December 2019 Seal Coat IDIQ – South 11th Avenue Scope - 1
SCOPE OF WORK
P1820 Crack Seal and Seal Coating IDIQ
Seal Cracks and Seal Coat South 11th Avenue
Fort McCoy, WI
W.O. # 2738
1. Contractor shall provide all tools, labor, equipment, supervision, transportation and materials necessary to seal cracks and apply 2 coats of asphalt mastic sealer on South 11th Avenue from South A Street to the eastern cantonment boundary at Building 1024. Work is to be done in accordance with all existing Federal, State and local codes and industry standards.
2. This project has four phases:
A. Clean and prepare all roadway cracks and seal all cracks with crack seal compound for the entire length of the scope. Remaining quantities of crack sealer shall be placed on roadways found elsewhere on Fort McCoy cantonment area roadways. A map containing additional crack sealing locations shall be provided by the COR.
B. Clean and prepare entire roadway surface and apply two coats of asphalt mastic sealer on entire length and width of roadway defined in this scope.
C. Apply roadway striping consisting of centerline skips and fog lines for entire length of roadway defined in this scope. All crosswalks and stop lines will be completed by Fort McCoy Directorate of Public Works Shops.
D. Provide and deliver forty four tons of cold mix asphalt patch material to Fort McCoy for stockpiling for Roads and Grounds maintenance and repair use.
Coordinate stockpile location for material stockpile with COR and with DPW Environmental Division prior to delivery of material.
3. The Contractor shall coordinate all traffic control work with COR and with Fort McCoy Directorate of Emergency Services. Contractor shall provide COR and Fort McCoy Directorate of Emergency Services with a Traffic Control Plan for entire duration of project.
4. Contractor shall provide a construction schedule to the COR two weeks prior to commencement of work.
5. The Contractor shall submit a safety plan to the Contracting Officer prior to any work commencing. All work shall comply with all appropriate OSHA regulations and standards pertaining to the type of work being performed.
6. The Contractor shall provide all warranty information to the Contracting Officer prior to inspection. This shall include all as-built drawings, serial numbers, and model numbers, if applicable.
7. Access and General Protection/Security Policy and Procedures
FOR OFFICIAL USE ONLY
December 2019 Seal Coat IDIQ – South 11th Avenue Scope - 2
a) The contractor and all associated subcontractors’ employees shall provide all information required for background checks to meet installation access requirements to be accomplished by Director of Emergency Services or Security Office.
b) Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and /or local policy.
c) The contractor and all associated subcontractors’ employees shall also comply with adjudication standards and procedures using the National Crime Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation /facility access and local security policies and procedures (provided by government representative).
d) In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
e) The Government may require monthly participation in the Installation Random Antiterrorism Program.
8. Contractor’s Requiring Common Access Card (CAC)
a. Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014- 05.
b. The contractor employee will be issued a CAC only if duties involve one of the following:
i. Both physical access to a DOD facility and access, via logon, to DOD networks on-site or remotely;
ii. Remote access, via logon, to a DOD network using DOD-approved remote access procedures; or
iii. Physical access to multiple DOD facilities or multiple non-DOD federally controlled facilities on behalf of the DOD on a recurring basis for a period of 6 months or more.
c. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI.