20170509_-_Appx_3.5_VCC_SWPPP_Stormwater_Pollution_Prevention_Plan.pdf
PDF 6 MB Posted
- Attached to
- Construct Visitor Control Center, Fort Drum, NY Federal contract opportunity
- Solicitation number
- W911S2-17-B-0001
About this file
20170509 - Appx_3.5 VCC_SWPPP_Stormwater_Pollution_Prevention_Plan
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BES DESIGN/BUILD, LLC | 766 MIDDLE STREET, FAIRHOPE, AL 36532 | PHONE: 251.990.5778 | FAX: 251.990.3716
FINAL DESIGN FOR CONSTRUCTION
SWPPP
Prepared For
VISITOR CONTROL CENTER
FORT DRUM, N.Y.
IDIQ for Architectural and Engineering Services Contract
No. W911S-16-D-8000 Work Order No. HE-00001-5JA
Submission Date: 9 May, 2017
A/E Design & SWPPP
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
Final Design for Construction May 09, 2017
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Table of Contents
CHAPTER 01 Project Information
Project Name and Location
Owner Name and Address
CHAPTER 02 Project Description
Purpose and Extent of Proposed Development
Project Disturbance Area
Site Soil Descriptions
Historic
CHAPTER 03 Construction
Sequence
Streams
CHAPTER 04 Controls
Timing of Controls / Measures
Erosion and Sediment Control Plan
Temporary Stabilization
Permanent Stabilization
Winter Operations
Winter Shutdown
Other Controls
Waste Disposal
Vehicle Tracking
Other Discharges
Certification of Compliance with Federal, State, and Local Regulations
CHAPTER 05 Post-Construction Stormwater Management
Water Quality
Pre-Development Site Conditions
Post Development Conditions
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Low Impact Development Features
Calculations for Determining Water Quality Treatment and Runoff Reduction Volumes-
Infiltration Trenches
WATER QUALITY TREATMENT
Floodplains
CHAPTER 06 Maintenance / Inspection Procedures
Erosion and Sediment Control Inspection and Maintenance Practices
Owner/Operator Inspection Requirements
Qualified Inspector Inspection Requirements
General Requirements
Post-Construction Stormwater Inspection and Maintenance Practices
CHAPTER 07 Inventory for Pollution Prevention Plan
Consumables
CHAPTER 08 Spill Prevention
Housekeeping
Hazardous Products
Product Specific Practices
Petroleum Products
Fertilizers
Paints
Concrete Trucks
Watercourse Protection
Spill Control Practices
CHAPTER 09 Updating the SWPPP
SWPPP Certification
Contracting Firm Information:
Contractor’s Certification
APPENDICES A SOIL INFORMATION ....................................................................................... -
APPENDICES B HISTORIC PRESERVATION INFORMATION ................................................. -
APPENDICES C SITE DRAWINGS ............................................................................................ -
FIGURE 1: LOCATION PLAN................................................................................................. -
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
FIGURE 2: EXISTING PLAN .................................................................................................. -
FIGURE 3: PROPOSED PLAN............................................................................................... -
APPENDICES D NOTICE OF INTENT ....................................................................................... -
APPENDICES E SPDES GENERAL PERMIT (GP-0-15-002) ..................................................... -
APPENDICES F INSPECTION FORMS & MAINTENANCE INFORMATION .............................. -
APPENDICES G EROSION AND SEDIMENT CONTROL PLAN WITH DETAILS ...................... -
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
CHAPTER 01
Project Information
Project Name and Location
Visitor Control Center
Project Number HE- 00001-5JA
Fort Drum, New York
Jefferson County, New York
Owner Name and Address
Kurt W. Hauk DPW Director
4896 Nininger Street
Fort Drum, New York 13602
(315) 772-7911
Kurt.W.Hauk.civ@mail.mil
CHAPTER 02
Project Description
Purpose and Extent of Proposed Development
This project consists of constructing a new 3 Processor Visitors Control Center at Fort Drum, including a new 14 space parking lot, existing building expansion (615 square feet), a passenger vehicle search canopy area and access roads, and search waiting shelter as shown on the mailto:Kurt.W.Hauk.civ@mail.mil
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716 attached site plan. The project is located adjacent to building #11010 along Iraqi Freedom Drive and will disturb approximately 1.43 acres.
This SWPPP covers all site development and is scheduled to be completed by 2017.
Project Disturbance Area
Total Disturbed Area: ±1.43 acres
Proposed Total Impervious Area: ±0.40 acres (0.16 of which was previously impervious)
Site Soil Descriptions
The soil disturbance for the proposed work is limited to 1.43 ± acres within the property boundary.
The site is undisturbed and covered with tree vegetation. According to the USDA Soil Survey of
Jefferson County, New York, the area of disturbance consists primarily of Hudson silt loam (HuB)
(see Appendix A).
The Natural Resource Conservation Service (NRCS, formerly known as the SCS), as part of their soil classification system, assigns each soil series to a Hydrologic Soil Group (HSG). The HSG is a four-letter index intended to indicate the minimum rate of infiltration obtained after prolonged wetting, and to indicate the relative potential for a soil type to generate runoff. The infiltration rate is the rate at which water enters the soil at the soil surface. The HSG also indicates the transmission rate – the rate at which water moves within the soil. Soil scientists define the four groups as follows:
HSG ‘A’ (sand, loamy sand, or sandy loam): Soils have low runoff potential and high infiltration rates even when thoroughly wetted. They consist chiefly of deep, well to excessively drained sands or gravels and have a high rate of water transmission (> than 0.30 inches/hour).
HSG ‘B’ (silt loam or loam): Soils have moderate infiltration rates when thoroughly wetted, and consist chiefly of moderately deep to deep, moderately well to well drained soils with moderately fine to fine texture. These soils have a moderate rate of water transmission (0.15 to 0.30 inches/hour).
HSG ‘C’ (sandy clay loam): Soils have low infiltration rates when thoroughly wetted and consist chiefly of soils with a layer that impedes downward movement of water, and soils with moderately fine to fine texture. These soils have a low rate of water
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716 transmission (0.05 to 0.15 inches/hour).
HSG ‘D’ (clay loam, silty clay loam, sandy clay, silty clay, or clay): Soils have high runoff potential. They have very low infiltration rates when thoroughly wetted, and consist chiefly of clay soils with a high swelling potential, soils with a permanent high water table, soils with a clay pan or clay layer at or near the surface, and shallow soils over nearly impervious material. These soils have a very low rate of water transmission (< 0.05 inches/hour).
If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is for drained areas and the second is for undrained areas. Only the soils that in their natural condition are in Group D are assigned to dual classes.
Hudson silt loam are classified as HSG B soils.
Historic
The proposed project will have no adverse impact on a property that is eligible for listing on the
State or National Register of Historic Places in Jefferson County, New York. This is confirmed via the Cultural Resource Information System (CRIS) online at https://cris.parks.ny.gov/ searched
November 1, 2016 (see Appendix B).
CHAPTER 03
Construction
Sequence
This SWPPP presents erosion and sediment controls, both temporary and permanent, to assist the operator in compliance with the project’s SPDES General Permit for construction activity. To the degree practicable, all temporary erosion and sediment control mitigation measures shall be installed immediately before associated project areas are disturbed in anticipation of all soil disturbing activities to follow. Based upon NYS DEC regulations, the owner or operator of a construction activity shall not disturb greater than five (5) acres of soil at any one time without prior written authorization from the Department or, in areas under the jurisdiction of a regulated, traditional land use control MS4, the MS4 (provided the MS4 is not the owner or operator of the
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716 construction activity). At a minimum, the owner or operator must comply with the following requirements in order to be authorized to disturb greater than five (5) acres of soil at any one time:
1. The owner or operator shall have a qualified inspector conduct at least two (2) site inspections in accordance with Part IV.B. every seven (7) calendar days, for as long as greater than five (5) acres of soil remain disturbed. When performing just two (2) inspections every seven (7) calendar days, the inspections shall be separated by a minimum of two (2) full calendar days.
2. In areas where soil disturbance activity has been temporarily or permanently ceased, temporary and/or permanent soil stabilization measures shall be installed and/or implemented within seven (7) days from the date the soil disturbance activity ceased. The soil stabilization measures selected shall be in conformance with the most current version of the technical standard, New York Standards and Specifications for Erosion and Sediment Control.
3. The owner or operator shall install any additional site specific practices needed to protect water quality.
4. The owner or operator shall include the requirements above in their SWPPP.
It is the responsibility of the Contractor to ensure that all soils removed from the project site are spoiled in a manner consistent with all local, state, and federal regulations. Appropriate erosion and sediment controls shall be installed at all spoil sites. Additionally, the Contractor is responsible for coordinating the application for a GP- 0-15-002 permit (and development of an associated
SWPPP) if disturbance associated with any soil spoils area is greater than 0.4 hectares (1 acre).
GP-0-15-002 applications must be signed by the owner of the lands on which soils are spoiled.
Disturbances associated with offsite spoil areas do not contribute to the total disturbances associated with onsite activities.
It is not anticipated to disturb greater than 5 acres of land at one time for this project. See construction documents for sequencing information.
Streams
Stormwater runoff generally drains to the southwest discharging to West Creek (Class A, Standards A) which is a second order stream or larger.
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
CHAPTER 04
Controls
Timing of Controls / Measures
The erosion and sediment control measures shall be constructed prior to clearing or grading of any portion of the project. Where land disturbance is necessary, temporary seeding or mulching must be used on areas which will be exposed for more than 14 days. Permanent stabilization should be performed as soon as possible after completion of grading. After the entire project area is stabilized, the accumulated sediment shall be removed from the project area. Erosion control devices shall remain in place until disturbed areas are permanently stabilized. For projects where soil disturbance is greater than five (5) acres, and construction activity has temporarily or permanently ceased, temporary and/or permanent soil stabilization measures shall be installed and/or implemented within seven (7) days from the date the soil disturbance activity ceased. The soil stabilization measures selected shall be in conformance with the most current version of the technical standard, New York Standards and Specifications for Erosion and Sediment Control.
Erosion and Sediment Control Plan
Temporary Stabilization
Topsoil stockpiles, staging areas and disturbed pervious portions of the project area where construction activity temporarily ceases for at least 14 days shall be stabilized with temporary seed and mulch no later than 14 days from the last construction activity in that area.
Temporary seed shall be ryegrass applied at the rates specified below:
If seeding in spring, summer or early fall then seed with annual or perennial rye at a rate of 30 lbs per acre. If area is to remain stabilized over the winter into the following spring use perennial rye only.
If seeding in late fall or early winter, use certified Aroostook winter rye (cereal rye) at a rate of 90 lbs per acre.
Any seeding method may be used that will provide uniform application of seed to the area and result in relatively good soil to seed contact. Area must be free of large rocks and debris and seeded within 24 hours of disturbance or scarification of the soil surface will be necessary prior to seeding. Fertilizer or lime is not typically used for temporary plantings.
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Mulch shall be applied in conjunction with seeding and applied at the rate of 90 lbs per 1,000 square feet. Mulch shall be reapplied as necessary. Areas of the project area, which are to be paved, shall be temporarily stabilized by applying temporary gravel subbase until pavement can be applied.
Sediment control fencing shall be installed around the site where depicted on the attached plan sheets. Additional fencing shall be installed as necessary.
Permanent Stabilization
Disturbed portions of the project area where construction activities permanently cease shall be stabilized with permanent seed no later than 14 days after the last construction activity. The permanent seed mix shall be in accordance with the project specifications and plans. Construction and maintenance of erosion and siltation control measures are in accordance with the New York
Standards and Specifications for Erosion and Sediment Control.
Where construction activity is complete over areas to be permanently vegetated, stabilize with permanent seeding. Verify seeding dates with engineer. If engineer determines that seed cannot be applied due to climate, topsoil shall not be spread and mulching shall be applied to the exposed surface to stabilize soils until the next recommended seeding period. Other project areas shall be permanently stabilized with pavement, concrete, gravel or building structures.
Winter Operations
If construction activities proceed through the winter season, access points should be enlarged and stabilized to provide for snow stockpiling. Drainage structures should be kept open and free of potential snow and ice dams. Inspection and maintenance are necessary to ensure the function of these practices during runoff events. For sites where construction activities temporarily cease, temporary and/or permanent soil stabilization measures shall be installed within seven (14) days from the date the soil disturbing activity ceased. Disturbed areas should be stabilized with seed and mulch, or other approved methods, even if the ground is covered by significant amounts of snow.
Winter Shutdown
Site inspections (by the qualified inspector) may be decreased to a minimum of one (1) time every thirty (30) days for sites where soil disturbing activities have ceased and the site has been completely stabilized with an approved method. Inlet protection should be installed and/or
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716 repaired before shutdown of the site. The owner or operator shall provide written notification to the owner prior to reducing the frequency of any site inspections.
Other Controls
Waste Disposal
Waste materials – Foreign waste materials shall be collected and stored in a secured area until removal and disposal by a licensed solid waste management company. All trash and construction debris from the project area shall be disposed of in a portable container unit. No foreign waste materials shall be buried within the project area. All personnel shall be instructed regarding the correct procedure for waste disposal. Notices stating these practices shall be posted in the project trailer and the individual who manages day-to-day project operations will be responsible for seeing that these procedures are followed.
Petroleum Impacted Waste – During the excavation activities, there is the potential that petroleum impacted soils may be encountered. In the event that field evidence of contamination is identified during the project, potentially contaminated soils will be segregated and stockpiled on polyethylene sheeting and covered in a predetermined staging area. The potentially impacted, stockpiled soils will then be sampled to determine if the soils are suitable for use as clean backfill. In the event that the soils are not suitable for re-use, the contaminated soil will be properly characterized and disposed of at an off-site NYSDEC permitted facility. The excavation will then be backfilled with clean, imported fill.
Hazardous Waste - All hazardous waste materials shall be disposed of in a manner specified by local or state regulations or by the manufacturer. Project personnel shall be instructed in these practices and the individual who manages day-to-day project operations shall be responsible for seeing that these practices are followed.
Sanitary Waste - Any sanitary waste from portable units shall be collected from the portable units by a licensed sanitary waste management contractor, as required by NYS DEC regulations.
Vehicle Tracking
A stabilized construction entrance shall be installed and maintained as necessary to help reduce vehicular tracking of sediment should the potential for sediment tracking exist. The entrance shall be cleaned of sediment and redressed when voids in the crushed stone become filled and vehicular tracking of sediment is occurring. Dump trucks hauling materials to and from the construction project area shall be covered with a tarpaulin to reduce dust. Any sediment and debris tracked from work area along project adjacent roadways shall be immediately removed with a street sweeper or equivalent sweeping method. Further, sweeping of streets adjacent to disturbed
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716 areas shall be performed prior to the end of each work day (at a minimum) when tracking of sediment is occurring.
Other Discharges
Non-stormwater discharges are not expected to exit the project area during construction.
Certification of Compliance with Federal, State, and Local Regulations
The stormwater pollution prevention plan reflects the New York State requirements for stormwater management and erosion and sediment control. Even though permit coverage is not required due to the direct discharge to the combined sewer system, Federal regulations require the project to be designed as if State regulations applied. To ensure compliance, this plan was prepared in accordance with New York State Standards. There are no other applicable State or Federal requirements for sediment and erosion plans (or permits), or stormwater management plans (or permits).
CHAPTER 05
Post-Construction Stormwater Management
Water Quality
Water quality treatment will be designed to capture and treat 90% of the annual stormwater runoff volume, or the full water quality volume (WQv) for the new impervious surfaces. Treatment practices need to be capable of 80% Total Suspended Solids (TSS) removal and 40% Total
Phosphorous (TP) removal, have an accepted longevity in the field and have a pretreatment mechanism.
Per Chapter 9 of the New York State Stormwater Management Design Manual (NYSSMDM), the project falls within the Redevelopment guidelines. Therefore, 25% of the Water Quality Volume
(WQv) is required to be treated for existing impervious surfaces, while 100% is required for new impervious surfaces.
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Pre-Development Site Conditions
The existing topography of the site is rolling terrain with swales that capture storm water runoff varying in slope from 3% to 7% while varying in elevation from 483 ft. to 465 ft. The site generally drains towards the project and out to eventually outfall to West Creek to the west. The site is undisturbed covered with tree vegetation. The predominant soil type in this area is glacial till consisting of Hudson silt loam, 3 to 8 percent slopes with an infiltration rate potentially as low as 16 in/hr. Proposed grades will accommodate the UFC regulations regarding minimum and maximum slopes for both grading of building frontage and within the proposed parking facilities addition. The stormwater management for the site will be accomplished through a combination of overland flow, infiltration beds in the ditches, bio-retention basin, and a parking filtration strip along the parking lot as per the UFC 3-210-10, Low Impact Development Manual. The bio-retention basin will be located near the low point just south of the parking area. The total land disturbance is approximately 1.43 acres; while the total drainage area of the site is 2.4 acres.
Post Development Conditions
The site will be cleared of trees, re-graded to suit the design requirements and parking and building expansion will be added. The total disturbed area is approximately 1.43 acre therefore a Notice of Intent will be filed to gain coverage under the NYSDEC SPDES General Permit (GP
0-015-002). New impervious area added will include asphalt pavement, concrete sidewalks, canopy, and new building expansion. The total new impervious area added will be 0.40 acres.
The new design will direct the existing swale into roadside ditches on both sides of the road and direct it to the outfall. In order to meet low impact development requirements outlined in UFC 3-
210-10, roadside ditches will be four feet wide with infiltration trenches, and a bio retention pond will be constructed near the outfall at station 11+00 left side. The parking lot will sheet flow over the pavement to the ditch to allow more infiltration time. The parking lot will also include a stone filter diaphragm at the edge of pavement to help absorb and filter the runoff. The entire site will be seeded and trees will be added to further reduce the impacts of the cleared site.
Low Impact Development Features
In order to achieve and reduce post development runoff at least the pre-development characteristics of the site will be maintained after development and the following design features will be implemented.
Infiltration ditches---Added into the roadside ditches. This will filter the water and reduce the volume
Bio-retention bed---This will detain the water, filter the water and reduce the volume through infiltration and plant absorption
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Stone filter diaphragm—located adjacent to on the down side of the parking lot to reduce and filter the runoff.
Calculations for Determining Water Quality Treatment and Runoff Reduction Volumes-Infiltration Trenches
Calculations for water quality runoff and reduction are based on New York State Stormwater
Management Design Manual 2015 chapter 4 and 9. This is considered a redevelopment project due to it being an existing site that we are adding new impervious area to. Because of this, the site will have an increase in runoff. The existing impervious area consists of a building, asphalt parking lot and concrete sidewalk totaling 0.16 acres. The new construction will include an addition to the building, expanded parking, and additional pavement for the access road and a search canopy. Post construction impervious area is 0.40 acres. The redevelopment guidelines for treatment require treating 25% of the water volume for existing impervious areas and 100% treatment for new impervious areas; Chapter 9 page 9-5. The treatment will be handled by 4’ wide x 4’ deep stone filled infiltration trenches and bio-retention. The formulas used are from Chapter
4 and 6 of the sited manual.
Redevelopment project-----description based on criteria of Chapter 4
Water Quality volume based on the 90% rule Table 4.1---New York State Stormwater Design Manual
Treat 90% of all 24 hour rain events
Treat 100% of all new impervious areas
Treat 25% of all existing impervious areas
Existing impervious area= 0.16 acres = 7% of total
New impervious area = 0.40 acres = 17% of total
Total drainage basin = 2.4 acres
Total disturbed area = 1.43 acres
WATER QUALITY TREATMENT
Equation used to calculate volume of treatment:
WQv= (P x Rv x A)/12 (from section 4.1 pg 4-1)
WQv is water quality storage volume ac-ft
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
P is 90% rainfall event from fig 4-1 referenced manual---P=1= 1.0
Rv = 0.05+0.009(I) I is impervious cover in percent
A is contributing site area
New Impervious area--- treat 100%
WQv = 1.0 x 0.05 + (0.009 x 100)(0.41)/12 = 0.033 ac-ft = 1438 cf
Required surface area needed for 4’ wide x 4’ deep trench
Surface area Equation: Ap = Vw/(ndt) (from section 6.3 pg 6-37 manual)
Ap = surface area in sf
Vw = design volume (WQv) cf
N = porosity (assume 0.40)
Dt = trench depth
Ap = 1438/(0.40 x4) = 898 sf
Length of trench = 898/4= 224 feet-------100% treatment for new impervious area
Existing impervious treatment needed 25% of area
WQv= 1.0 x 0.05+(0.009 x 100)(0.16)/12 x 25%= 0.004 ac ft = 176 cf
Length of trench Ap = 176/(0.40 x 4) = 110 sf = 28 lf north side of road
RUNOFF REDUCTION VOLUME (chapter 4; pg 4-6)
RRvmin = (P x Rv x Aic x S)/12
RRv minimum reduction volume
Rv = 0.05+ 0.009 x I where I is 100% (100)
Aic is total new impervious area 0.56 acres
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
S = Hydrologic soil group specific reduction factor Use HSG B = 0.40
RRv min= 1 x[[(0.05+(0.009*100)] x 0.56 x 0.40]/12 = 0.0177ac-ft =773 cf
Minimum treatment required is 773 cf---- treatment provided is 1438 + 176 = 1614 cf—meets goals
Ap = 1614/(0.40 x4) = 1008 sf 1008/4 = 252 linear feet trench needed
Also providing a bio retention pond.
Abasin = Vw/db------------(section 6.3 pg 6-37)
Abasin= required bottom
Vw= WQv= 176 c.f. from above
Db = depth of basin = 3 ft
Abasin =176 c.f./3= 51 sf required. Area provided = 855 sf provided
Summary:
Treatment: ---Using Infiltration Trenches Required
Provided
Pre-development runoff treatment (25%) 176 cf (28 lf)
Post development runoff treatment (100%) 1438 cf (224 lf)
1614 cf (252 lf) 310 lf
Runoff Reduction---Using Infiltration Trenches
Total Reduction 1614 cf (252 lf) 310 lf
Bio-Retention Bed---Additional 855 sf
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Floodplains
The project site is not located within a floodplain, therefore, floodplain impacts are not applicable.
CHAPTER 06
Maintenance / Inspection Procedures
Erosion and Sediment Control Inspection and Maintenance Practices
These are the minimum required inspection and maintenance practices that shall be used to maintain erosion and sediment controls:
Owner/Operator Inspection Requirements
Prior to construction activity the owner/operator shall have contractors and sub-contractors identify a trained individual responsible for the implementation of the SWPPP. The trained individual must be on-site on a daily basis when soil disturbing activities are occurring.
The owner/operator shall inspect the erosion and sediment control measures as identified in the SWPPP to ensure that they are being maintained in effective operating conditions at all times. Where soil disturbing activities temporarily cease (e.g. winter shutdown) and temporary stabilization measures have been applied to all disturbed areas, the owner/operator can stop conducting inspections. The owner/operator shall resume inspections when soil disturbing activities begin again.
Where soil disturbing activities have ceased with partial project completion, the owner/operator can stop conducting inspections when disturbed areas have reached final stabilization. All post construction stormwater management practices required for the completed areas shall have been constructed in conformance with the SWPPP and be fully operational. Final stabilization means that all soil disturbance activities have ceased and a uniform, perennial vegetative cover with a density of eighty (80) percent over the entire pervious surface has been established; or other equivalent stabilization measures, such as permanent landscape mulches, rock rip-rap or washed/crushed stone have been applied on all disturbed areas that are not covered by permanent structures, concrete or pavement.
The owner/operator shall notify the DEC Regional Office’s and Fort Drum’s stormwater contact person prior to any reduction in the frequency of site inspections.
The owner/operator shall retain copies of the NOI, NOI acknowledgment letter, SWPPP, MS4 SWPPP acceptance forms and any inspection reports submitted in conjunction with
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716 this permit and records or all data used to complete the NOI to be covered by this permit for a period of at least five (5) years from the date that the site is finally stabilized.
Qualified Inspector Inspection Requirements
The qualified inspector is defined as a person that is knowledgeable in the principles and practices of erosion and sediment control, such as a licensed Professional Engineer, Certified Professional in Erosion and Sediment Control (CPESC), licensed Landscape Architect, or other Department endorsed individual(s). It may also mean someone working under the direct supervision of the licensed Professional Engineer or licensed Landscape Architect, provided that person has training in the principles and practices of erosion and sediment control. Training in the principles and practices of erosion and sediment control means the person has received four (4) hours of training endorsed by the Department and shall receive four (4) hours of training every three (3) years after the initial training.
A site inspection shall be conducted at least once every seven (7) days by the qualified inspector when soil disturbing activities are occurring. A copy of the “Construction Duration Inspection Form” is included in the “inspection forms” section of this plan.
All measures shall be maintained in good working order; if any repairs or corrective actions are necessary, it is the responsibility of the qualified inspector to notify the owner/operator and appropriate contractor within one business day. The contactor shall begin implementing the corrective action within one business day of being notified.
All inspection forms must be signed by a qualified inspector.
For construction sites where soil disturbing activities are temporarily suspended, temporary stabilization measures shall be applied and the qualified inspector shall conduct a site inspection at least once every thirty (30) calendar days.
Where soil disturbing activities have ceased with partial project completion the qualified inspector can stop conducting inspections when disturbed areas have reached final stabilization and all post construction stormwater management practices required for the completed areas have been constructed in conformance with the SWPPP and are fully operational.
Where soil disturbing activities are not resumed within two (2) years, from the date of shut down of partial project completion, the qualified inspector shall perform a final inspection and certify that all disturbed areas have achieved final stabilization, all temporary and permanent erosion control measures have been removed, and post-construction stormwater management practices have been constructed in conformance with the SWPPP. Qualified inspector shall sign the “Final Stabilization” and “Post- Construction stormwater Management Practice” certification statements on the Notice of Termination (NOT).
General Requirements
A copy of the SPDES General Permit (GP-0-15-002), the signed Notice of Intent (NOI), Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
NOI acknowledgement letter, SWPPP, MS4 SWPPP Acceptance Forms, and inspection reports shall be maintained onsite until the site has achieved final stabilization.
Built up sediment shall be removed from any silt fence when it has reached one-third the height of the fence / dike.
Sediment fencing shall be inspected for depth of sediment, and tears, to see if fabric is securely attached to the fence posts, and to see that the fence posts are firmly in the ground.
The construction entrance shall be cleaned of sediment and redressed when voids in the crushed stone become filled and vehicular tracking of sediment is occurring.
Dust shall be controlled on access points and other disturbed areas subject to surface dust movement and blowing.
Stabilization fabric shall be inspected to ensure that slopes are not being eroded. Fabric shall be replaced / reinstalled as necessary to prevent any such erosion.
Inspection of diversion swales shall be conducted to check condition of swale.
Inspection must verify that all practices are adequately operational, maintained properly and that sediment is removed from all control structures.
Inspection must look for evidence of soil erosion on the site, potential of pollutants entering drainage systems, problems at the discharge points, and signs of soil and mud transport from the site to the public road.
Post-Construction Stormwater Inspection and Maintenance Practices
The Fort Drum Military Reservation will maintain ownership of the development. Long-term inspection forms for the stormwater management practices (included in Appendix F of this plan) are referenced from Appendix G of the New York State Stormwater Management Design Manual.
CHAPTER 07
Inventory for Pollution Prevention Plan
Consumables
The materials or substances listed below are expected to be within the project area during construction:
Portland cement concrete.
Fertilizers / seeding materials.
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Stone.
Bituminous asphalt.
Petroleum based products.
Silt fence fabric.
Lumber.
Pavement marking paint.
HDPE pipe, PVC pipe, and CMP.
Bonded fiber matrix material.
HDPE Geomembrane material.
CHAPTER 08
Spill Prevention
The following are the material management practices that shall be used to reduce the risk of spills or other accidental exposure of materials and substances to stormwater runoff.
Housekeeping
The following good housekeeping practices shall be followed within project areas during construction:
An effort shall be made to store only enough products required to do the job.
All materials stored within project areas shall be stored in a neat, orderly manner in their appropriate containers and, if possible, under a roof or other enclosure.
Products shall be kept in their original containers with the original manufacturer's label.
Substances shall not be mixed with one another unless recommended by the manufacturer.
Whenever possible, all of a product shall be used up before disposing of the container.
Manufacturers' recommendations for proper use and disposal shall be followed.
The project superintendent shall inspect daily to ensure proper use and disposal of materials.
Hazardous Products
These practices are used to reduce the risks associated with hazardous materials:
Products shall be kept in original containers unless they are not resealable.
Original labels and material safety data shall be retained.
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
If surplus product must be disposed of, manufacturers' or local and state recommended methods of proper disposal shall be followed.
Material Safety Data Sheets for all hazardous products shall be within the project area for the duration of construction.
Product Specific Practices
The following product-specific practices shall be followed within the project areas:
Petroleum Products
All project related vehicles shall be monitored for leaks and receive regular preventive maintenance to reduce the chance of leakage. Petroleum products shall be stored in tightly sealed containers which are clearly labeled. Any asphalt substances used during construction shall be applied according to the manufacturer's recommendations.
Fertilizers
Fertilizers used shall be applied only in the minimum amounts recommended by the manufacturer.
Once applied, fertilizer shall be worked into the soil to limit exposure to stormwater. Fertilizers shall be stored in a covered or other contained area.
Paints
All containers shall be tightly sealed and stored when not required for use. Excess paint shall not be discharged to the storm sewer system but shall be properly disposed of according to manufacturer’s instructions or State regulations.
Concrete Trucks
Concrete trucks shall be allowed to wash out within project areas provided that the contractor provides an area which collects and contains any concrete / slurry material washed from trucks for recovery and disposal at a later time. No concrete / slurry shall be discharged from the property at any time of construction. If such washing is anticipated, the contractor shall submit a plan detailing the control of concrete / slurry to the engineer for approval.
Watercourse Protection
Construction operations shall be conducted in such a manner as to prevent damage to watercourses from pollution of debris, sediment, or other foreign material, or from manipulation, from equipment and/or materials in or near the watercourse. The contractor shall not return directly to the watercourse any water used for wash purposes or other similar operations which
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716 may cause the water to become polluted with sand, silt, cement, oil or other impurities. If the contractor uses water from the water course, the contractor shall construct an intake or temporary dam to protect and maintain watercourse water quality.
Spill Control Practices
The contractor will be responsible for preparing a project area specific spill control plan in accordance with local and NYS DEC regulations. At a minimum this plan should:
Reduce stormwater contact if there is a spill.
Contain the spill.
Stop the source of the spill.
Dispose of contaminated material in accordance with manufactures procedures, and NYS DEC regulations.
Identify responsible and trained personnel.
Ensure spill area is well ventilated.
CHAPTER 09
Updating the SWPPP
The SWPPP shall be updated/revised as conditions merit or as directed by the regulating authority. The attached inspection forms included with this document allows for the certification of any updates/revisions.
SWPPP Certification
Contracting Firm Information:
Contracting Firm
Address
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
City/Town State Zip
Site Location:
Fort Drum Military Reservation Town of Fort Drum
Contractor’s Certification
I hereby certify that I understand and agree to comply with the terms and conditions of the SWPPP and agree to implement any corrective actions identified by the qualified inspector during a site inspection. I also understand that the owner or operator must comply with the terms and conditions of the most current version of the New York State Pollutant Discharge Elimination
System (SPDES) general permit for stormwater discharges from construction activities and that it is unlawful for any person to cause or contribute to a violation of water quality standards.
Furthermore, I understand that certifying false, incorrect or inaccurate information is a violation of the referenced permit and the laws of the State of New York and could subject me to criminal, civil and/or administrative proceedings.
Signature (Contractor/Subcontractor) Date
For
Responsible For
Signature (Trained Contractor) Date
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
Signature (Contractor/Subcontractor) Date
Signature (Trained Contractor) Date
Fort Drum, N.Y.
Public Works Engineering Division
Work Order No. HE- 00001-5JA BESDB Project No. 16008
BES Design/Build, LLC I 766 Middle Street, Fairhope, AL. 36532 I PH: 251-990-5778 I FX: 251-990-3716
APPENDICES A
SOIL INFORMATION
United States
Department of
Agriculture
Natural
Resources
Conservation
Service
A product of the National
Cooperative Soil Survey, a joint effort of the United
States Department of
Agriculture and other
Federal agencies, State agencies including the
Agricultural Experiment
Stations, and local participants
Custom Soil Resource
Report for
Jefferson
County, New
York
November 1, 2016
Preface
Soil surveys contain information that affects land use planning in survey areas. They highlight soil limitations that affect various land uses and provide information about the properties of the soils in the survey areas. Soil surveys are designed for many different users, including farmers, ranchers, foresters, agronomists, urban planners, community officials, engineers, developers, builders, and home buyers. Also, conservationists, teachers, students, and specialists in recreation, waste disposal, and pollution control can use the surveys to help them understand, protect, or enhance the environment.
Various land use regulations of Federal, State, and local governments may impose special restrictions on land use or land treatment. Soil surveys identify soil properties that are used in making various land use or land treatment decisions. The information is intended to help the land users identify and reduce the effects of soil limitations on various land uses. The landowner or user is responsible for identifying and complying with existing laws and regulations.
Although soil survey information can be used for general farm, local, and wider area planning, onsite investigation is needed to supplement this information in some cases.
Examples include soil quality assessments (http://www.nrcs.usda.gov/wps/portal/ nrcs/main/soils/health/) and certain conservation and engineering applications. For more detailed information, contact your local USDA Service Center (http:// offices.sc.egov.usda.gov/locator/app?agency=nrcs) or your NRCS State Soil
Scientist (http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/contactus/?
cid=nrcs142p2_053951).
Great differences in soil properties can occur within short distances. Some soils are seasonally wet or subject to flooding. Some are too unstable to be used as a foundation for buildings or roads. Clayey or wet soils are poorly suited to use as septic tank absorption fields. A high water table makes a soil poorly suited to basements or underground installations.
The National Cooperative Soil Survey is a joint effort of the United States Department of Agriculture and other Federal agencies, State agencies including the Agricultural
Experiment Stations, and local agencies. The Natural Resources Conservation
Service (NRCS) has leadership for the Federal part of the National Cooperative Soil
Survey.
Information about soils is updated periodically. Updated information is available through the NRCS Web Soil Survey, the site for official soil survey information.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or a part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means http://www.nrcs.usda.gov/wps/portal/nrcs/main/soils/health/ http://www.nrcs.usda.gov/wps/portal/nrcs/main/soils/health/ http://offices.sc.egov.usda.gov/locator/app?agency=nrcs http://offices.sc.egov.usda.gov/locator/app?agency=nrcs http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/contactus/?cid=nrcs142p2_053951 http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/contactus/?cid=nrcs142p2_053951 for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD). To file a complaint of discrimination, write to USDA, Director, Office of Civil Rights, 1400
Independence Avenue, S.W., Washington, D.C. 20250-9410 or call (800) 795-3272
(voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer.
Contents
Preface
Soil Map
Soil Map
Legend
Map Unit Legend
Map Unit Descriptions
Jefferson County, New York
ElB—Elmridge fine sandy loam, 3 to 8 percent slopes
Fu—Fluvaquents-Udifluvents complex, frequently flooded
HuB—Hudson silt loam, 3 to 8 percent slopes
PoB—Plainfield sand, 0 to 8 percent slopes
Soil Map
The soil map section includes the soil map for the defined area of interest, a list of soil map units on the map and extent of each map unit, and cartographic symbols displayed on the map. Also presented are various metadata about data used to produce the map, and a description of each soil map unit.
C u s to m S o il
R e s o u rc e R e p o rt
S il
M a p
' 9
N
' 9
' 5
' 5
M p S ca le :2
,0 if p ri n te d o n A la n d sc ap e x
.5 s h e e t.
te rs
W rn in g S o il M a p m a y n o t b e v a lid a t th is s ca le
4877760 4877800 4877840 4877880 4877920 4877960 4878000 4878040
75° 49' 44'' W 75° 49' 44'' W
75° 49' 24'' W 75° 49' 24'' W
4877760 4877800 4877840 4877880 4877920 4877960 4878000 4878040
Fe e t p p ro je ct io n W e b M e rc a to r
C o rn e r co o rd in a te s:
W
G S
E d g e ti cs
U T M
Z o n e
N W
G S
Ira qi
F re ed om
D riv e
Ira qi
F re ed om
D riv s to m S o il
R e s o u rc e R e p
A
P L
E G
E
D
P I
N F
O R
M A
T
IO
re a o f In te re s t
(A O
I) a o f In te re s t (A
I) il s il
M a p U n it P o ly g o n il
M a p U n it L in il
M a p U n it P o in ts e c ia l
P o in t
F e a tu
B lo w o u t
B o rr o w
P it la y
S p s e d D e p re s s io
G ra v e l it
G v e lly
S p
L n d fi ll v a F w rs h o r s w a m e o r Q u a rr y is c e lla n e o u s W a r re n n ia l W a
R c k O u tc ro lin e S p n d y S p v e re ly E ro d e d S p k h le lid e o r lip d ic
S p o il
A to n y S p
V ry
S to n y S p t S p th e c ia l L in e F e a tu te r F e a tu tr e a m s a n d C a n ls
T n s p o rt a ti
R ils
In rs ta te
H ig h w a
U
R o u jo r R o a d c a l R o a
B c k g ro u n d A e ri a l P h o to g ra p h e s o il s u rv e y s t h a t c o m p ri s e y o u r
A O
I w e re m a p p e d a t :1
,8 le a s e r e ly o n t h e b a r s c a le o n e a c h m a p s h e e t fo r m a s u re m e n ts u rc e o f M a p
N a tu ra l R e s o u rc e s C o n s e rv a ti o n S e rv ic b S o il
S u rv e y U
R L h tt p /w e b s o ils u rv e y .n rc s .u s d a .g v o rd in a te
S y s te m
W e b M e rc a to r (E
P S
G :3 p s f ro m t h e W e b S o il
S u rv e y a re b a s e d o n t h e W e b M e rc a to r p ro je c ti o n w h ic h p re s e rv e s d ir e c ti o n a n d s h a p e b u t d is to ta n c e a n d a re a A p ro je c ti o n t h a t p re s e rv e s a re a s u c h a s t lb e rs e q u a l-a re a c o n ic p ro je c ti o n s h o u ld b e u s e d if m o re a c c u c lc u la ti o n s o f d is ta n c e o r a re a a re r e q u ir e is p ro d u c t is g e n e ra te d f ro m t h e U
S D
A -N
R C
S c e rt if ie d d a ta a s o f th e v e rs io n d a te
(s lis te d b e lo w il
S u rv e y A re a
J e ff e rs o n C o u n ty
N e w
Y rk rv e y A re a D a ta
V e rs io n
S e p il m a p u n it s a re la b e le d a s s p a c e a llo w s fo r m a p s c a le s
:5 ,0 la rg r.
D te
(s a e ri a l im a g e s w e re p h o to g ra p h e d
J u n
J u l e o rt h o p h o to o r o…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .