SEE SCHEDULE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
RE: W911WN-15-T-0030 Hydraulic Pump System, Allegheny River Lock 8 and 9
The purpose of this amendment is to provide responses to questions received.
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-May-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911WN-15-T-0030
X 9B. DATED (SEE ITEM 11)
14-May-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-May-2015
CODE
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CELRP-RC-P
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2203
PITTSBURGH PA 15222-4186
W911WN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
Michelle.L.Anderson@usace.army.milEMAIL:412-395-7417TEL:
MICHELLE L ANDERSON / CONTRACTING OFFICER
W911WN-15-T-0030
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND ANSWERS - 1
Solicitation: W911WN-15-T-0030 Project: Hydraulic Pump Systems with Structural Steel Support Frames
Questions and Answers - 1
Q1. Is there an OEM for the system?
A1. These hydraulic pumping systems are comprised of on the shelf items (pumps, motors, piping, valves, etc..) meeting the specifications. A potential vendor would need to piece that system together to meet the requirements. The only custom fabrication would most likely be the steel frame.
Q2. Does the U.S. Army Corps of Engineers have a preference on the manufacturer of the hydraulic pumps & motors?
A2. Imo Pump is the preferred hydraulic pump manufacturer, and Baldor the preferred motor manufacturer. However, any suitable pump and motor will be considered.
Q3. Would the U.S. Army Corps of Engineers like the contractor to attempt to duplicate the existing HPU set up as shown in the pictures, or attempt to replicate the existing layout of the HPU’s equipment?
A3. The USACE would prefer the contractor to attempt to duplicate the existing HPU set up as shown in the photographs of previous HPUs acquired for Allegheny Locks and Dams 6 and 7.
Q4. Is it possible to schedule a visit with at locks 8 & 9 to review the existing HPUs and their location so that any limitations in the space can be considered (ie: Paragraph 2.5.1 states the length of the hydraulic reservoir may be limited due to space limitations)?
A4. The HPUs requested in this contract will be installed at an alternate location from the existing HPUs.
A site visit to Allegheny Locks and Dams 2 (Pittsburgh, PA), 3 (New Kensington, PA), 6 (Freeport, PA), or 7 (Kittanning, PA) is recommended to view the general layout for installation. For requests to visit any of the Locks and Dams listed above, please contact Contract Specialist, Tony Abate at anthony.abate@usace.army.mil or 412-395-7474 for a Point of Contact (POC) and information.
Q5. The specifications call for flexible lines, which we assume are to allow for an easy fit up with existing supply and return lines. Is there a required length for the flexible hoses? The pictures show flex hoses that appear to be at least 4’ in length.
mailto:anthony.abate@usace.army.mil
A5. Approximately 30’ of flex hose for each hydraulic line is required.
Q6. Refer to Specifications - Paragraph 2.1.2.2 Capacity: Please confirm that the operating viscosity range (225 to 1000 SSU) is correct.
A6. This viscosity range is correct.
Q7. Refer to Specifications – Paragraph 2.1.4 Pump Assembly Base: Are machined steel pump-motor adapter installations permitted in lieu of foot-mounted and aligned pump/motor installations for this project?
A7. No. Foot mounting and gear type flexible couplings as specified in Specifications Paragraph 2.1.2.1 are the preferred method of connecting pumps to motors in assemblies such as these.
Q8. Refer to Specifications – Paragraph 2.1.5.2 Oil Filter: Can USACE provide information about the “greater system” that would assist with a designer selecting an appropriate filter?
A8. Shop drawings and additional information from previous Hydraulic Pump Systems contracts for other Allegheny Locks will be made available to the vendor awarded the contract.
Q9. Refer to Specifications – Paragraph 2.1.5.2 Oil Filter: This specification section mentions a drawing.
I was unable to locate a drawing or schematic of the desired power unit(s) in the FBO Solicitation posting. Can you please advise if a drawing and/or schematic is available?
A9. Shop drawings and additional information from previous Hydraulic Pump Systems contracts for other Allegheny Locks will be made available to the vendor awarded the contract.
Q10. The USACE’s responses to the above questions will significantly affect the design of the proposed hydraulic power unit. In light of this, can a two or three week extension be offered to give bidders enough time to assemble well thought out and engineered equipment proposals?
A10. The bid will not be extended. The Bid Due Date is still 15 June 2015.
Q11. Refer to Specifications Paragraph 2.1.2.1 General:
a) Can the USACE please clarify what is meant by the specification text: “Operating demands on the pump will vary from maximum rated delivery to the low volume demands required when starting, stopping or inching miter gates and operating emptying and filling valve cylinders”?
b) Will the specified fixed displacement pumps be used (presumably with speed [VFD] controlled motors) to deliver a range of flow rates?
A11. The pumps shall be fixed displacement, constant speed. Inching operations are achieved by modulating the manually-operated four-way valve.
Q12. Refer to Specifications Paragraph 2.1.2.1 General:
a) Can the USACE please advise if Joint Industrial Council (JIC) type reservoirs are to be used, but suitably modified to resist the stated leak test pressure?
b) In this case, should the single-bolt end access covers typical of JIC type reservoirs be eliminated or be replaced by access covers of a different construction (deviating from JIC norms) to resist the test pressure? Or should reservoirs that “strictly” conform to JIC standards be used and tested at an appropriately low (and safe) pressure for leaks?
c) Alternatively, can/should the “Joint Industrial Council” wording in the specification be disregarded?
d) If standard JIC style reservoirs are allowed and the specified test pressure is maintained at 10 psi, will bidders that choose more conservative and safe designs be offered special consideration by the USACE over those that choose to test (unsafely in INSYSMA’s opinion) standard JIC reservoirs at pressures above their ratings?
A12. JIC type reservoirs with single-bolt end access covers are acceptable. Use a test pressure that is appropriate for JIC reservoirs. Bidders are encouraged to review and submit their bids based on the information in the Specifications.
Q13. Refer to Specifications Paragraph 2.1.3.1 Rating: The single phase requirement of this specification section was just noticed. It is unusual for motors of this size (15 or, perhaps 20 horsepower) to operate on single phase power. To meet this requirement with the other specification requirements, custom motors will likely be required. Can the USACE please confirm that single-phase motors are, indeed, required?
A13. Correct. Only single-phase power is available.
(End of Summary of Changes)