W911SA18B2013

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

QUESTIONS AND ANSWERS

Q1. Wire mesh railing panels are indicated in the Spec's, however, none where shown in plans or elevation views. Can you clarify if, in fact, these mesh panels are actually required?

A1. This specification contains to new construction. We seldom do new construction, but if we do, a full set of specifications will be provided with the task order.

Q2. Will you provide a breakdown of the amount of work anticipated for each base to be serviced under the JOC?

A2. No, a breakdown cannot be provided. It is difficult to determine the anticipated amount of work because it can be different for each base/site/facility. Projects vary depending on the needs of that location, any emergencies that may arise, and funding.

(End of Summary of Changes) image1.wmf