This document contains the Questions and Answers for Request for Information (RFI) W911SG24B0010 for the WSMR Repair RR7 Culverts project. The RFI provides clarification on several aspects of the planned construction work, including the locations and lengths of the culverts to be replaced, the requirements for grading and asphalt, the use of fire hydrants and borrow pits, and the specifications for the bypass roads. The responses indicate that the project will involve replacing 4 culverts along Range Road 7 at WSMR, with 48-inch corrugated metal pipes rather than precast concrete box culverts as initially stated. The bypass roads will be constructed of compacted dirt rather than temporary paving. The contractor will be responsible for coordinating with the COMMO department and disposing of demolition materials. The solicitation for this project, W911SG-24-B-0010, is a Firm-Fixed Price construction contract set aside for Service-Disabled Veteran-Owned Small Businesses, with an anticipated delivery date of 365 days after the Notice to Proceed.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI QUESTIONS AND ANSWERS
W911SG24B0010
WSMR Repair RR7 Culverts
1) Sheet 4 drawing: Plans call to remove and replace culverts 4 separate locations, Culvert 1, 32.7890, -106.4838, Culvert 2, 32.7801, -106.4761, Culvert 3, 32.7771, -106.4762, Culvert 4, 32.7670 -106.4696, please provide for starting points and end points for each culvert location.
ANSWER: Means and methods are not dictated by the Government.
2) Sheet 05 Note 2 – Replace Rd. Please provide start and end points of road replacement.
ANSWER: Means and methods are not dictated by the Government.
3) Sheet 05 Note 3- States for the contractor to re-grade the arroyo streambed and side slopes 50’ from end of culvert on both sides. Please confirm this is limited to the 4 new culvert locations.
ANSWER: 50’ is the limit of the grading, please be aware that on the east side there is the WSNP fence that will limit the grading. Grade up to the fence without disturbing it.
4) Per sheet 09 note 1. There are Commo lines along the East side of Range Road 7 the contractor shall protect the Commo lines. Commo lines will need to be placed in a split duct system and encased in concrete. Will there be a need to cut the wire, lower, and reconnect?
ANSWER: No, contractor will need to coordinate with the COMMO department via COR.
5) Please prove detail for grading and asphalt on top of the new culverts, for example we need depth for cover fill on top of the culverts
ANSWER: Follow NMDOT standards for minimum cover.
6) There are not details for guard rails, or concrete parapet to protect traffic from falling into the arroyo. Please confirm it will stay open or will need guardrails or enlarged headwall.
ANSWER: No guardrail required.
7) Please provide dimensions on the win walls and aprons.
ANSWER: Follow NMDOT standards for dimensions.
8) Pg 52 of the solicitation Scope of work states “The project consists of constructing 8 – 10 X 12 pre‐fab concrete box culverts with wing walls and aprons” please confirm this is correct information. The roadway shall be reconstructed as per plan sheets. The plans do not depict the installation of a prefabricated concrete box culverts. Will the government please clarify where the concrete box culverts are to be installed on the plans?
ANSWER: This project does not require precast box culverts. Each culvert requires 48” CMP.
9) A fire Hydrant is located at mile marker 10 on Range Road 7 at Verna. This fire hydrant is approximately 10 miles closer to the construction site. Can the contractor be allowed to use the fire hydrant at Verna?
ANSWER: Yes, contractor can also use the water source at MM 13 on RR 7. This water source will require a backflow preventor and contractor must supply standpipe.
10) Enough borrow material does not exist to construct the bypass road at the Government Specified Borrow location. Will the government specify a secondary borrow pit that contains required amount of material necessary to construct the bypass road?
ANSWER: Bypass road will now be broken into 4 small bypass roads and each culvert.
11) Can the Government specify how much material is available at the government specified borrow location(s)?
ANSWER: No
12) Rather than a bypass road that extends the length of all 4 culvert locations, constructing a bypass road at each separate culvert location would require less borrow material, therefore the cost to build would be less. Will the government allow the contractor to construct the bypass road at each separate culvert location?
ANSWER: Bypass road will now be broken into 4 small bypass roads and each culvert.
13) Are there a specific length of culvert runs for the bypass?
ANSWER: Bypass is 30’ wide
14) Are there a specific length of culvert runs for the main road (RR7)?
ANSWER: Permanent culvert CMP is 70’ for each run.
15) Has there been a geotechnical report done on borrow pit and bypass road native soils?
ANSWER: No
16) Can SPIV be used instead of SP III asphalt?
ANSWER: Yes
17) Will construction water be provided at no cost to contractor for this project?
ANSWER: Construction water is at no cost to the contractor.
18) Which specs will be used to govern this project?
ANSWER: NMDOT
19) Can pictures be provided for all four work sites?
ANSWER: Pending OPSEC approval
20) Will the bypass road be (1) continuous road or can it be (4) individual detours?
21) Will the existing hydrant on south end need modification to allow for construction water extraction?
ANSWER: No
22) Will SWPPP with approved plan be required?
ANSWER: No
23) Will the existing range road 7 asphalt demo be only what is needed to allow for new culverts installation?
ANSWER: Yes
24) Will there be any existing utilities that will have to be relocated?
ANSWER: Contractor is required to call for locates, COMMO will be placed in a split duct system by contractor.
25) Will demo’ d materials (asphalt, and existing culverts) be disposed of on site, or does it have to be removed off White Sands Missile Range property?
ANSWER: 9. Contractor shall remove and dispose of any existing asphalt pavement or rigid concrete. Contractor shall dispose rigid concrete at the WSMR Hughes Reclamation Area (Main Cantonment) located at the intersection of Watertown and Hughes Ave. Rigid concrete shall be free of rebar and/or all debris. Contractor shall provide a report to the COR of quantities disposed of.
26) Will be bypassing road be dirt or asphalt?
ANSWER: Dirt
27) Has there been an existing topo done on bypass road work zones?
ANSWER: No
28) Is there an estimated quantity of fill material needed for bypass road?
ANSWER: Estimated Quantities for each bypass are approximately 45CY.
29) How much testing will be required for the bypass road (subgrade, base, and asphalt)?
ANSWER: Subgrade is required to be tested. There is no base or asphalt.
30) Have all work zones been cleared for possible unexploded ordnances?
ANSWER: Yes
31) Will existing berms in bypass road work zone areas have to be removed and rebuilt?
ANSWER: Berms do not have to be replaced.
32) Has there been an estimated down time due to road closures?
ANSWER: No
33) Can we get the specs for the backflow prevention device needed for fire hydrants?
ANSWER: Yes, please see document, “BPDI_975XL2 – 2_-Spec-Sheet,” posted to SAM.gov.
34) Is the 30’ called out for the bypass road toe of slope to toe of slope or edge of road to edge of road?
ANSWER: Edge of road to edge of road
35) What is the dimension of the Apron from the face of the culvert to the end of the Apron on page 06, figure “D8”?
ANSWER: Refer to NMDOT standards.
36) What kind of threaded Rod Anchor will be used, and how big (size). And how many anchors per pipe end, all this on page 07?
ANSWER: Refer to NMDOT standards.
37) Do you have any details on the transition of thickness on page 07, figure “D10”, dimension “H” to Apron thickness on page 06, figure “D7”?
ANSWER: Refer to NMDOT standards.
38) Is the contractor responsible for placing the COMMO lines inside the spit duct system or is something somebody else will do. All these on page 09?
ANSWER: Contractor places COMMO in Duct.
39) Plans request for 1 bypass road to match the length of the current?
40) Confirm the bypass roads do not have any temporary base course/asphalt paving on them, only compacted dirt?
ANSWER: Compacted dirt only.
41) Are we installing 4 CMP at each location as per drawings or just replace what was taken out, example remove 2 pipes install 2 CMP?
ANSWER: 4 CMPs for temporary culverts, 5 for permanent culverts.
42) Page 4 note 5 states 4, 36" CMP for bypass but would you consider 2 since it is temporary and will be taken down once that section is completed?
ANSWER: No
43) Are we installing the same length of pipe as listed on demolition notes, page 6?
ANSWER: Yes, each run is 70’.
44) What is the space in between each CMP?
ANSWER: Refer to sheets 4 and 5 in the plan set.
45) Are any of the existing culverts at a skew? If so, can you please provide the skew for each location?
ANSWER: The alignment of the CMP shall be skewed to match the existing arroyo, align with the center of the arroyo's flow path crossing the road.
46) Would you consider changing the asphalt mix from SP-III to SP-IV? The local supplier doesn’t carry a SP-III mix.
ANSWER: Yes
47) Are the two additional temporary CMP Crossing on sheet 4 note 5 to be built per note 4 of sheet 4?
ANSWER: The two additional CMP crossings are now eliminated.