LETTERKENNY ARMY DEPOT

PURCHASE DESCRIPTION

Blast Booth 44 Screening System - BLDG 350

1. GENERAL REQUIREMENTS

1.1. SCOPE: This specification shall apply to adding media screening equipment to the media recycle system for blast booth #44 in building 350. The purpose for this screening system is to allow the media changeover from garnet to stainless steel grit.

The screening system will aid in recycling all the usable stainless steel grit since it is a more expensive blast media. The screen system will sieve all used media and send back into the blast booth any media that is larger than a 30 screen size and smaller than a 100 screen size particle. The blast booth will be located at building 350 at Letterkenny Army Depot (LEAD), Chambersburg, PA. The specification calls for a turnkey operation and the successful contractor shall install the new system, any ductwork required and associated components herein in their entirety, including all necessary electrical, plumbing for compressed air, ventilation, fire alarm system tie in, and ductwork modifications required for system operation. The contractor shall furnish all materials, equipment, and labor needed to meet all requirements described in this solicitation and shall provide a complete and usable system. The contractor shall also perform testing to indicate full operational compliance with this contract and shall also provide system training for necessary personnel at 350.

1.2. GENERAL INFORMATION

1.2.1. Place and Performance of Installation: The blast booth media recycling system upgrades will be installed in the north end of building 350 next to door 12 on the east side of the building. The blast booth modifications will tie in equipment at the blast booth with the dust collector which is outside the building on a support structure with controls inside the building. See attachment A for a layout showing approximate locations. Any controls will be in the blast booth area and tied to controls for the overall system that are located next to door 12. All work will be performed between the hours of 6:00 AM and 3:30 PM, Monday thru Thursday, exclusive of Federal Holidays and special depot closures (Typically the Monday before or Friday after Federal Holidays that fall on a Saturday, Sunday, Tuesday or Thursday). Other hours, weekend, and holiday work will be considered separately as requested by the contractor and approved by the Contracting Officer.

1.2.2. Security Requirements: The contractor shall be responsible to ensure that all employees and subcontractor employees that will visit the depot shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce shall comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.2.3. Security, Safety, and Fire Protection: All work shall comply with LEAD pamphlet 385-4. The equipment and the installation shall also meet all the safety criteria set forth in OSHA 1926.501 and ANSI/ASSE Z359.

1.2.4. AT Level I Awareness Training: All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: www.lead.army.mil.

1.2.5. iWATCH Training: The contractor and all associated sub-contractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the TPOC or contracting officer. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the TPOC and contracting officer within 15 calendar days after completion of training. iWATCH training is available on the Letterkenny Army Depot homepage – www.lead.army.mil

1.2.6. OPSEC Training: Per AR 530-1, Operations Security. Contractor employees and associated sub-contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer if a COR is not assigned, within 15 calendar days after completion of training. Level 1 OPSEC training is available on the Letterkenny Army Depot homepage – www.lead.army.mil

1.2.7. Badges: Identification badges will be issued for admittance of personnel before performing work or service on this contract. The identification badge is the property of the US Government and shall be returned upon termination or demand. The contractor/vendor shall ensure all badges issued to employees are returned to the Badge and Identification Section, Security Division, Letterkenny Army Depot promptly on termination of need or on expiration, which occurs first. The badge room is located in Bldg. 2, phone # 717-267-5301. Hours of operation are 7:30 AM to 3:30 PM, Monday thru Thursday, exclusive of Federal Holidays.

2. Government Furnished property and Materials: The government will provide the facilities, equipment, materials and/or services listed below

2.1. Facilities: The government will provide clear access to all working areas necessary for the contractor to perform the installation outlined, during the hours listed in section

1.2.1 above

2.2. Equipment: A dust collection/recovery system that this equipment shall tie into.

The dust collection system is comprised of a media auger recovery system with elevator with scalping screen followed by an air wash and an 8 cubic foot double blast pot.

2.3. Materials/Services:

2.3.1. Provide a single point of connection for power and compressed air within 25 feet of the blast booth. Power will be provided via a fused disconnect switch or circuit breaker depending on availability.

2.3.2. Provide staging space for parts and equipment near the project.

2.3.3. Provide a work area for installation crew and their tools near the project.

2.4. Utilities: Provide electricity and compressed air for vendor tools.

3. Contractor Responsibilities: The contractor shall be responsible for the following:

3.1. Provide design and construction drawings completed by an engineer licensed in the state of Pennsylvania for review and approval prior to ordering equipment (see 3.2 for time requirements).

3.2. Provide a summary of the required utilities and general layout 60 days prior to the equipment delivery, and the detailed installation requirements (to include installation schematics and installation schedule) 30 days prior to equipment delivery.

3.3. Supply all equipment, parts, labor and materials necessary for off-loading, positioning, installation and operation of the system.

3.4. Provide all labor and materials required to install and incorporate a blast media screening system in a blast media recovery system including screening system, a means for transferring the media to either the blast pot, a waste drum, or to the exhaust ductwork.

3.5. All screening equipment, media transfer equipment, fans, motors, valves, piping, ductwork, supports, and all other parts required for installation and labor for a complete and usable system.

3.6. All materials shall be spec’d to function within system guidelines for media flow rates, system pressure, and air velocity.

3.7. Ensure that all welding is performed in accordance with AWS D1.1.

3.8. Ensure that all plumbing follows the applicable codes for ASME B31.3 process piping.

3.9. Ensure that the electrical installation is performed in accordance with the National Electrical Code. All electrical work shall be subject to inspection by LEAD electricians.

3.10. Contractor shall make final connection to a government installed disconnect switch or breaker located within 25 feet of the test cell. Supplied voltage will be 480 Volt, 3-phase, 3-wire with a separate equipment grounding conductor. Contractor shall provide any transformation to other required voltages.

3.11. Remove all excess equipment, shipping crates, scrap and consumable materials used by the contractor for shipment and installation of the system.

3.12. The contractor shall supply no fewer than two of each special tool required to service the system and its components.

3.13. The contractor shall be responsible for obtaining site/equipment measurements and dimensions. Any dimensions provided by government personnel shall be considered approximate and shall not be used for design purposes. Failure of the contractor to acquaint himself with conditions attending the work site will not be considered sufficient reason for changing the cost or performance schedule of this project.

3.14. The contractor shall coordinate all layout, saw cut, and wall penetrations with the government representative for plumbing, electrical, and ductwork.

3.15. No structural members shall be removed or modified to make penetrations. All penetrations shall be sealed with a material acceptable for use on existing walls in the test cell area.

4. SPECIFICATIONS

4.1. General Requirements

4.1.1. The system shall utilize screening equipment to reuse media between the particle size of a 30 mesh screen and a 100 mesh screen. Any media smaller than 100 mesh and larger than 30 mesh screen shall treated as waste.

4.1.2. The media’s path through the media recycle system shall be modified to include screening equipment. (See process flow diagram attachment B).

4.1.3. A means of transferring media from the screening system to either the blast pot or media waste shall be included.

4.1.4. If transfer from the screening system to the blast pot is gravity fed by inserting the new screening equipment and raising the current setup, than maintenance platform(s) shall be included.

4.1.5. From the screening system the media shall either be sent to the dust collector if it is below 100 mesh size or greater than 30 mesh size, and into the blast pot if it is between 30 and 100 mesh size.

4.1.6. All equipment within the complete system shall be sized for specified loads and run times.

4.1.7. The media to be utilized by this system shall be stainless steel grit with a working particle size range of 30 to 100 mesh, an average density of 225 lbs/cubic foot, and a Rockwell hardness rating of 64HRc.

4.1.8. The media screening system shall be located between booths 44 and 50 (see attachment A).

4.1.9. All screening, ductwork, piping, valves, etc. shall be provided for a complete system that is a turnkey upon completion.

4.1.10. Safe guards against sparks or explosion risks shall be built into the system.

4.1.11. All materials and equipment for electrical and control requirements shall be provided for a complete system that is turnkey.

4.1.12. All welding design procedures shall conform to AWS D1.1/D1.1M

4.1.13. All Plumbing shall conform to ASME B31.3 process piping.

4.1.14. The system installation shall meet the requirements of the international Plumbing Code, International Mechanical Code, and National Electric Code.

4.2. Equipment

4.2.1. Sweco Model CL60S888 Vibro-Energy Separator unit or Kason model K48-2-SS High Efficiency Circular Vibroscreen Separator or equivalent shall be included as part of this project.

4.2.2. The screen separator equipment shall be capable of handling a minimum of 5,000 pounds per hour of stainless steel grit blast media.

4.2.3. A means of transferring the separated good media to the blast pot shall be included as part of this project.

4.2.4. A means of transferring media that is too large or too small for reuse to the waste media system shall be included.

4.2.5. All necessary ductwork, hardware, fans, motors, etc. as required by the overall design shall be incorporated.

4.2.6. Any motors and electrical wiring, connections, etc. shall be rated for Class II Div. I.

4.2.7. Access ladders and platforms shall be included if any part of the new system requires maintenance above 4’

5. Safety/Fire System Requirements

5.1. Class II Div. I requirements shall be followed for all equipment added or modified as part of this project.

5.2. No alarm tie ins are required but any work requiring the existing alarm systems to be shut down for a temporary basis shall require coordination with the production department, safety department, and fire department.

5.3. Hot work permits, if needed will require a minimum of 24 hour notice to the fire department and safety department.

5.4. Confined space permits, if needed will require a minimum of 24 hour notice to the safety department.

5.5. Specialized training certifications will be required for any hot work or confined space work necessary as part of the installation.

5.6. Any special equipment needed for hot work or confined space shall be provided and available for inspection as part of the permit process.

5.7. Fall protection training and tie off equipment shall be required for any work required at over 4 feet above floor level.

6. Electrical

6.1. All electrical construction for the system shall be NEC rated as required.

6.2. Complete electrification shall be provided.

6.3. All bus box disconnects, conduit, control boxes, starters, and associated electrical components necessary to make the equipment operational shall be included.

6.4. The primary voltage shall be 480 volt, 3-phase, 60 hertz, and 3 wire with a separate equipment grounding conductor. Contractor shall provide any transformation to other required voltages.

6.5. All enclosures shall have a NEMA 3 rating.

6.6. The equipment provided shall conform to the specifications cited herein and shall be designed and constructed in accordance with NFPA 70.

7. NAMEPLATE: A corrosion resistant metal nameplate shall be securely attached to the system. The nameplate shall contain the information listed below:

7.1. Nomenclature

7.2. Manufacturer’s Name

7.3. Manufacturer’s Model Designation

7.4. Manufacturer’s Serial Number

7.5. Input Voltage, Current, Phase, and Hertz

7.6. Date of Manufacture

8. DRAWINGS AND MANUALS: Two sets of the manufacturer’s design drawings shall be submitted for approval within 4 weeks of award. Approval shall be provided within 10 days after receipt by LEAD engineering personnel. Two sets of operator instruction manuals, maintenance service manuals and parts listing manuals shall be provided for the unit. These manuals shall be written in the English language.

9. HAZARDOUS MATERIALS: Two sets of listing for all lubricants, seals, and/or any other hazardous material necessary for preventive and corrective maintenance along with their respective Safety Data Sheets (SDS) shall be submitted for approval within 4 weeks of award. These lists and SDS shall be written in the English language.

10. WARRANTY: A standard commercial warranty or a one year commercial warranty, whichever is larger, shall be furnished with the media screening system in its entirety.

The warranty shall cover the screening equipment, media transfer equipment, ductwork, control panel, platforms and all other components of the system. The warranty period begins when the LEAD Contracting Officer provides official confirmation that the system has satisfied all operational provisions of the contract.

11. STANDARD PRODUCTS: The unit and ancillary equipment shall be new and regularly advertised products in order to provide a constant source of replacement parts and technical assistance.

12. PRESERVATION, PACKAGING AND DELIVERY: The contractor shall utilize standard commercial methods for preservation and packaging appropriate for the equipment provided. As a minimum, all areas susceptible to damage from exposure to the elements shall be preserved and/or packed to prevent damage. The contractor shall be responsible for ensuring the equipment is delivered to LEAD in good condition.

LEAD will assume no responsibility for off-loading or storage of the provided equipment.

13. INSPECTION AND ACCEPTANCE

13.1. The blast booth media screening and associated equipment shall be examined for design, construction, materials, components, and workmanship to determine compliance with the contract and this specification. Any deviation from these requirements shall be cause for rejection.

13.2. The contractor shall be responsible for developing test procedures to demonstrate compliance with the requirements of this specification. All test procedures shall be submitted to and approved be Depot Technical Point of Contact (TPOC) prior to the start of testing. To support the testing procedures, LEAD will provide operators, blast media and an asset for testing the blast media screening system and training.

14. INSTRUCTION: The contractor shall conduct no less than 2 hours of operator training for up to 6 personnel that are already familiar with the operation of LEAD’s blast operations, and shall conduct no less than 4 hours of maintenance training for up to 6 personnel familiar with the maintenance of LEAD’s blast booth system.

15. APPLICABLE DOCUMENTS

15.1. OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)

29 CFR, 1910.94, Ventilation.

(Copies may be obtained at www.osha.gov)

15.2. Unified Facilities Criteria (UFC) 3-410-04N, Industrial Ventilation (Copies may be obtained at www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc )

15.3. ANSI Z9.4-2011, Abrasive-Blasting Operations – Ventilation and Safe Practices for Fixed Location Enclosures (Copies may be obtained at www.ansi.org)

15.4. AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

B31.3 Code for Pressure Piping, Process Piping (Copies may be obtained at www.asme.org)

15.5. NATIONAL ELECTRICAL MANUFACTURER’S ASSOCIATION (NEMA)

NEMA 250 Enclosures for Electrical Equipment (Copies may be obtained at www.nema.org)

15.6. AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M Structural Welding Code (Copies may be obtained at www.aws.org)

15.7. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 National Electrical Code (NEC) NFPA 101 Life Safety Code (Copies may be obtained at www.nfpa.org)

15.8. LETTERKENNY ARMY DEPOT (LEAD)

LEAD Regulation 385-1 Safety and Occupational Health Program and 385-4 Safety pamphlet for contractors. Copies may be obtained from LEAD Directorate of Contracting, Bldg. 2)