- Engine Dynamometer Test Cell Control Systems
- Solicitation number
- W911RQ-18-Q-0016
About this file
Technical Information Questionnaire (TIQ)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 18Q0016QA25SEP18docx.docx | DOCX document | |
| W911RQ18Q0016__NMWRs.pdf | ||
| W911RQ18Q0016_Q&As_13_Sep_2018.pdf | ||
| W911RQ-18-Q-0016-0001_Amendment.pdf | ||
| W911RQ-18-Q-0016_Engine_Dyno_Test_Cell_Systems.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Information Questionnaire (TIQ)
W911RQ-18-Q-0016
August 2018
Engine Dynamometer Test Cell Control Systems
W911RQ-18-Q-0016
FAILURE TO PROVIDE ALL OF THE INFORMATION REQUIRED BELOW MAY RENDER YOU QUOTE INELIGIBLE FOR AWARD.
The purpose of this questionnaire is to determine the suitability of your equipment to satisfy the requirements as stated in the SOW.
GENERAL INFORMATION
Personnel Responding to Questionnaire:
(a) Name___________________________________________________________
(b) Job title__________________________________________________________
(c) Company name___________________________________________________
(d) Telephone / Fax Numbers___________________________________________
(e) E-mail address____________________________________________________
(f) Mailing address____________________________________________________
(g) Company website__________________________________________________
(h) Comments:
Criteria 1: Engine dynamometer control systems must be able to meet the general engine dynamometer testing as define by the Government and the general engine test requirements of the following engines and their associated NMWR test documents on SOW sections 2.1.1.1. thru 2.1.1.7. (SOW section 2.1.1.)
Question 1: Can the offeror provide engine dynamometer control systems that are able to meet the general engine dynamometer testing and the engine test requirements to include their associated NMWR test documents define by the Government on SOW sections 2.1.1.1. thru 2.1.1.7. under section 2.1.1. Functionality Salient Characteristics?
Standard of Proof 1: Acknowledgment in this TIQ and submit manufacture technical data manual or specification sheet showing engine dynamometer testing characteristics.
Offeror Answer 1: Yes____ No____
Criteria 2: The in-cell touch-screen control monitor must be capable of start/stopping engine under test and display all available critical temperature, pressure, speed, and torque measurements (SOW section 3.1.1.1)
Question 2: Are the in-cell touch-screen control monitor capable of start/stopping the engine under test and display all available critical temperature, pressure, speed, and torque measurements?
Standard of Proof 2: Acknowledgment in this TIQ and submit manufacture technical data manual or specification sheet showing that the in-cell touch-screen control monitor capabilities.
Offeror Answer 2: Yes____ No____
Criteria 3: The control and command system to control and monitor engine speed, torque, and power from a control room must be separate from the test cell (SOW section 3.1.1.2)
Question 3: Will the control and command system that control and monitor engine speed, torque, and power be in a control room that is separate from the test cell?
Standard of Proof 3: Acknowledgment in this TIQ and submit manufacture technical data manual showing control and command system schematics and capabilities.
Offeror Answer 3: Yes____ No____
Criteria 4: Control room system shall provide full control of unit under test and display all critical performance and test data of the unit under test (SOW section 3.1.1.2)
Question 4: Will the control room system provide full control of the unit under test and display all critical performance and test data of the unit under test?
Standard of Proof 4: Acknowledgment in this TIQ and submit manufacture technical data manual showing control and command system schematics and capabilities.
Offeror Answer 4: Yes____ No____
Criteria 5: The system shall utilize a Windows 10 or later based workstation. (SOW section 3.1.1.2)
Question 5: Will the system utilized a Windows 10 or later based workstation?
Standard of Proof 5: Acknowledgment in this TIQ and submit manufacture technical data manual showing control and command systems workstation software.
Offeror Answer 5: Yes____ No____
Criteria 6: The equipment shall allow the continuation of the test from the point of segment from which it was stopped and paused without having to restart the test from the beginning (SOW section 3.1.10.2)
Question 6: Will the equipment allow for the continuation of the test from the point of segment from which it was stopped and paused without having to restart the test from the beginning?
Standard of Proof 6: Acknowledgment in this TIQ and submit manufacture technical data manual or specification sheet showing the capabilities in 3.1.10.2.
Offeror Answer 6: Yes____ No____
Criteria 7: The offeror shall provide a full turn-key installation of the system that include all equipment, manpower, tools, labor and materials to remove the existing control system and install the new dynamometer control system and make it fully operational and functional (SOW section 5.1)
Question 7: Can the offeror provide a full turn-key installation of the system that include all equipment, manpower, tools, labor and materials to remove the existing control system and install the new dynamometer control system and make it fully operational and functional?
Standard of Proof 7: Acknowledgment in this TIQ and submit a schedule and milestone that will detail to a level that clearly indicates thorough in-depth planning coupled with realistic scheduling and indicates the delivery date of all contract deliverables.
Offeror Answer 7: Yes____ No____
Criteria 8: The offeror shall provide a full-time (start of installation to completion of final acceptance test) field supervisor to direct installation, testing of the equipment and shall have full authority to implement field decisions expeditiously (SOW section 5.1.6)
Question 8: Can the offeror provide a full-time (start of installation to completion of final acceptance test) field supervisor to direct installation, testing of the equipment and have full authority to implement field decisions expeditiously?
Standard of Proof 8: Acknowledgment in this TIQ that the offeror is capable of providing a full time field supervisor.
Offeror Answer 8: Yes____ No____
Criteria 9: The offeror shall provide one or more qualified representatives who are knowledgeable in English and are thoroughly familiar with all aspects of the engine dynamometer test cell equipment, installation, calibration, maintenance, and operation, for the purpose of training Government personnel (SOW section 6)
Question 9: Can the offeror provide one or more qualified representatives who are knowledgeable in English and are thoroughly familiar with all aspects of the engine dynamometer test cell equipment, installation, calibration, maintenance, and operation, for the purpose of training Government personnel?
Standard of Proof 9: Acknowledgement in this TIQ that the offeror is capable of providing a one or more qualified representatives to provide the training to Government personnel.
Offeror Answer 9: Yes____ No____
Criteria 10: The offeror shall submit a schedule and milestones chart that is detailed to a level that clearly indicates thorough in-depth planning coupled with realistic scheduling and indicates the delivery date of all contract deliverables (SOW section 7.2.)
Question 10: Can the offeror submit a schedule and milestones chart that is detailed to a level that clearly indicates thorough in-depth planning coupled with realistic scheduling and indicates the delivery date of all contract deliverables?
Standard of Proof 10: Acknowledgment in this TIQ and submit a schedule and milestone chart.
Offeror Answer 10: Yes____ No____