Specifications Tangier Island Jetty.pdf
PDF 458 KB Posted
- Attached to
- Jetty Construction located on Tangier Island, VA
- Solicitation number
- W9123620B5000
About this file
This document provides details for an upcoming solicitation for jetty construction services on Tangier Island, Virginia. The Norfolk District Corps of Engineers will issue an unrestricted, firm fixed price invitation for bid for construction of approximately 685 feet of jetty structure using Type 1 riprap/armor stone, Class III riprap/core stone, geotextile fabric, marine mattresses, and excavated material placement. The project requires use of a turbidity curtain during construction and includes pre- and post-construction surveys. The estimated value is between $1 million and $5 million. Liquidated damages will be assessed at $1,007 per day of delay. The NAICS code is 237990 and the small business size standard is $39.5 million. Responses are due based on the future solicitation dates.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TANGIER ISLAND JETTY CONSTRUCTION TANGIER
100% Submittal
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 55 SOIL BORING DATA
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 22 00.00 10 MEASUREMENT AND PAYMENT
01 30 00 PROJECT MEETINGS
01 32 01.10 50 PROJECT PROGRESS SCHEDULE - SIMPLIFIED
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 CONTRACTOR QUALITY CONTROL
01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 78 00 CLOSEOUT SUBMITTALS
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR
STRUCTURES
35 42 35 POLYMERIC MARINE MATTRESS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 15
LIST OF DRAWINGS
03/16
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
PART 2 PRODUCTS (This Division not used)
PART 3 EXECUTION (This Division not used)
-- End of Section Table of Contents --
DOCUMENT 00 01 15 Page 1
SECTION 00 01 15
LIST OF DRAWINGS
03/16
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings dated NOVEMBER 2019 are as follows:
DRAWING SHEET TITLE
NO.
C-101 COVER SHEET
C-102 LOCATION MAP, LEGEND & GENERAL NOTES
C-103 EXISTING CONDITIONS
C-104 PROPOSED CONSTRUCTION
C-105 LIMITS OF CONSTRUCTION
C-106 PLACEMENT AREA FOR EXCAVATED MATERIAL
C-107 EXISTING & PROPOSED PROFILES
C-108 TYPICAL CROSS SECTION
C-109 MARINE MATTRESS DETAIL
PART 2 PRODUCTS (This Division not used)
PART 3 EXECUTION (This Division not used)
-- End of Section --
DOCUMENT 00 01 15 Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 55
SOIL BORING DATA
02/16
PART 1 GENERAL
1.1 Soil Classification
1.2 Sampling Method
1.3 Soil Consistency Determination
1.4 Boring Elevations and Locations
1.5 Abbreviations (if applicable)
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
SECTION 01 00 55 Page 1
SECTION 01 00 55
SOIL BORING DATA
02/16
PART 1 GENERAL
1.1 Soil Classification
The soil was visually classified in the field according to the "Unified Soil Classification System" and described utilizing ASTM D 2488 Standard Practice for Description and Identification of Soils (Visual-Manual Procedure). While it is believed that borings accurately indicate subsurface conditions for boring locations on the date taken, the Government assumes no responsibility for actual conditions which may be encountered in execution of Contract. Should the Contractor rely, for any purpose, upon the accuracy or completeness of soil borings, or boring logs thereof, he does so at his own risk. The geotechnical report, including soil boring drilling logs and data are provided with the design package.
All samples contained at the end of this SECTION were obtained on various dates as designated on the respective boring. Geotechnical analysis data is available for review at Norfolk District, 803 Front Street, Norfolk, VA 23510 (Attention: Andrew Brooks, telephone 757-201-7075).
1.2 Sampling Method
Cone Penetration Testing (CPT) was completed at three locations proximate to the proposed structure in accordance with ASTM D 5778. Cone resistance, friction resistance and pore pressure, among other data sets, were recorded at approximate five centimeter intervals. CPT data is available for review in the Geotechnical report located in ATTACHMENT 1:
Geotechnical Report. Additionally, soil samples were collected at depths ranging from about three to five below the mudline at two locations using a vibracore sampler until the sampler could not be advanced due to encountering denser soils. The CPT rig was also used to direct push tube samples to recover soils for visual classification and laboratory testing at one location to a depth of about 30 feet.
1.3 Soil Consistency Determination
Estimated consistencies (med. stiff, soft, etc.) are from Terzaghi & Peck "Soil Mechanics in Engineering Practice".
1.4 Boring Elevations and Locations
All boring elevations and locations are approximated. Boring logs are shown at the end of this section.
1.5 Abbreviations (if applicable)
BOH Bottom of Hole moist moisture bot bottom MP medium plasticity brk broken mrb marbled brwn brown mst moist cly clayey NP nonplastic const consistency OD Outside diameter
SECTION 01 00 55 Page 2 crs, c coarse org organic dk dark PI Plastic Index dns dense PL Plastic Limit fn, f fine sam sample frac fracture sat saturated frag fragments (fragmented) sft soft grn green slt slight(ly) gry gray sly silty HP high plasticity sm some hrd hard sta station hrs hours tr trace len lense v very lit little v.f. very fine LL Liquid Limit w moisture content
LP Low Plasticity w/ with lt light wd weathered med, m medium & and mica micaceous %200 Minus No. 200 Sieve
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
SECTION 01 00 55 Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
11/17
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
1.3.2 Location
1.4 SPECIAL WORK REQUIREMENTS
1.4.1 Use of Turbidity Curtain(s) and/or Aqua Dam(s)
1.4.2 Transportation Facilities
1.5 LOCATION OF UNDERGROUND FACILITIES/UTILITIES
1.5.1 Notification Prior to Excavation
1.6 LAYOUT OF WORK AND SURVEYS
1.6.1 General
1.6.2 Pre-Construction Survey
1.6.3 Post-Construction Survey
1.6.4 Placement Records and Survey Data
1.7 Electronic Survey and Positioning Systems
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
11/17
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-1003 (2013) Hydrographic Surveying Manual
EM 1110-1-1005 (2007) Topographic Survey Manual
VIRGINIA DEPARTMENT OF TRANSPORTATION (VDOT)
VDOTRBS (2016) Virginia Department of Transportation Road and Bridge Specifications
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
*Pre-Construction Survey; G The Pre-construction survey data shall be submitted within ten (10 ) business days after completion of the surveys in that area.
Data shall be submitted in the format specified herein.
SD-11 Closeout Submittals
*Post-Construction Survey; G
The Post-Construction survey shall be completed and submitted for Government review no later than 30 calendar days after acceptance of final project.
*Placement Records; G
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
The purpose of this project is to construct a jetty structure at Tangier Island. The work includes performing pre and post construction survey of the project area, placement of Type I ( VDOTRBS)riprap/armor stone and
SECTION 01 11 00 Page 2
Class III ( VDOTRBS)riprap/core stone, placement of geotextile fabric, placement of marine mattresses, placement of excavated material in placement area (shown on the construction drawings) to include measures to contain sediment from entering the navigation channel (Tangier West Channel), and any incidental work related to the construction of this project.
1.3.2 Location
The work shall be performed on Tangier Island, Virginia located in Accomack County, Virginia, as indicated on the contract drawings.
1.4 SPECIAL WORK REQUIREMENTS
1.4.1 Use of Turbidity Curtain(s) and/or Aqua Dam(s)
Type III ( VDOTRBS) turbidity curtains shall be properly secured at all times during the placement of excavated material . See Turbidity Curtain Specifications and typical aqua dam dimensions attached at the end of this section.
1.4.2 Transportation Facilities
The project location can only be accessed by water. Material and construction equipment will be transported to the project site by barge.
1.5 LOCATION OF UNDERGROUND FACILITIES/UTILITIES
The Contractor is responsible for obtaining all digging permits, including associated locating and marking services, in accordance with local requirements, at no additional cost to the Government. The Contractor will be responsible for maintaining all utility markings during construction.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.6 LAYOUT OF WORK AND SURVEYS
1.6.1 General
The Contractor shall be responsible for the expense and layout of all work. The Contractor's work methods may require physical markings to be placed for easement control points. All range markers or that otherwise are required to accomplish the work, shall be placed in the field and marked by a licensed Professional Engineer or Surveyor currently licensed in the Commonwealth of Virginia. The licensed Professional Engineer or Surveyor shall have Topographic and Hydrographic Surveying Experience. All hydrographic surveying shall be in accordance with EM 1110-2-1003 and all topographic surveying shall be in accordance with EM 1110-1-1005 . The horizontal plane of reference for the surveys shall be the Virginia State Plane Coordinate System (South Zone), in U.S. Survey Feet, North American Datum of 1983 (NAD 83). The vertical plan of reference shall be Mean Lower Low Water (MLLW), National Tidal Datum Epoch (NTDE) 1983-2001, in feet, as established by National Ocean Service (NOS).
SECTION 01 11 00 Page 3
1.6.2 Pre-Construction Survey
Conditions existing during the preparation of this contract may not be an accurate representation of the site area conditions existing at the commencement of work operations. Consequently, the Contractor shall perform a pre-construction survey of the entire project area, as well as 500 feet of the Tangier Island Federal Navigation channel to the East and West of the placement site, to confirm site conditions. The Contractor shall perform a multi-beam hydrographic survey with a bin size of 1 foot by 1 footcovering the project areas over water, and a topographic survey of areas on land with cross-sections taken on parallel profile lines (ranges) spaced at a maximum of 50 feet intervals. Elevations along the cross-sections shall be taken at a maximum of 10 foot intervals, with additional elevations taken at breaks in grade and as necessary to describe all hydrographic and topographic features. The pre-construction condition surveys shall be completed and submitted for Government review not later than ten (10) calendar days after the receipt by him of the notice to proceed.
1.6.3 Post-Construction Survey
The post construction survey shall cover the completed construction and 500 feet of the Tangier Island Federal Navaigation channel to the East and West of the placement site (to ensure material has not moved into the channel during construction). The Contractor shall perform a multi-beam hydrographic survey with a bin size of 1 foot by 1 footcovering the project areas over water, and a topographic survey of areas on land with cross-sections taken on parallel profile lines (ranges) spaced at a maximum of 50 feet intervals. Elevations along the cross-sections shall be taken at a maximum of 10 foot intervals, with additional elevations taken at breaks in grade and as necessary to describe all hydrographic and topographic features. The survey shall be completed and submitted for Government review no later than thirty (30) calendar days after acceptance of final project and comply with the same requirements stated for the pre-construction survey.
1.6.4 Placement Records and Survey Data
The Contractor shall also refer to Section 01 78 00 for direction of final As-Built drawings. All original field notes, computations, and other records for the purpose of the layout of surveys and determining material placed by the Contractor shall be recorded in duplicating field books, the original pages of which shall be stamped and signed by the licensed surveyor as specified and furnished promptly to the Contracting Officer at the site of the work. The Contractor shall furnish the Contracting Officer the survey data compiled and certified by the licensed surveyor as specified for each respective survey on a computer disk as well as the metadata files. The survey data shall be furnished in x,y,z format with a bin size of 1 foot by 1 foot. The data shall be submitted to the Government in the following files:
a. Files having a descriptive header for each profile line followed by three columns: Easting (x), Northing (y) and Elevation (z).
b. Plotted cross section drawings in AutoCAD 2018 or later format and AutoCAD files for each cross section survey taken. Each drawn cross section shall show the station that it was taken from.
c. The Government reserves the right to change and revise requirements
SECTION 01 11 00 Page 4 at the Preconstruction Conference to the survey data formats as described above.
1.7 Electronic Survey and Positioning Systems
All plant utilized for stone placement at the construction area(s) shall be equipped with electronic hardware and software capable of providing real time kinematic (RTK) positioning, on a computer display during material placement operations. Software package such as HYPACK or equivalent are capable of accomplishing these requirements. The system should have the capability displaying a shape file of leases and or any structure that the equipment needs to avoid. It should be able to capture the accurate tracking of the equipment and playback in 60 second intervals. The tracking positions must be recorded on a disk every 15 minutes and submitted to the contracting officer on a weekly basis. All electronic survey and plant positioning equipment, and the work accomplished with the use of the system must render the results in the same datum coordinate system as indicated on the drawing.
All work accomplished with the use of the systems shall be reviewed and certified as accurate by the Contracting Quality Control manager. This signed certification shall be submitted as part of the Daily report of Operations in accordance with the requirements of SECTION 01 45 00 CONTRACTOR QUALITY CONTROL to assure that all work being performed with the use of the equipment and system meets or exceeds the contract requirement.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 11 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
11/17
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SPECIAL SCHEDULING REQUIREMENTS
1.3 Construction Restrictions
1.4 Personnel Restrictions
1.5 Time of Year Restriction
1.6 CONTRACTOR ACCESS AND USE OF PREMISES
1.6.1 Activity Regulations
1.6.1.1 Subcontractors and Personnel Contacts
1.6.2 Working Hours
1.6.3 Work Outside Regular Hours
1.6.4 Miss Utility (va 811.com) Notification
1.6.5 Utility Cutovers and Interruptions
1.7 1.16 SPECIAL COAST GUARD REQUIREMENTS
1.7.1 1.16.1 Local Notice To Mariners
1.7.2 1.16.2 Relocation of Navigation Aids
1.7.3 1.16.3 Use of Coast Guard Navigation Aid Structures
1.8 PHYSICAL DATA
1.8.1 Physical Conditions Information
1.8.2 Site Related Weather Conditions
1.8.3 Time Extensions For Unusually Severe Weather
1.8.3.1 Schedule
1.8.4 Responsibility
1.8.5 Condition of Construction Areas
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/17
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals list of contact personnel
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Permission to interrupt any channel activity roads and/or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.3 Construction Restrictions
The Contractor shall be aware that the water depths toward the land are shallow. The Contractor shall refer to the construction drawings and preconstruction survey for depths at the start of construction.
No construction shall occur outside the limits of disturbance (shown on construction drawings). Vegetated wetlands or marsh within the limits of disturbance shall not be used as laydown or storage areas but may be used for construction access.
Low ground pressure equipment shall also be used by the Contractor when constructing over the shoreline.
1.4 Personnel Restrictions
Personnel are limited to the immediate site areas and shall not enter buildings or facilities not involved in the work. All employees of the Contractor will be subject to all federal, state, and local laws, ordinances, criteria, rules and regulations. The Contractor's plans for restricting personnel access to the project site shall be submitted for approval as a part of the Safety Plan (Accident Prevention Plan).
1.5 Time of Year Restriction
There are no time of year restrictions for this project.
1.6 CONTRACTOR ACCESS AND USE OF PREMISES
1.6.1 Activity Regulations
Ensure that the Contractor personnel employed on the Activity become
SECTION 01 14 00 Page 2 familiar with and obey activity regulations including safety, fire, traffic and security regulations. They will stay within the limits of the work and avenues of ingress and egress and wear hard hats in designated areas. They will not enter any restricted areas unless required to do so and are cleared for such entry. Ensure the Contractor's equipment is marked for identification.
The contractor shall ensure that personnel abide by the posted speed limits on the site access route. Site access route is provided at the end of this SECTION. The contractor shall ensure that personnel shall take caution when traveling and transporting equipment and materials up and down the site access road.
1.6.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.6.2 Working Hours
Regular working hours must consist of an period excluding Government holidays. Regular working hours shall occur during daylight. If the contractor would like to work outside of daylight hours, the contractor shall submit a request to the COR.
1.6.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 5 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress.
1.6.4 Miss Utility (va 811.com) Notification
The Contractor shall contact Miss Utility to confirm location of all utilities (above ground and below water). The Contractor shall comply with all requirements of the Virginia Underground Utility Damage Prevention Act § 56-265.14 (the Miss Utility law). The Contractor must call the Miss Utility Notification Center at 811 OR 1-800-552-7001 before commencing any excavation work.
The Contractor shall provide to the Government, in writing, all Ticket numbers, Miss Utility system responses and other information upon completion of the Contractor's notification process to Miss Utility prior to the start of work. Requirements of the law, procedures to followed by the Contractor and other pertinent information for the Contractor's use can be found at http://www.missutilityofvirginia.com (or http://va811.com/lawspolicies/). Each "person" as defined in the Underground Utility Damage Prevention Act must provide their own notice of excavation. Subcontractors may not work under another company's ticket unless they are under the direct supervision of the company that provided the notice of excavation.
The Contractor shall allow a minimum of 48 hours after notifying the Miss Utility notification center and begin excavation only after checking the Positive Response System, and confirm through the Ticket Information Exchange (TIE) System, that all applicable utilities have either marked their underground line locations or reported that no lines are present in
SECTION 01 14 00 Page 3 the work vicinity. The Contractor shall wait an additional 24 hours before commencing excavation work if any utility operators have failed to respond to the Ticket Information Exchange within the first 48 hours.
1.6.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air, are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The County will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.7 1.16 SPECIAL COAST GUARD REQUIREMENTS
1.7.1 1.16.1 Local Notice To Mariners
The Local Notice To Mariners (LNM) for the Fifth Coast Guard District is available by phone at (757) 398-6367. Additionally, LNM are locatedon the Internet at the following address:
http://www.navcen.uscg.gov/?pageName=lnmDistrict®ion=5 and e-mail address: D5Local@LANTD5.uscg.mil.
The LNM is the primary means for disseminating information concerning aids to navigation, hazards to navigation, and other items of marine information of interest to mariners on the waters of the United States, its territories, and possessions. These notices are essential to all navigators for the purpose of keeping their charts, light lists, Coast Pilots and other nautical publications up-to-date. These notices are published weekly. They may be obtained free of charge, by making application to the Fifth Coast Guard District, Federal Building, 431 Crawford Street, Portsmouth, Virginia 23704. If the Contractor encounters any objects on the channel bottom during dredging operations or transport of his plant that could be a hazard to navigation, he shall notify the Coast Guard immediately as to location and at the same time notify the Contracting Officer.
1.7.2 1.16.2 Relocation of Navigation Aids
The Contractor shall not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aid to navigation moved in order to complete dredging operations under this contract, the Contractor shall notify the U.S. Coast Guard in writing at the address above with a copy to the Contracting Officer not less than 15 calendar days prior to such need for movement. The Contractor shall notify the U.S. Coast Guard of the approximate time the navigation aid may
SECTION 01 14 00 Page 4 be relocated to its original position. All notifications to the U.S. Coast Guard shall at the same time be provided to the Contracting Officer and recorded in the Daily Report of Operations. In the event that the Contractor disturbs or damages any navigation aid during work operations, which includes during mobilization or demobilization of his plant, the Contractor shall immediately stop the activity which disturbed or damaged the navigation aid, take immediate corrective action to prevent further disturbances or damage, and shall notify the Coast Guard immediately as to location, and at the same time notify the Contracting Officer.
1.7.3 1.16.3 Use of Coast Guard Navigation Aid Structures
The Commander, Fifth Coast Guard District, has authorized the Norfolk District, Corps of Engineers, and its Contractors to use fixed Federal aids to navigation structures, established and maintained by the U. S.
Coast Guard, for support of temporary dredging tide gauges when performing Federal dredging operations. If a Contractor chooses to use navigation aid structures for this purpose, he shall abide by the following requirements:
a. The Contractor shall advise the Commander, Fifth Coast Guard District, Aids to Navigation Branch, Federal Building, 431 Crawford Street, Portsmouth, Virginia 23704, in writing, of his intention to attach tide gauges to navigation aid and structures, prior to commencing a dredging project. This notice shall include the name of each aid to navigation to which tide gauges are to be attached, and the anticipated dates the gauges will be attached and removed. A copy of this notice shall be furnished at this time to the Contracting Officer.
b. The Contractor shall be required to remove any temporary tide gauges immediately upon completion of dredging operations and demobilization of dredging plant. The Contractor shall at his expense repair or replace any aids that he has damaged or destroyed as a result of the Contractor's use of such aids.
c. This provision refers only to Federal aids to navigation structures and does not authorize the Contractor to utilize aids that are not established and maintained by the U. S. Coast Guard. This provision also does not authorize the Contractor to utilize Federal navigation aid structures for any purposes other than the support of temporary tide gauges.
1.8 PHYSICAL DATA
1.8.1 Physical Conditions Information
The physical conditions indicated on the drawings and in the specifications are the result of site investigations and surveys.
Information and data furnished are for the Contractor's information;
however, it shall be expressly understood that the Government will not be responsible for any interpretation or conclusion drawn from this information or data by the Contractor.
1.8.2 Site Related Weather Conditions
The Contractor shall anticipate that severe weather conditions may occasionally interfere with the progress of work. Complete weather forecasts, records and reports may be obtained from the National Weather Service in Wakefield, Virginia, telephone (757) 899-4200. Menu selection
SECTION 01 14 00 Page 5 service or operator assisted as applicable. The Contractor shall be aware of the hazards likely to arise from the weather conditions during the construction period. Allowance for claims of weather delays are solely based upon the Government Contracting Officer's discretion. Basis for allowing any delay for weather related delay time shall be based upon FAR clauses 52.236-3, 52.236-4, and 52.249-10.
1.8.3 Time Extensions For Unusually Severe Weather
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather may actually cause a delay to the completion of the project. The delay must be beyond the Contractor's control and without the fault or negligence of the Contractor.
1.8.3.1 Schedule
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS
BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
10 9 8 6 7 7 9 6 5 5 6 9
1.8.4 Responsibility
The Contractor shall hold and save harmless the United States, its officers, and employees from all claims that may arise as a result of the Contractor's negligence in connection with the work performed under the contract, from noncompliance by the Contractor with the provisions of the contract drawings and specifications, or from the instruction of the Contracting Officer.
1.8.5 Condition of Construction Areas
The required construction areas specified on the plans are based on the condition of the site at the time of the most recent surveys as indicated.
The conditions shown by the surveys specified are subject to change due to the natural forces of rain, wind, waves, river velocities and flows which constantly erode the riverbank.
SECTION 01 14 00 Page 6
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 7
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
11/17
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 LUMP SUM PAYMENT ITEMS
1.3.1 Payment Item No. 0001 Mobilization and Demobilization
1.3.2 Payment Item No. 0002 Site Work
1.4 UNIT PRICE PAYMENT ITEMS
1.4.1 Payment Item No. 0003 Marine Mattresses
1.4.2 Payment Item No. 0004 Armor Stone (VDOT Type I Stone)
1.4.3 Payment Item No. 0005 Core Stone (VDOT Class III Stone)
1.4.4 Payment Item No. 0006 Purchase Tidal Wetlands Credits
1.5 MISPLACED MATERIAL
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00.00 10 Page 1
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
11/17
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
VIRGINIA DEPARTMENT OF TRANSPORTATION (VDOT)
VDOTRBS (2016) Virginia Department of Transportation Road and Bridge Specifications
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Weight Scale Tickets
Submit certified weight scale tickets for stone.
SD-07 Certificates
Weight Scale Certification; G
A copy of the certification from the regulatory agency attending to the scale's accuracy.
1.3 LUMP SUM PAYMENT I TEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
SECTION 01 22 00.00 10 Page 2
1.3.1 Payment I t em No. 0001 Mobi l i zat i on and Demobi l i zat i on
All costs connected with the mobilization and demobilization of all of the Contractor's plant and equipment as defined below will be paid for at the contract lump sum price for this item. Sixty percent of the lump sum price will be paid to the Contractor upon completion of his mobilization at the work site. The remaining forty percent will be paid to the Contractor upon completion of demobilization. In the event the Contracting Officer considers that the amount in this item, sixty percent which represents mobilization and forty percent which represents demobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer may require the Contractor to produce cost data to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer will result in payment of actual mobilization costs, as determined by the Contracting Officer, at the completion of mobilization, and actual demobilization costs, as determined by the Contracting Officer, at the completion of demobilization. The determination of the Contracting Officer is not subject to appeal.
Mobilization shall include all costs for operations accomplished prior to commencement of actual construction operations. This shall include as a minimum the following:
a. Transportation of personnel, equipment, and materials to the job site.
b. Any required labor and materials to set up working operations (i.e.
administrative, electricity, telephone, lay down area preparations, etc.)
c. Construction of access to construction area.
d. All costs for any other associated work that is necessary in advance of the actual project.
Demobilization shall include general preparation for closeout of project including, but not limited to Transportation of personnel, equipment, and materials from the job site, decommissioning of temporary facilities, etc.
1.3.2 Payment I t em No. 0002 Si t e Wor k
Payment will be made for costs associated with all methods material and labor required for performing all pre and post construction survey work and, excavation of material, containment of excavated material (by means of turbidity curtain and/or aqua dam), and site-work associated with the construction of the jetty structure.
1.4 UNI T PRI CE PAYMENT I TEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.4.1 Payment I t em No. 0003 Mar i ne Mat t r esses
Payment items for costs associated with furnishing, transporting, SECTION 01 22 00.00 10 Page 3 stockpiling (if applicable), placing and constructing the marine filter mattress (12" thickness) including stone fill and geotextile fabric as specified. Marine Mattress will be measured for payment per square yard of stone filled mattress.
1.4.2 Payment I t em No. 0004 Ar mor St one ( VDOT Type I St one)
Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable), placing, and constructing the imported of VDOT Type I armor stone for the construction of the new breakwaters as specified. Imported Armor Stone (VDOT Type I) ( VDOTRBS) will be measured for payment by the ton (2,000 pounds) by certified Weight Scale Tickets furnished by a public weighmaster provided for each truckload, barge and/or scow to the nearest 0.1 ton, and the final quantity of each truckload, barge and/or scow will be rounded to the nearest whole ton. All weigh scale tickets shall be furnished to the Government. A copy of the Weight Scale Certification shall be furnished from the regulatory agency attesting to the scale's accuracy. The Contracting Officer may elect to accept weighing imported armor stone on the project site. Scale(s) shall be inspected, tested and sealed as directed to assure accuracy within 0.5 percent throughout the range of the scales. If commercial scales are readily available in close proximity 10 miles of site of work, the Contracting Officer may approve the use of the scales. The imported armor stone shall be weighed in the presence of the Government representative.
1.4.3 Payment I t em No. 0005 Cor e St one ( VDOT Cl ass I I I St one)
Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable), placing, and constructing the core stone into the new breakwaters as specified. Core Stone (VDOT Class III) ( VDOTRBS) will be measured for payment by the ton (2,000 pounds) by certified Weight Scale Tickets furnished by a public weighmaster provided for each truckload, barge, and/or scow to the nearest 0.1 ton, and the final quantity of each truckload, barge, and/or scow will be rounded to the nearest whole ton. All weigh scale tickets shall be furnished to the Government. A copy of the Weight Scale Certification shall be furnished from the regulatory agency attesting to the scale's accuracy. The Contracting Officer may elect to accept weighing imported armor stone on the project site. Scale(s) shall be inspected, tested and sealed as directed to assure accuracy within 0.5 percent throughout the range of the scales. If commercial scales are readily available in close proximity 10 miles of site of work, the Contracting Officer may approve the use of the scales. The imported armor stone shall be weighed in the presence of the Government representative.
1.4.4 Payment I t em No. 0006 Pur chase Ti dal Wet l ands Cr edi t s
The Contractor shall be responsible for the purchase of 0.11 acres of tidal wetlands credits from the available Virginia Aquatic Resources Trust Fund (VARTF) In-Lieu Fee (ILF) Program in HUC 02080101 (Lower Chesapeake Bay) prior to construction. To purchase the credits, the Contractor must first apply for a credit availability voucher from VARTF. Payment for the tidal wetland credits may be submitted after the Contractor receives the credit availability voucher from VARTF. The VARTF will provide a credit sale confirmation letter to the Contractor at the completion of the wetland credit purchase. Contractor must provide the credit sale confirmation letter to the Contracting Officer as proof of purchase prior
SECTION 01 22 00.00 10 Page 4 to commencing construction activities. The government shall reimburse the Contractor in accordance with the bid schedule.
1.5 MISPLACED MATERIAL
Any material that is deposited elsewhere than in places designated or approved by the Contracting Officer will not be paid for, and the Contractor may be required to remove such misplaced material and deposit it where directed by the Contracting Officer at the Contractor's expense.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 22 00.00 10 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 SUBMITTALS (NOT APPLICABLE)
1.2 PRECONSTRUCTION CONFERENCE
1.2.1 Scheduling
1.2.2 Purpose
1.2.3 Discussion Items
1.3 OTHER MEETINGS DURING THE CONTRACT
1.4 MINUTES OF MEETINGS
PART 2 PRODUCTS (THIS PART NOT USED)
PART 3 EXECUTION (THIS PART NOT USED)
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 SUBMITTALS (NOT APPLICABLE)
1.2 PRECONSTRUCTION CONFERENCE
1.2.1 Scheduling
After award of the construction contract and prior to the start of any construction work, the Contracting Officer Representative (COR) will schedule and conduct an initial preconstruction conference. The Contractor's Project Manager, Superintendent and Quality Control System Manager shall attend these meetings. The Contractor is encouraged to have an officer of his company (Project Manager could be this person) and representation from each of his sub-contractors and major construction work divisions at the conferences. The conferences will be held at a location and time as specified by the COR.
1.2.2 Purpose
The purpose of this preconstruction conference is to enable the COR to outline the procedures that will be followed by the Government in its administration of this construction contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, about security requirements, regulations, and other similar matters. The COR may include other Government personnel involved in the work to attend this meeting.
1.2.3 Discussion Items
The following is a sample list of items for discussion during the preconstruction conference; however, the Contracting Officer may modify this list or include additional items for discussion as conditions and the work require.
a. Authority of the Contracting Officer/Contracting Officer's Representative.
b. Contractor's Progress Schedule.
c. Correspondence Procedures.
d. Contractor Labor Standards Provisions.
e. Contract Modifications and Administrative Procedures.
f. Contractor's Administrative, Laydown and Storage Areas.
g. Procedures for Processing Submittals.
SECTION 01 30 00 Page 2
h. Payment Estimate Data and Procedures.
i. Contractor Utilities.
j. Security Requirements and Other Regulations, if applicable.
k. Project Site Access
l. Government Furnished Equipment, if applicable.
m. Disposition of Salvage Property, if applicable.
n. Contractor Insurance Requirements.
o. Environmental Protection Plan.
p. Spill Response Plan.
q. Stormwater Pollution Prevention Plan (SWPPP).
r. Contractor Performance Evaluation.
s. Emergency and Safety Procedures.
t. Plant and Suitability to Perform the Work.
u. Turnover of Placement Areas After Construction.
v. Contractor Required Notification Procedures.
w. Contractor's Submittal Register.
x. Contractor's Survey and Information Reporting Procedures.
y. Contractor's Quality Control Plan and Activity Hazard Analysis,shall ensure special emphasis to coordinate the proposed work procedures of the Contractor and the associated procedures the Contractor intends to employ to protect the public and comply to noise and safety requirements.
1.3 OTHER MEETINGS DURING THE CONTRACT
Other meetings may be held after the Preconstruction Conference, for the purpose to discuss concerns and deficiencies that may include the following:
a. Contractor's Site Safety and Health Plan.
b. Quality Control Plan.
c. Environmental Protection Plan.
d. Progress Schedule updates.
1.4 MINUTES OF MEETINGS
The Government will prepare minutes of all meetings. Progress meetings shall occur monthly or as needed.
SECTION 01 30 00 Page 3
PART 2 PRODUCTS (THIS PART NOT USED)
PART 3 EXECUTION (THIS PART NOT USED)
SECTION 01 30 00 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.10 50
PROJECT PROGRESS SCHEDULE - SIMPLIFIED
06/16
PART 1 GENERAL
1.1 SUBMITTALS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 EXECUTION
3.1.1 PROJECT SCHEDULING AND DETERMINATION OF PROGRESS (Simplified
Bar-Chart Method)
SECTION 01 32 01.10 50 Page 1
SECTION 01 32 01.10 50
PROJECT PROGRESS SCHEDULE - SIMPLIFIED
06/16
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-07 Certificates
Preliminary Project Schedule; G Three copies of the schedules showing codes, values, categories, numbers, items, etc., as required.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 EXECUTION
3.1.1 PROJECT SCHEDULING AND DETERMINATION OF PROGRESS (Simplified Bar-Chart Method)
In accordance with the Contract Clauses, the Contractor shall, within ten calendar days after receipt of Notice to Proceed, submit for approval a practicable progress schedule. A preliminary project schedule, acceptable to the Contracting Officer, may be submitted in order for the Contractor to begin work. The progress schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. Each activity in the construction shall be represented by an arrow. The head to tail arrangement of arrows shall flow from left to right and shall show the order and interdependence of activities and the sequence in which the work is to be accomplished as planned by the Contractor. Each arrow representing an activity shall be annotated to show the activity description and duration. Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction efforts is appraised. When changes are authorized that result in contract time extensions, Contractor shall submit a modified chart for approval by the Contracting Officer. The Contract Clause entitled "SCHEDULE FOR CONSTRUCTION CONTRACTS" with reference to overtime, extra shifts, etc., may be invoked when the Contractor fails to start or complete work
SECTION 01 32 01.10 50 Page 2 features or portions of same by the time indicated by the milestone dates of the approved progress chart, or when it is apparent to the Contracting Officer from the Contractor's actual progress that these dates will not be met. Neither on this chart nor on the periodic chart which the Contractor is required to prepare and submit, as described in "SCHEDULE FOR CONSTRUCTION CONTRACTS" of the Contract Clauses, shall the actual progress to be entered include or reflect any materials which may be on the site, but are not yet installed or incorporated in the work.
For payment purposes only, an allowance will be made by the Contracting Officer of 100 percent of the invoiced cost of materials or equipment delivered to the site but not incorporated into the construction, pursuant to Contract Clause "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS".
The Contractor's progress schedule shall include a chart of the scheduled work activities plotting scheduled completion percentage based on dollar value on one axis and time on the other axis. The actual progress shall be plotted on the required periodic chart submittals to indicate the percentage of work scheduled and actually completed.
SECTION 01 32 01.10 50 Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
10/15
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved G
1.4.2 Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.6 INFORMATION ONLY SUBMITTALS
1.7 DISAPPROVED OR REJECTED SUBMITTALS
1.8 APPROVED OR ACCEPTED SUBMITTALS
1.9 APPROVED SAMPLES
1.10 WITHHOLDING OF PAYMENT
1.11 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL
3.2 SCHEDULING
3.2.1 Submittal and Report Identification
3.3 SUBMITTAL REGISTER (ENG FORM 4288)
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
10/15
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
Surety bonds
List of proposed Subcontractors & Personnel Contacts
SECTION 01 33 00 Page 2
List of proposed products
Construction progress schedule
Network Analysis Schedule (NAS)
Submittal register
Schedule of prices
Health and safety plan
Work plan
Quality Control(QC) plan
Environmental protection plan
SD-02 Shop Drawings
As used in this section, drawings, schedules, diagrams, and other data prepared specially for this contract, by the Contractor or through Contractor by way of subcontractor, manufacturer, supplier, distributor, other lower tier contractor, to illustrate portion of work.
SD-03 Product Data
C…