within the offer, to the contractual and/or technical terms and conditions of the solicitation.

3.1.4 Restrictions on Offeror-Provided Information.

“Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can nonetheless be provided to the Government as part of the offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must clearly mark the information in accordance with FAR 52.215-1, “Instructions to Offeror – Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”. Files shall not contain classified data.

3.2 REQUIREMENT FOR SEPARATE PRICE AND TECHNICAL PROPOSAL VOLUMES.

Each offeror must submit both a “price proposal” volume and a “technical proposal” volume. The price proposal includes the signed offer and the offeror’s proposed prices. The technical proposal includes all required information relating to the “non-cost” evaluation factors. The two volumes must be submitted as separate, physically distinct volumes. Both volumes must be received at the location shown in Block 8 of Standard Form 1442, not later than the date and time specified in Block 13 of Standard Form 1442. The information in the two volumes is evaluated separately and independently. Therefore, all information intended by the offeror to be evaluated as part of the price proposal must be submitted as part of the price proposal. All information intended by the offeror to be evaluated as part of the technical proposal must be submitted as part of the technical proposal. Do not merely cross-reference similar material between the technical and price proposals. Information in the price proposal will not be considered in the technical evaluation, and vice versa.

3.2.1 Marking of Proposal Volumes.

Mark each volume as either the “Price Proposal” or the “Technical Proposal”. Additionally, mark the outside front cover of each volume with the project title and location, solicitation number, name and address of the offeror, and volume copy number. (Markings which identify the offeror are not required on either the back cover or on the spine/binding.)

3.2.2 Tabbing of Proposal Volumes.

Offers are to be formatted and tabbed in accordance with the instructions that follow for each proposal volume.

3.2.3 Table of Contents.

Include a table of contents for each proposal volume.

4 PRICE PROPOSAL VOLUME.

4.1 NUMBER OF SETS OF THE PRICE PROPOSAL.

Submit the original (hard copy) of the price proposal volume. Also, submit an electronic copy on a Compact Disc (CD).

4.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE PRICE PROPOSAL.

Use only 8-1/2” x 11” pages. There are no page limits for the price proposal; however, limit responses to required information. Excess information will not be evaluated. Organize your price proposal as indicated below.

PRICE PROPOSAL VOLUME

TAB CONTENTS OF THE PRICE PROPOSAL

1 Proposal Cover Sheet

2 SF 1442; Acknowledgement of Amendments; (Joint Venture Agreement (if applicable))

3 CLIN Schedule

4 Representations and Certifications

5 Offer Guarantee

6 Pre-Award Survey Information

4.3 DETAILED SUBMISSION REQUIREMENTS FOR THE PRICE PROPOSAL.

Tab 1 of the Price Proposal: Proposal Cover Sheet.

The proposal cover sheet is required by FAR 52.215-1 (c)(2). This provision, titled “Instructions to Offerors – Competitive Acquisition” is provided in full text in Section 00 21 00. The format and content for the proposal cover sheet follows:

PROPOSAL COVER SHEET

1. Solicitation Number:

2. The name, address, DUNS number, telephone numbers and email addresses of the offeror.

3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the Solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item.

4. Names, titles, email addresses, and telephone numbers of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation:

5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority.

(End of Proposal Cover Sheet)

Tab 2 of the Price Proposal: SF 1442; Acknowledgement of Amendments; Joint Venture Agreement.

The Standard Form (SF) 1442 must be completed by the offeror and duly executed with an original signature by the official(s) identified in the proposal cover sheet as authorized to bind the offeror in accordance with FAR 4.102, which includes specific instructions pertaining to individuals, partnerships, corporations, Joint Venture participants, and agents. Include the offeror’s DUNS number in block 14 of the SF 1442, along with the offeror’s address. All amendments must be acknowledged in accordance with the instructions on the Standard Form 30, Amendment. If the offeror is a Joint Venture (JV), include a copy of the JV agreement and indicate its status. (Note: It is preferred, but not required, that you use a document protector in lieu of punching holes in the original SF 1442.)

Tab 3 of the Price Proposal: CLIN Schedule.

Submit the completed CLIN Schedule with the offeror’s proposed contract prices inserted in the appropriate spaces. Prices must be proposed for all contract line items. Unit prices must be extended to the actual “dollar and cents” amounts (i.e., to two decimal places). Do not round off the extended prices to the nearest dollar. Check your pricing submission very carefully for mathematical and clerical errors prior to submission. Any qualification of pricing may render the proposal unacceptable and therefore not eligible for award. (Note: It is preferred, but not required, that you use a document protector in lieu of punching holes in the completed “original” CLIN schedule.)

Tab 4 of the Price Proposal: Representations and Certifications.

The offeror must have electronically completed the annual representations and certifications on the System for Award Management (SAM) website in accordance with FAR 52.204-8. The offeror is responsible for ensuring that these on-line Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that they are kept current, accurate and complete. Additionally, the offeror must also complete and return the “Representations, Certifications, and Other Statements of Offerors” included in Section 00 45 00 of the solicitation. If the offeror is a Joint Venture, all participants must separately complete annual representations and certifications and Section 00 45 00.

Tab 5 of the Price Proposal: Offer Guarantee.

All offerors must submit a Offer guarantee (e.g., Standard Form 24, Bid Bond) which complies with the requirements of FAR 28.101 Bid Guarantees, and any Defense and Army supplements thereto.

Tab 6 of the Price Proposal: Pre-Award Survey Information.

a. The Contracting Officer is required to make an affirmative pre-award determination of the prospective contractor’s responsibility in accordance with the mandatory requirements of Part 9 of the Federal Acquisition Regulation (FAR) and its supplements. The Contracting Officer must have sufficient information available to determine that a prospective contractor meets these minimum standards. Therefore, the offeror is requested to provide the pre-award survey information described below with its price proposal:

(1) The completed Construction Contractor Data Form with Supplemental Schedules A-C (see format which follows). If the offeror is a large multi-segmented business concerns, the data provided on the supplemental schedules may be limited to information that directly pertains to the specific segment of the business concern (e.g., the division, group, unit, etc.) proposed to perform work under the prospective contract with its own work force. If the offer is being submitted by a Joint Venture, submit a separate form for each Joint Venture participant. The offeror may submit pre-award survey information in another format, provided that the information furnished is substantially the same as that which would be furnished on the Construction Contractor Data Form and its supplemental schedules.

(2) Current financial statements. If the financial statement is more than 60 days old, submit a certificate stating that the firm's financial condition is substantially the same, or, if not the same, state the changes that have taken place. If a Joint Venture, provide this information for each participant in the Joint Venture.

(3) Banking information. Provide letters from banks or other financial institutions with which the contractor conducts business. The letters should contain information about your firm's accounts, loans, lines of credit, etc. The Government is interested in financial stability, timely payments, the length and nature of the relationship between the firm and the financial institution, and the firm's financial ability to perform the contract. The letters should also provide the name and telephone number of the bank representative the Government may contact. If a Joint Venture, provide this information for each Joint Venture participant.

b. The Government will treat the pre-award survey information submitted by the offeror as proprietary.

5. TECHNICAL PROPOSAL VOLUME

5.1 NUMBER OF SETS OF THE TECHNICAL PROPOSAL

The Technical Proposal is to be submitted in one original (hard copy) and two copies.