Amendment_03_-_Summary,_Rev_Bid_Sched,_Answers,_Spec_Changes.pdf

PDF 389 KB Posted

Attached to
Dam Gate Installation at Montgomery Locks and Dam, Monaca, PA
Solicitation number
W911WN-17-B-8003
Issued by

About this file

Summary of Changes, FINAL Bid Schedule, Answers, Spec revisions with new gate delivery dates and on site availability.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Montgomery Locks and Dam Dam Gate Installation 2017

W911WN-17-B-8003

Amendment No. 0003

1. The bid schedule has been updated to the FINAL version. Please use the bid schedule in

Amendment 03 for your bids.

2. The remaining questions have been answered.

3. The following changes are made to the Solicitation:

Section 00800 – SPECIAL CONTRACT REQUIREMENTS -- 00800-4 AWARDABLE OPTIONS - The time extension for completion of Awardable Option 2 has been removed.

Awardable Option 2 will be completed within the completion time for the Base Contract and Awardable Option 1.

4. The following changes are made to the Specifications:

Section 01 35 00.00 08 SPECIAL PROCEDURES

Paragraph 3.1.1 Restrictions on Work at Montgomery Dam – A restriction has been added that no work will be permitted at the Montgomery Dam site before November 1, 2017.

Section 01 73 19.00 08 GOVERNMENT-FURNISHED PROPERTY

Paragraph 1.4.3 Delivery – Delivery dates for all three gates have been revised.

INSTALLATION OF VERTICAL LIFT GATES NO. 3, 2, AND 1

MONTGOMERY LOCKS & DAM

BASE CONTRACT – INSTALLATION OF LIFT GATES NO. 3 AND 2 (450 CALENDAR DAYS)

BID SCHEDULE

Item Description QTY Unit Unit Price $ Total $

0001 REIMBURSEMENT FOR

ACTUAL PERFORMANCE

AND PAYMENT BONDS

PREMIUMS

1 JOB

0002 DIGITAL PROGRESS

IMAGES, MONTHLY, BASE

CONTRACT

10 SET

0003 DEMOLITION OF EXISTING

LIFT GATES AND

ASSOCIATED ITEMS, BASE

CONTRACT

2 EACH

0004 CONCRETE REMOVAL, PIER

MODIFICATIONS, BASE

CONTRACT

142 CUBIC

YARDS

0005 CONCRETE REMOVAL

BEYOND LIMITS OF

MODIFICATION, BASE

CONTRACT

10 CUBIC

0006 STEEL DOWELS AND

REINFORCING STEEL, BASE

CONTRACT

1,650 POUNDS

0007 ADDITIONAL STEEL

DOWELS AND

REINFORCING FOR

CONCRETE REPAIR, BASE

CONTRACT

100 POUNDS

0008 CONCRETE, PIER

MODIFICATION, BASE

CONTRACT

142 CUBIC

0009 ADDITIONAL CONCRETE

FOR CONCRETE REPAIR

BEYOND MODIFICATION

LIMITS, BASE CONTRACT

10 CUBIC

0010 EMBEDDED METALS, BASE

CONTRACT

18,060 POUNDS

0011 TYPE 1 SPALL REPAIR

(SHALLOW), BASE

CONTRACT

150 SQUARE

FEET

0012 TYPE 2 SPALL REPAIR

(DEEP), REINFORCING

STEEL, BASE CONTRACT

800 POUNDS

0013 EPOXY INJECTION

ADHESIVE, BASE

CONTRACT

200 LINEAR

0014 TYPE 2 SPALL REPAIR

(DEEP), CONCRETE, BASE

CONTRACT

250 SQUARE

0015 MODIFICATION OF

MACHINERY HOUSINGS,

BASE CONTRACT

3 EACH

0016 MODIFICATION OF LIFT

GATE MACHINERY

SUPPORTS, BASE

CONTRACT

2 SETS

0017 REPAIR AND

REHABILITATION OF GATE

HOIST MACHINERY, BASE

CONTRACT

2 SETS

0018 INSTALL GOVERNMENT-

FURNISHED LIFT GATES,

BASE CONTRACT

2 EACH

0019 INSTALL NEW

GOVERNMENT- FURNISHED

HOISTING CHAINS, BASE

CONTRACT

2 SETS

0020 ELECTRICAL EQUIPMENT

AND SYSTEMS, BASE

CONTRACT

2 EACH

0021 FURNISH AND INSTALL

SIGNAGE ON GATE NO.

1 JOB

0022 CLEAN BULKHEAD

UNITS, BASE

CONTRACT

2 SETS

0023 MOBILIZATION &

DEMOBILIZATION

1 JOB

TOTAL BASE CONTRACT ITEMS 0001-0023 $_________________________

AWARDABLE OPTION 1 – INSTALLATION OF LIFT GATE NO. 1 (210 CALENDAR DAYS)

Item Description QTY Unit Unit Price $ Total $

1001 REIMBURSEMENT FOR

ACTUAL PERFORMANCE

AND PAYMENT BONDS

PREMIUMS

1 JOB

1002 DIGITAL PROGRESS

IMAGES, MONTHLY

6 SET

1003 DEMOLITION OF EXISTING

LIFT GATES AND

ASSOCIATED ITEMS

1 EACH

1004 CONCRETE REMOVAL, PIER

MODIFICATIONS

71 CUBIC

1005 CONCRETE REMOVAL

BEYOND LIMITS OF

MODIFICATION

5 CUBIC

1006 STEEL DOWELS AND

REINFORCING STEEL

825 POUNDS

1007 ADDITIONAL STEEL

DOWELS AND

REINFORCING FOR

CONCRETE REPAIR

50 POUNDS

1008 CONCRETE, PIER

MODIFICATION

71 CUBIC

1009 ADDITIONAL CONCRETE

FOR CONCRETE REPAIR

BEYOND MODIFICATION

LIMITS

5 CUBIC

1010 EMBEDDED METALS 9,030 POUNDS

1011 TYPE 1 SPALL REPAIR

(SHALLOW)

100 SQUARE

1012 TYPE 2 SPALL REPAIR

(DEEP), REINFORCING

STEEL

400 POUNDS

1013 EPOXY INJECTION

ADHESIVE

50 LINEAR

1014 TYPE 2 SPALL REPAIR

(DEEP), CONCRETE

150 SQUARE

1015 MODIFICATION OF

MACHINERY HOUSINGS

1 EACH

1016 MODIFICATION OF LIFT

GATE MACHINERY

SUPPORTS

1 SETS

1017 REPAIR AND

REHABILITATION OF GATE

HOIST MACHINERY

1 SETS

1018 INSTALL GOVERNMENT-

FURNISHED LIFT GATES

1 EACH

1019 INSTALL NEW

GOVERNMENT- FURNISHED

HOISTING CHAINS

1 SETS

1020 ELECTRICAL EQUIPMENT

AND SYSTEMS

1 EACH

1021 CLEAN BULKHEAD UNITS 1 SETS

TOTAL AWARDABLE OPTION ITEMS 1001-1021 $_________________________

AWARDABLE OPTION 2 – REPAIR COATINGS ON GATE NO. 4 AND PAINT MACHINERY HOUSE

BEAMS ON PIERS 4 AND 5

Item Description QTY Unit Unit Price $ Total $

2001 REIMBURSEMENT FOR

ACTUAL

PERFORMANCE AND

PAYMENT BONDS

PREMIUMS

1 JOB

2002 PREPARATORY WORK

FOR REPAIR OF

EXISTING COATING ON

LIFT GATE NO. 4

1 JOB

2003 CLEAN & PRESSURE

WASH EXISTING GATE

NO. 4 FOR

GOVERNMENT

INSPECTION

1 JOB

2004 REPAIR OF EXISTING

METALLIZING ON LIFT

GATE NO. 4

175 SQUARE

2005 REPAIR OF EXISTING

PRIME AND

INTERMEDIATE

COATINGS ON LIFT

GATE NO. 4

175 SQUARE

2006 TOP COATING REPAIR

ON LIFT GATE NO. 4

1 JOB

2007 FURNISH AND

INSTALL SIGNAGE ON

GATE NO. 4

1 JOB

TOTAL AWARDABLE OPTION ITEMS 2001-2007 $________________________

GRAND TOTAL – BASE YEAR, OPTION 1, OPTION 2 $_________________________

Montgomery Gate Installation

W911WN-17-B-8003

Amendment No. 3

Bidder Questions

Q1. Currently the solicitation reads that Gate No. 3 will be delivered by December 31, 2017, Gate No. 2 by April 30, 2018, and Gate No. 1 by December 31, 2018. This presents several problems. If Gates 3 and 1 are delivered on or around December 31, then it is likely they cannot be installed at that time due to high water conditions. In fact, high water conditions could prevent unloading of the gates. Second, in order to keep crews productive, gate delivery should be advanced to no later than October 31st. Finally, if the dates stand, it is likely that both Gates 1 and 3 will be stored on barges through the high water season and Gate 2 will be stored for several months while preparatory work for setting Gate 2 is completed following Gate 3 erection.

Advancing delivery of Gate 3 to October 31, 2017 mitigates this potential storage cost. Please consider moving the delivery date for Gate 3 back to October 31, 2017 and the delivery date for Gate 1 back to October 31, 2018.

A1. No. The gate deliveries are determined from current fabrication contracts. Gate No. 3 will not be ready for delivery by October 31, 2017 as proposed. The anticipated delivery dates for the gates have been revised by Amendment No. 3 to March 1, 2018 for Gate No. 3, June 30, 2018 for Gate No. 2, and December 2, 2018 for Gate No. 1.

Q2. The current solicitation provides for a 450 day performance period and an additional 210 days if Gate 1 erection option is exercised. Assuming an August 1, 2017 Notice-to-Proceed, the completion date for the base contract would be approximately October 31, 2018. This could be problematic if river conditions prevent erection of Gate 3 from the current delivery date of 12/31/2017 until June of 2018. Please consider extending the completion time for the base contract by a minimum of 30 and preferably 60 days.

A2. No. The period of performance is reasonable with the exclusion of time associated with adverse weather and high water. Modification for adverse weather delays will be made in accordance with Addendum to Section 00800 Paragraph 00800-7 TIME EXTENSIONS FOR

UNUSUALLY SEVERE WEATHER.

Q3. Also, the additional 210 days for the Gate 1 installation option is insufficient because most of that additional time occurs during normal high water season. Please consider extending the completion time for the Gate 1 erection option to the fall of 2019, preferably October 31, 2019.

Current completion date is late spring or early summer of 2019 for this option.

A3. No. The period of performance is reasonable with the exclusion of time associated with adverse weather and high water. Modification for adverse weather delays will be made in accordance with Addendum to Section 00800 Paragraph 00800-7 TIME EXTENSIONS FOR

UNUSUALLY SEVERE WEATHER.

Questions Q4 through Q15 were addressed in Amendment 2.

Q16. How many vulcanized spliced will be made per each gate seal?

A16. There will be two vulcanized splices for each gate seal.

Questions Q17 through Q25 were addressed in Amendment 2.

Montgomery L/D Dam Gate Installation 2017

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 00.00 08

SPECIAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.2 REFERENCES

1.3 SUBMITTALS

1.4 DRAWINGS

1.4.1 Contract Drawings - General

1.4.2 Government-Furnished Material Drawings

1.4.3 Reference Drawings

1.5 WORK UNDER OTHER CONTRACTS

1.6 1.4 CONSTRUCTION SITE PLAN

1.7 WORK AREAS AND RESTRICTIONS

1.7.1 General

1.7.2 Work Areas

1.7.3 Access Plan

1.7.4 Access to Project Site

1.7.5 Protection of Existing Roads and Property

1.7.5.1 General

1.7.5.2 Hauling Permits

1.7.6 Laydown, Storage and Parking Area

1.7.7 Utilities

1.8 EXISTING SURVEY CONTROLS

1.8.1 Project Alignment

1.9 RESTRICTIONS TO RIVER TRAFFIC FOR CONSTRUCTION

1.10 PROTECTION AND MAINTENANCE OF ROAD TRAFFIC

1.11 DAMAGE TO WORK

1.12 PROTECTION OF UTILITIES

1.13 OPERATION OF FACILITIES

1.14 CONDITIONS OF WORK

1.14.1 Montgomery Locks and Dam, Hours of Operation

1.14.2 Contractor's Work Hours

1.14.3 Coordination with Lock Operations

1.14.3.1 Restrictions to River Traffic for Delivery of Products

1.14.3.2 Installation and Removal of Dam Bulkhead

1.14.4 Government Service Crane and Bulkhead Hoist

1.14.5 Dam Gate Operating Schedule

1.14.6 Operation of Dam Gates During Contract Work

1.14.7 Warning Signs, Lights and Buoys

1.14.8 Contractor Coordination and Scheduling

1.15 EMERGENCY USE OF BULKHEAD UNITS

1.15.1 Installation of Concrete Gravity Blocks

1.16 CONTRACTOR'S FLOATING PLANT

1.16.1 General

1.16.2 Equipment Requirements

1.16.3 Signal Lights and Markers

1.16.4 Maintenance of Floating Plant

SECTION 01 35 00.00 08 Page 1 Certified Final RTA - W911WN-17-B-8003 Revised by Amendment 3

1.16.5 Mooring of Floating Plant

1.16.6 Suspension of River Traffic and Construction

1.16.6.1 Withdrawal of Equipment and Floating Plant

1.16.6.2 Plan of Action, Withdrawal of Equipment and Floating Plant

1.16.6.3 Compensation and Extension of Contract Period, Suspension of Work

1.16.7 Operation of Small Water Craft

1.17 SAFETY AND HEALTH REQUIREMENTS

1.18 POOL LEVELS

1.18.1 Hydrographs and Stage-Duration Curves

1.19 DISCHARGES

1.20 INSPECTIONS AND ACCEPTANCE OF WORK

1.20.1 General

1.20.2 Access to Work

PART 2 PRODUCTS

2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE

PART 3 EXECUTION

3.1 SEQUENCE OF WORK AND RESTRICTIONS

3.1.1 Restrictions on Work at Montgomery Dam

3.2 RECORDS AND REPORTS

3.3 ANTITERRORISM (AT) AND PROJECT SPECIFIC SECURITY REQUIREMENTS

3.3.1 Access and General Protection/Security Policy and Procedures

3.3.2 OPSEC Training

3.3.3 Escort of Contractor Employees

3.3.4 Pre- screen candidates using E-Verify Program

3.3.5 Changes in Security Requirements

3.3.6 Identification Of Employees

3.4 CLEANING BULKHEAD UNITS

3.4.1 General

3.4.2 Pressure Washing

-- End of Section Table of Contents --

SECTION 01 35 00.00 08 Page 2

SECTION 01 35 00.00 08

SPECIAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

This section contains information of a general nature, and covers general requirements applicable to the performance of the work under this contract. The information provided, and the requirements specified are in addition to those specified in other sections of the contract.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. COAST GUARD (USCG)

NAVIGATION RULES (August 2014) Navigation Rules and Regulations Handbook

U.S. DEPARTMENT OF HOMELAND SECURITY (DHS)

HSPD-12 (2004) Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 81 72 COLREGS: Implementing Rules

33 CFR 84 Annex I: Positioning and Technical Details of Lights and Shapes

33 CFR 89 Inland Navigation Rules: Implementing Rules

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having an "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Propelling Unit Agreement; G, RO

SECTION 01 35 00.00 08 Page 3

The written agreement between the Contractor and the lessor documenting the requirement for required towboat or propelling unit to be on site within the specified time limit shall be provided to the Contracting Officer prior to mobilization of any floating plant to the work site.

Construction Site Plan; G, RO

Access Plan; G, RO

The Contractor shall submit an access plan for Government lock operating personnel to the Contracting Officer.

Plan of Action, Withdrawal of Equipment and Floating Plant; G, RO

The Contractor shall prepare and submit a Plan of Action for withdrawal of equipment and floating plant in accordance with paragraph PLAN OF ACTION, WITHDRAWAL OF EQUIPMENT AND FLOATING PLANT. The plan shall be submitted for the Government's review prior to the start of work. The Contractor is advised that the plan must be submitted and accepted or no work at the site will be allowed.

Small Water Craft Operations Plan; G, RO

The Contractor shall develop and submit a plan for operation of small water craft within the area of the dam.

SD-07 Certificates

OPSEC Training; G, RO

1.4 DRAWINGS

1.4.1 Contract Drawings - General

The contract drawings reflect the work to be performed under this contract. The Contractor shall check all drawings immediately upon receipt, and verify the figures, dimensions, and representation of the work. The Contractor shall compare all drawings and verify the figures before laying out the work. Dimensions marked on drawings shall, in general, be followed in preference to scale measurements. The Contractor shall promptly notify the Contracting Officer of any discrepancies, and shall be responsible for any errors which might have been avoided by complying with this paragraph. Any omissions from the contract drawings and specifications or incorrect description of details of the work which are manifestly necessary to carry out the intent of the contract drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or incorrectly described details of work, but shall be performed as if fully and correctly set forth and described in the contract drawings and specifications. Unless otherwise noted, dimensions and elevations, and other features shown on contract drawings are based on site surveys and measurements, and As-Built drawings. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the contract drawings which are based on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government.

SECTION 01 35 00.00 08 Page 4

1.4.2 Government-Furnished Material Drawings

The Government-furnished material drawings included in the folio of contract drawings are the as-awarded contract drawings for the purchase of the Government-furnished lift gates and associated components identified in Section 01 73 19.00 08 GOVERNMENT-FURNISHED PROPERTY. To the best knowledge of the Government, the Government-furnished material drawings reflect the as-fabricated condition of the items. The Government cannot guarantee the accuracy of the dimensions and features shown on the reference drawings, and it shall be the responsibility of the Contractor to verify all dimensions shown by measurements in the field, at no additional cost to the Government. The Contracting Officer shall be notified of any discrepancies prior to commencing work.

1.4.3 Reference Drawings

The reference drawings included in the folio of contract drawings show original construction conditions of the original lock and dam and the existing facilities and structures shown on the drawings. To the best knowledge of the Government, the reference drawings reflect the original work incorporated into this project, and do not reflect changes or new work since the date of the drawing. Unless otherwise noted, dimensions and elevations, and other features shown on reference drawings are generally based on As-Built conditions. Where known variations in actual construction occur between that shown on the reference drawings and that existing, it will be noted on the drawings or within the specifications, as practical. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government. The Contracting Officer shall be notified of any discrepancies prior to commencing work. It is noted that some of the As-Built conditions reflected by the reference drawings have since been modified. Such modifications to the As-Built conditions are described within the sections of these specifications where applicable.

1.5 WORK UNDER OTHER CONTRACTS

Attention is directed to the fact that other Contractors may be employed by the Government at or in the vicinity of the work covered by these specifications. It is noted that the information provided is for the Contractor's information, and no attempt has been made to list all the work activities required under those contracts. Unless specified otherwise, all Contractors shall have equal rights to the use of access roads and other areas which are not identified on the Contract Drawings as work areas or laydown areas for specific contractors, so far as practicable, and the Contractor employed under this contract shall cooperate with other Contractors so that the work may be performed with maximum efficiency. Should a disagreement occur between Contractors as to the use of facilities or in other matters, the decision of the Contracting Officer shall govern. See also Section 00800 SPECIAL CONTRACT REQUIREMENTS, clause WORK UNDER OTHER CONTRACTS. See also paragraph Protection of Existing Roads and Property.

1.6 1.4 CONSTRUCTION SITE PLAN

Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, SECTION 01 35 00.00 08 Page 5 equipment and material storage area, and access and haul routes, avenues of ingress/egress to the work area). Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas. All areas must be limited to the Government provided lands as shown on the Drawings.

1.7 WORK AREAS AND RESTRICTIONS

1.7.1 General

The work under this contract shall be performed at Montgomery Locks and Dams, Ohio River, Beaver County, Pennsylvania. The Montgomery facility is located 31.7 river miles downstream of the point in Pittsburgh. Dual lock chambers are located at the left bank of the channel. Access to the dam is made from the dam abutment on the right bank and from the locks on the left bank.

1.7.2 Work Areas

The work areas under this contract shall be at the dam. As required by Section 00700 CONTRACT CLAUSES, 52.236-10 OPERATIONS AND STORAGE AREAS, all operations of the Contractor shall be confined to areas shown on the drawings required to accomplish the work under this contract and as authorized and approved by the Contracting Officer. The limits of the Contractor's work areas are as shown on the Contract Drawings. All work areas shall be coordinated with the Contracting Officer prior to commencement of work.

1.7.3 Access Plan

The Contractor shall prepare a plan to address maintaining access to existing facilities and temporary access as required for construction of the various features of work. The plan shall address all requirements or conditions given in paragraphs Work Areas, CONTRACTOR'S FLOATING PLANT, OPERATION OF FACILITIES, CONDITIONS OF WORK, POOL LEVELS, and DISCHARGES, herein.

1.7.4 Access to Project Site

The Montgomery Dam may be accessed from the right abutment of the dam and the left bank at the locks. An area at the locks, as shown, will be reserved for Contractor parking, field offices, laydown, and storage. The Contractor will be provided parking areas as designated by the Contracting Officer. Access onto floating plant may be made from the lock walls, but will be closely coordinated with the Contracting Officer. The most direct access to the dam may be from the river. The Contractor shall investigate and arrange for all personnel access to the floating plant.

1.7.5 Protection of Existing Roads and Property

1.7.5.1 General

The Contractor's traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic.

The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for all damage to existing roads and property occasioned by any of his

SECTION 01 35 00.00 08 Page 6 operations. When intending to transport any heavy loads on roadways, the Contractor shall investigate all weight limits for the roads he intends to use and shall secure any required bond(s) from the respective owner(s).

The Contractor shall document the existing condition of the roadways that he will be using, with the owners thereof. In the past, video recordings of the original roadway conditions have provided satisfactory documentation. Prior to beginning any construction, the Contractor shall videotape on DVD format all existing structures including, but not limited to, local roads, public and private property, and any other areas as directed by the Contracting Officer. The owners of such roadways and other property should be present at the time of the documentation. An unedited copy of all video recordings shall be given to the owners and the Contracting officer with 5 calendar days after documented. All damage to transportation facilities, public or private property, or utilities caused by the Contractor's operations shall be repaired to the satisfaction of the Contracting Officer at no additional cost to the Government. Any damage to the roadways, caused by the Contractor's operations, shall be repaired in kind by the Contractor and at his own expense. Roads shall be kept clear of all debris generated by the Contractor's operations. Roads shall be cleaned of any spillage. Upon completion of all work requiring use of the local roads, the roadways shall be restored to their preconstruction condition by cleaning and or reconstruction of damaged drainage facilities, base courses, and pavements as necessary. Repairs shall be made in the same manner as the original construction. No separate payment will be made for maintaining and restoring the condition of the roads, and all costs in connection therewith shall be considered as incidental to performance of the work.

1.7.5.2 Hauling Permits

The Contractor shall be responsible for acquiring all necessary oversized hauling permits and general hauling permits for any equipment or debris transported via roadways, as required. No heavy hauling on public roads will be permitted until all permits and bonds have been obtained as required. All costs associated with securing these permits shall be borne by the Contractor.

1.7.6 Laydown, Storage and Parking Area

Laydown, storage and parking areas will be provided in an area located on the locks esplanade. The contractor may arrange for other areas as approved by the Contracting Officer. Laydown, storage or parking will not be permitted in the area located on the right dam abutment.

There are currently occupied storage areas located on the locks esplanade, as shown on plans, consisting of items associated with other Government work. These areas shall not be disturbed without the approval of the Contracting Officer. Additionally, there is potential for another Government Contractor to be concurrently on site for pickup and transport of these items. The Contractor shall coordinate work in this area closely with Contracting Officer to avoid conflict.

1.7.7 Utilities

The Contractor shall be responsible for coordination of all existing utilities with the work and for providing utilities for construction purposes. Utilities shall be coordinated in accordance with Section

01 50 00.10 UTILITY COORDINATION.

SECTION 01 35 00.00 08 Page 7

1.8 EXISTING SURVEY CONTROLS

Corps of Engineer survey controls are located on the top of lock walls.

These control points are shown on the drawings provided.

1.8.1 Project Alignment

All new work to be constructed under this contract shall be constructed level, plumb, and accurately from the control points established by the Government and/or additional survey controls established by the Contractor as necessary to construct all work within the proper alignment. The Contractor shall verify the elevations and positions of the Corps of Engineers survey controls before using them to layout the work under this contract, and shall notify the Contracting Officer of any discrepancies prior to commencing work. The Contractor shall utilize existing project monuments shown on the contract drawings to establish any additional control points for this work. The Contractor shall not use any monuments that are outside the Government's project limits to establish additional control points.

1.9 RESTRICTIONS TO RIVER TRAFFIC FOR CONSTRUCTION

Unless specifically authorized or directed, no interruption of traffic through the lock chambers or their approaches will be permitted.

1.10 PROTECTION AND MAINTENANCE OF ROAD TRAFFIC

During construction the Contractor shall maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. The traveling public shall be protected from damage to person and property. The Contractor shall submit his proposed traffic control plan for approval.

1.11 DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in Section 00700 CONTRACT CLAUSES, 52.236-7 PERMITS AND RESPONSIBILITIES. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such work, an equitable adjustment pursuant to the Section 00700 CONTRACT CLAUSES, 52.243-4 CHANGES, will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or job prices.

Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

1.12 PROTECTION OF UTILITIES

Utilities shall be protected as specified in Section 01 50 00.10 UTILITY COORDINATION, paragraph "Protection of Utilities".

SECTION 01 35 00.00 08 Page 8

1.13 OPERATION OF FACILITIES

The Montgomery Locks and Dams facility shall remain in operation at all times. The Contractor shall perform his work in a manner which will not interfere with the operation of the facilities and the duties of Government personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall take all necessary precautions to ensure the safety of the workers in accordance with the applicable provisions of EM 385-1-1 . Contractor operations shall be performed in such a manner to ensure that project personnel, navigation industry personnel and the public are protected at all times.

1.14 CONDITIONS OF WORK

1.14.1 Montgomery Locks and Dam, Hours of Operation

Montgomery Locks and Dam operates 24 hours per day, seven days per week.

1.14.2 Contractor's Work Hours

There will be no restrictions imposed on Contractor's work hours for this project.

1.14.3 Coordination with Lock Operations

The Contractor shall perform all work in a manner that will not interfere with the duties of the lock personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall continuously maintain safe access to all areas of the lock project for lock operating personnel, during every phase of the work, unless otherwise directed by the Contracting Officer.

1.14.3.1 Restrictions to River Traffic for Delivery of Products

No interruption of traffic through the lock chambers or their approaches will be permitted. The Contractor will not be permitted any priority lockage privileges for delivery of the equipment, materials or supplies.

1.14.3.2 Installation and Removal of Dam Bulkhead

The dam bulkhead must be in place for work within the gate bay. The Contractor will not be permitted to place equipment or personnel downstream of the existing gate or perform any work on the existing gates until the bulkhead is in place. Work may be performed on the tops of the dam piers without the dam bulkhead in place. The project bulkhead used for dewatering dam bays is formed of three structural units that are stacked vertically on top of one another to form the closure. Government personnel will conduct all operations necessary to install and remove the bulkhead in a gate bay. In general, installation of the complete bulkhead takes approximately 2 to 4 hours. It is brought to the Contractors attention that once the bulkhead is installed, there will be extensive leakage in the form of spray at the joints between the individual units, and along the side seals. Leakage may occur along more than 50% of the length of the joints. The Contractor shall be responsible for furnishing and installing any tarps, sheeting, neoprene seals, or other materials that are necessary to control this leakage and keep it from the affecting

SECTION 01 35 00.00 08 Page 9 the Contractor's work. The Contractor's construction schedule, submitted in accordance with Section 01 32 17 CONSTRUCTION PROGRESS SCHEDULE, shall show the time periods that the bulkhead will be required. The Government may use the bulkhead temporarily during periods in which the Contractor does not require it. Any such Government use will be coordinated through the Contracting Officer. The Contractor shall give a 14 calendar day written notice to the Contracting Officer as to when the bulkheads will need to be placed and 14 calendar days written notice when they will require removal. Bulkheads will be set and removed from each bay only once during the contract unless otherwise approved by the Contracting Officer.

1.14.4 Government Service Crane and Bulkhead Hoist

The Contractor will not be permitted to use the Government's service crane or bulkhead hoist for any purposes under this contract. The Contractor shall provide all necessary cranes for lifting equipment.

1.14.5 Dam Gate Operating Schedule

The dam gate operating schedules attached at the end of this section are applicable for governing gate movements by the Government at Montgomery Locks and Dam for the operating conditions during the period of this contract. This schedule will be the basis for minimizing the effect of flow through the dam on the work at the site and maintaining customary river stages above the dam. The schedule REPAIR OF GATE 3 WITH GATES 2 AND 4 RESTRICTED, ALL REMAINING GATES IN SERVICE will be in effect for the replacement of Gate 3, the schedule REPAIR OF GATE 2 WITH GATES 1 AND 3 RESTRICTED, ALL REMAINING GATES IN SERVICE will be in effect for the replacement of Gate 2, and the schedule REPAIR OF GATE 1 WITH GATE 2 RESTRICTED, ALL REMAINING GATES IN SERVICE will be in effect for replacement of Gate 1. The schedule CLOSE GATE 4 WITH GATES 3 AND 5 RESTRICTED will be in effect for the repair of the coatings of Gate 4.

1.14.6 Operation of Dam Gates During Contract Work

All dam gates, except the one being replaced, shall be operable at all times during the contract period.

The Contractor should review the plan for replacement of the gates with the gate schedules provided, along with the hydrographs, rating curves, and duration curves to determine the influence that river conditions may have during the on site portion of the work under this contract.

It is noted that work within any particular bay can proceed without operating the gates in adjacent bays up to a total operational gate opening of 35 feet. If forecasted river conditions indicate additional total operational gate opening beyond 35 feet will be required, one of the gates in the adjacent bays would be opened. The Contractor's floating plant must be withdrawn from the gate bays and moored before gate operations occur in adjacent bays. See paragraph Withdrawal of Equipment and Floating Plant for additional details. As total operational gate opening approaches 35 feet, close coordination with the Lockmaster is required. The Contracting Officer may instruct the Contractor to move the floating plant before a total operational gate opening of 35 feet if the Lockmaster determines it necessary to maintain the safety of the project site. No additional gate operations will be conducted in support of any other work, unless specifically authorized by the Contracting Officer.

The Contracting Officer will have sole authority to review all requested

SECTION 01 35 00.00 08 Page 10 modifications to dam gate operations, and to what degree to accommodate active contract work. The Contractor may request in writing temporary adjustments to gate operations to accommodate active work, but such requests shall be given to the Contracting Officer a minimum of 30 calendar days in advance of the requested change. Approval of such changes shall rest with the Contracting Officer who's decision shall be final. Implementation of any approved modifications to the gate operations on the date(s) requested shall be subject to river conditions, and may be delayed or altered as necessary to accommodate the prevailing river (flow) conditions and shall not be considered as a basis of a change condition. All gate operations shall be performed by Government personnel.

1.14.7 Warning Signs, Lights and Buoys

The Contractor shall be required to furnish and install all buoys, lights, signs, and other safety devices as required by Coast Guard rules and regulations. All equipment and devices shall be Coast Guard approved.

1.14.8 Contractor Coordination and Scheduling

In accordance with Section 01 32 17 CONSTRUCTION PROGRESS SCHEDULE, the Contractor shall submit a project schedule for his work to the Contracting Officer. All necessary adjustments in the Contractor's work schedule shall be coordinated and approved by the Contracting Officer.

1.15 EMERGENCY USE OF BULKHEAD UNITS

The Contractor's attention is directed to the fact that, should a situation occur which would require use of the bulkhead at another gate bay, the Contractor will be directed take one of the following actions within four hours after notice by the Contracting Officer, depending on the status of gate installation:

a. If the original lift gate is in place on the gate sill with end trucks in place, The Contractor shall remove all equipment and materials that would be affected by removal of the bulkhead from the gate bay. However, items which would not be affected may remain in place provided they do not interfere with removal of the bulkhead units. No work will be permitted downstream of the existing lift gate.

b. If the new lift gate is in place on the gate sill with end trucks in place, The Contractor shall remove all equipment and materials that would be affected by removal of the bulkhead from the gate bay.

However, items which would not be affected may remain in place provided they do not interfere with removal of the bulkhead units.

Floating plant may remain in place downstream of the new gate and work which does not directly impact the gate may continue.

c. If no gate is in place, or if the gate body is not secured to the end trucks in the gate recesses, the Contract shall remove the gate body and end trucks, if present, and remove all equipment, scaffolding, and other materials from the gate bay and remove floating plant from the dam, as directed. Equipment and materials shall be removed to the extent necessary to permit the Government to install concrete gravity blocks on the gate sill downstream of the bulkhead, however, support items which do not interfere with this placement may remain in place. The Government will not be responsible for any damage to materials and equipment in the gate bay in the event they are not removed by the Contractor in a timely manner.

SECTION 01 35 00.00 08 Page 11

Payment for removal and replacement of equipment and materials to permit removal of the bulkhead units and installation of the concrete gravity blocks, if necessary, and removal and replacement of floating plant will be made as specified in Section 00700 CONTRACT CLAUSES, FAR 52.243-4 Changes. A payment will be made each time the work is directed. The time allowed for completion of work will be adjusted to include the time for the period from the Government's initial directive to stop work until the time that the Contractor is directed to resume work. Payment for repair of damage to work which has been completed will be made in accordance with Section 00700 CONTRACT CLAUSES, FAR 52.243-4 Changes.

1.15.1 Installation of Concrete Gravity Blocks

The following is provided for the Contractor's information only, all work will be performed by the Government.

a. In the event that the bulkhead must be removed, the Government will install a temporary closure in the gate bay consisting of precast concrete blocks and miscellaneous sealing items. The gravity blocks will be installed on the gate sill downstream of the bulkhead, and may extend past the bottom portion of the gate recess.

b. The Government will remove the bulkhead units and place them in another gate bay as required.

c. The Government will remove any obstructions in the gate bay and install a second set of gravity blocks in the gate bay.

d. When the temporary closure is completed, the Government will remove the bulkhead units from the gate bay and reinstall them in the gate bay in which the Contractor is working.

e. The Government will remove the gravity blocks from the gate bay in which the Contractor is working.

1.16 CONTRACTOR'S FLOATING PLANT

1.16.1 General

Floating plant, and the operation of such plant, shall comply with the requirements of EM 385-1-1 , Section 19. Floating plant which is not being used in the performance of the work shall be secured in a manner that does not interfere with navigation on the river. Emergency plans for removing or securing floating plant and evacuating personnel in the event of severe weather shall be prepared in accordance with EM 385-1-1 , Section 19.A.03.

The Contractor shall provide personnel as necessary to adjust moorings to provide for fluctuations of pool level. A propelling unit capable of moving the floating plant must be available at all times. If the Contractor chooses to have a leased towboat or propelling unit off-site, the plant must be capable of being on-site within 4-hours notice. The written propelling unit agreement between the Contractor and the lessor documenting this requirement shall be provided to the Contracting Officer prior to mobilization of any floating plant. The agreement shall also include documentation that the propelling unit operator currently possesses a U.S. Coast Guard "Operator of Uninspected Towing Vessels" license. The Contractor shall be fully responsible for selection of floating plant which is suitable for the performance of the work under this contract.

SECTION 01 35 00.00 08 Page 12

Contractor's floating plant shall operate only within the areas of work shown on the drawings, unless such areas are modified with the approval of the Contracting Officer and Lockmaster.

1.16.2 Equipment Requirements

The Contractor shall select floating plant and towboats and propelling units of a size and capacity suitable for performance of the work under this contract. Towboats and propelling units shall have sufficient horsepower capacity to control the floating plant used, considering the size and draft of the plant, for the expected river velocities and wind conditions. The minimum size of towboats shall be 1,000 horsepower. The Contractor shall submit a plan of all floating plant, floating plant based equipment (i.e. cranes, derricks), temporary operating systems (i.e.

generators, compressors, welding machines, etc.), and other appurtenant features which he will have present during the contract period. The Contractor shall use sketches, diagrams, and narratives to indicate location of all floating plant-equipment. The Contractor shall use manufacture catalog information or other suitable data to describe the specific equipment to be used. The Contractor shall also indicate the methods and procedures that will be used to deliver materials, supplies and equipment via floating plant.

1.16.3 Signal Lights and Markers

The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard, as set forth in NAVIGATION RULES or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (inland) as applicable. The Contractor shall be required to furnish and install all buoys, lights, signs, and other safety devices as required by Coast Guard rules and regulations. All equipment and devices shall be Coast Guard approved.

1.16.4 Maintenance of Floating Plant

The Contractor shall maintain all floating plant equipment in good working condition throughout the contract period.

1.16.5 Mooring of Floating Plant

The Contractor shall be responsible for all mooring of floating plant.

When not in use, the Contractor's floating plant shall be securely moored. The Contractor shall also be solely responsible for providing personnel in order to adjust mooring lines as required by the prevailing river conditions.

Floating plant may remain downstream of the dam during non-working time with consideration of the exceptions noted in paragraphs "Operation of Dam Gates during Contract Work," and "Withdrawal of Equipment and Floating Plant," herein. Without exception, all floating plant and equipment shall be removed from any position downstream of the dam when the total dam gate openings exceed 40 feet.

Floating plant may be moored to the riverward face of the upstream river wall when the upper gage is below 16.0 as shown on Drawing C-1135 However, this plant must be completely removed and secured at an off site location that is no closer than 1 mile from the site, by the time the upper pool river gauge reaches 20.0.

SECTION 01 35 00.00 08 Page 13

Withdrawal or relocation of floating plant shall be completed within four

(4) hours of any notice from the Contracting Officer or Lockmaster.

1.16.6 Suspension of River Traffic and Construction

1.16.6.1 Withdrawal of Equipment and Floating Plant

All floating plant shall be withdrawn from a gate bay when the projected total operational gate opening is forecasted to reach 35 feet or greater.

Once the total operational gate opening reaches 35 feet, floating plant may temporarily moor to the outside of the Lower Guard Wall directly below the spillway as long as the total gate opening is not projected to reach above 39 feet. This must be closely coordinated with the Lockmaster. If the total operational gate opening is forecasted to reach 40 feet or greater, the equipment shall be relocated to the outside face of the upstream river wall or to the Contractor's off-site mooring location. The decision of whether the Contractor's plant may be moored to the upstream River Wall will be determined on the basis of the projected upstream pool level. When the upstream pool level reaches an elevation of 686.00 (U/S Gage = 16), the Contractor shall begin preparations to move the floating plant. If the upstream pool level is expected to reach an El. of 690.0 (U/S Gage = 20) then mooring of the plant at the off-site location will be required. The Contractor shall monitor the prevailing river conditions at the project site, referring to the upstream project river gauge, river forecasts issued by the National Weather Services, and the Corps of Engineers River Forecast System, and shall determine when to withdraw equipment and floating plant. Projected dam gate operations shall be coordinated with the Lockmaster and Contracting Officer. The withdrawal of equipment and floating plant shall ultimately be the Contractor's decision and will not be directed by the Government. It shall be the Contractor's responsibility to determine the time necessary to make a complete and safe withdrawal of equipment and floating plant with due consideration given to the location of mooring area; amount of equipment;

size of the floating plant, and capacity of towboats and propelling units to operate safely and efficiently at the expected river velocities. All floating plant and equipment shall remain securely moored during the period that gate openings exceeds 40 feet or when the pool is at or above the specified level. The Contractor shall also be responsible for providing personnel during the suspension to adjust mooring lines as required by the prevailing river conditions. The Contractor shall resume all work, and remobilize equipment and floating plant from its moored location when gate openings at the dam fall below 35 feet. The Contractor shall submit a Plan of Action for withdrawal of equipment and floating plant. The plan shall be submitted for the Government's review prior to the start of work. The Contractor is advised that the plan must be submitted and accepted or no work at the site will be allowed.

1.16.6.2 Plan of Action, Withdrawal of Equipment and Floating Plant

The Contractor shall prepare and submit a Plan of Action for withdrawal of equipment and floating plant. The plan shall detail the procedures for withdrawal of equipment and floating plant in the event that suspension of river traffic and work is imminent. The Plan of Action shall include but is not limited to the following information:

- Procedure(s) For Monitoring River Conditions Including River Levels, Discharges, And Velocities

- Mooring Location(s)

- Monument River Condition Which Affect Notification Actions

SECTION 01 35 00.00 08 Page 14

- Monument River Conditions Which Affect Withdraw

- Sequence and Duration of Withdraw

- Procedures for Care of Moored Floating Plant and Equipment

- Monument River Conditions Affecting Remobilization

- Sequence and Duration of Remobilization

The Plan of Action shall include a listing of key Contractor's Points of Contact and telephone numbers. The Plan of Action shall include the withdrawal of any subcontractor's equipment and floating plant. The Contractor's Plan of Action shall be consistent with the applicable requirements for Emergency Planning as described in EM 385-1-1 . All key Contractor personnel including superintendents, foremen, safety officers, and QC personnel shall be given a copy of the Plan of Action and shall be thoroughly familiar with their duties under this plan. Subcontractors shall also be thoroughly familiar with their responsibilities and duties under the plan.

1.16.6.3 Compensation and Extension of Contract Period, Suspension of Work

The Contractor's withdrawal of equipment and floating plant shall not be construed as a direction on the part of the Government or Contracting Officer, under the provisions of Section 00700 CONTRACT CLAUSES, 52.242-14 SUSPENSION OF WORK, which shall not apply to this work condition. No compensation will be made to the Contractor for withdrawal of this equipment nor will any delay costs be made for the period during which work cannot be accomplished.

The contract period will be extended for the withdrawal of floating plant and equipment under this paragraph for unusual high water events in accordance with the Section 00700 CONTRACT CLAUSES, FAR 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension under this paragraph, the following conditions must be satisfied.

a. The high water events experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the high water events anticipated for the project location during any given month.

b. The unusual highwater events must actually cause a delay to the completion of the project. This delay must be beyond the control and without the fault or negligence of the Contractor.

The following schedule of monthly anticipated high water events is based on historic information for a similar project in the vicinity of the work location and will constitute the base line for monthly high water time evaluations. The Contractor's progress schedule must reflect these anticipated adverse high water event delays in all weather dependent activities. See also paragraph SEQUENCE OF WORK AND RESTRICTIONS, subparagraph Restrictions on Work at Montgomery Dam.

MONTHLY ANTICIPATED HIGH WATER EVENTS

WORK DAYS BASED ON FIVE DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

9 9 14 11 7 3 1 2 2 2 4 10

Upon acknowledgment of the Notice to Proceed and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of high water events and resultant impact to normally scheduled

SECTION 01 35 00.00 08 Page 15 work.

This is the start of the file's text. The full file is on GovTribe.