Asbestos_Survey.doc
DOC document 184 KB Posted
- Attached to
- Replace HVAC System in Building 1937 Federal contract opportunity
- Solicitation number
- W91151-17-B-0006
About this file
Asbestos Survey
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract_of_Bids-17-B-0006_(IFB).pdf | ||
| C-103_Revised_Drawings.pdf | ||
| Approved_Amendment_2.pdf | ||
| Approved_Amendment_1.pdf | ||
| Site_Visit_Sign_in_Sheet.pdf | ||
| Approved_Solicitation.pdf | ||
| Attachment_1-_Specifications_Appendix_A_04-Aug-2016.pdf | ||
| TECH_EXHIBIT_A_-_Specifications.pdf | ||
| TECH_EXHIBIT_B_-_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASBESTOS SURVEY REPORT
BUILDING 1937
FORT HOOD, TEXAS
Submitted to:
U.S. Army Corps of Engineers, Fort Worth District
For:
U.S. Army Corps of Engineers, Tulsa District
Prepared by:
Radian International LLC
8501 N. Mopac Blvd.
P.O. Box 201088
Austin, Texas 78720-1088
September 1997
Table of Contents
1.0
INTRODUCTION
1.1 Physical Inspections
1.2 Bulk Sampling and Analysis
1.3 Sample Numbering Scheme
2.0
FACILITY DESCRIPTION
3.0
DISCUSSION OF RESULTS
4.0
RISK ASSESSMENT
5.0
ABATEMENT COST ESTIMATES
APPENDIX A:
HOMOGENEOUS AREAS AND DETAILED ANALYTICAL RESULTS FOR BUILDING 1937 SURVEY
APPENDIX B:
BUILDING 1937 FLOOR PLAN
APPENDIX C:
REPRESENTATIVE PHOTOGRAPHS OF ACM AND PACM IN BUILDING 1937
APPENDIX D:
RISK ASSESSMENT METHODOLOGY AND DATA FOR BUILDING 1937
List of Figures
B-1 Building 1937 Floor Plan--First Floor B-1
B-2 Building 1937 Roof Plan B-2
List of Tables
3-1 Summary of ACM and PACM in Building 1937
4-1 Priority Rating Table for Recommended Response Actions
4-2 Building 1937 Risk Assessment Results
5-1 Building 1937 Abatement and Replacement Cost Estimates
5-2 Building 1937 Repair Cost Estimates
A-1 Building 1937 Homogeneous Areas A-1
A-2 Building 1937 Asbestos Survey Analytical Results A-2
B-1 Inspector, Risk Assessor, and Laboratory Licenses for Building 1937 B-3
D-1 Damage/Risk Values for Inspection Observations D-2
D-2 Exposure Values for Inspection Observations D-2
D-3 Summary of Damage/Risk Observations for ACM and PACM in Bldg. 1937 D-3
D-4 Summary of Exposure Observations for ACM and PACM in Bldg. 1937 D-3
List of Photographs (Appendix C)
Photo 1937-1-B: 12x12 beige floor tile; throughout interior except women’s and men’s restrooms, kitchen, Storage Rooms #118 and #120, and Janitor's Room #119
Photo 1937-1-E: Building caulkings and putties; interior and exterior windows and doors
Photo 1937-1-F: 9x9 dark brown floor tile; Storage Room #112
Acronyms and Abbreviations
ACM
Asbestos-containing material
Act.
Actinolite
Am.
Amosite
Anth.
Anthophyllite
Cell.
Cellulose
Chry.
Chrysotile
COR
Contracting Officer’s Representative
Croc.
Crocidolite
D
Damage/risk factor
DS
Dispersion staining
E
Exposure factor
EPA
United States Environmental Protection Agency
Fib.
Fiberglass
GRADE
Air Force Guidance for Rating Damage and Exposure
ID
Identification
LLC
Limited liability company m
Meter m2
Square meter
M.W.
Mineral wool
N/A
Not analyzed
NA
Not applicable
ND
Not detected
O&M
Operations and maintenance
PACM
Presumed asbestos-containing material
PLM
Polarized light microscopy
QA
Quality assurance
QC
Quality control
R
Risk rating
RPD
Relative percent difference
SACM
Suspect asbestos-containing material
SWD
Southwest Division (Laboratory)
Syn.
Synthetics
T
Total
TDH
Texas Department of Health
Trem.
Tremolite
TSI
Thermal systems insulation
USACE
United States Army Corps of Engineers
1.0
INTRODUCTION
Radian International LLC, under contract with the United States Army Corps of Engineers (USACE), Contract DACA56-94-D-0015, performed a facility-wide asbestos survey at Fort Hood, Texas, to meet the following project objectives:
· Identify and locate, to the extent possible, all friable and non-friable suspect asbestos-containing materials (SACM);
· Evaluate the condition of the SACM, collecting sufficient data to perform a risk assessment and to prioritize materials for appropriate response actions;
· Collect and analyze bulk material samples in order to quantify, in metric units, SACM which contain greater than 1% asbestos;
· Identify and quantify material which is presumed to contain asbestos;
· Conduct risk assessments for all asbestos-containing materials (ACM) and presumed ACM (PACM);
· Conduct air monitoring where necessary according to risk assessment models; and
· Prepare an Operations and Maintenance (O&M) program (under separate cover) for all ACM and PACM.
The survey included base buildings and approximately 10% of the family housing buildings at Fort Hood. Mr. Emmet Gray, Directorate of Public Works, is the post contact for this project. This report presents the findings from the asbestos survey at Building 1937.
1.1 Physical Inspections
Survey teams visually inspected the accessible areas of the interior and exterior of each building, including interior and exterior rooms, mechanical spaces, storage areas, crawl spaces, attics, and roofs, to identify appropriate homogeneous areas (i.e., unique SACM or PACM). A reasonable effort was made by the survey team to gain access to inaccessible areas. If access could not be gained, the survey team made assumptions regarding the presence and quantity of SACM based on the visual inspection of the remainder of the building and interviews with the building occupants.
The following steps were taken to complete physical inspections.
1. Obtain a copy of the building floor plan.
2. Perform an initial building walk-through.
a) Note fire doors/walls on the floor plan.
b) Identify homogeneous areas.
c) Identify locations of friable and non-friable SACM and PACM. PACM is defined as SACM which could be visually identified but which were inaccessible for sampling, or were not sampled at the client’s request.
d) Note the type, estimated quantity, description, friability, and physical damage of each SACM and PACM. Mark location(s) of SACM and PACM on the floor plan and take one color photograph of each homogeneous area to show materials and conditions present at the time of the survey.
e) Define the bulk sample locations.
1.2 Bulk Sampling and Analysis
Homogeneous materials were categorized by the survey teams as surfacing materials, thermal systems insulation (TSI), or miscellaneous materials. Building age, use, and size were taken into consideration, along with building materials, when determining sample locations. Three bulk samples were obtained from each SACM within each building surveyed. Homogeneous areas categorized as PACM were not sampled. Where applicable, bulk samples were collected from all material layers (e.g., roofing and flooring materials). Samples were collected by cutting, scraping, and/or coring. The following procedures were used during bulk sample collection:
1.
Mark sample locations on the floor plan using a unique identification number.
2.
Record SACM sample information on a field data sheet, including:
a) Building number and room number/area description;
b) Typical occupancy and population;
c) SACM description (e.g., pipe insulation, 9x9 brown floor tile, etc.);
d) Estimated quantity of SACM (i.e., area or length);
e) Friability;
f) Physical damage;
g) Potential for damage or disturbance during maintenance;
h) Potential cause of damage or disturbance; and
i) Unique sample identification number.
3.
Take one color photograph from each homogeneous area to show materials and conditions present at the time of the survey.
4.
Repair any damage caused by sampling using sealants and methods approved by the Contracting Officer’s Representative (COR).
Samples were analyzed by RJ Lee Group, Inc. laboratory in Houston, Texas, using polarized light microscopy (PLM) coupled with dispersion staining (DS) in accordance with the Environmental Protection Agency (EPA)-approved method USEPA 600/R-93/116: “Method for Determination of Asbestos in Bulk Building Samples.” In accordance with the Scope of Work dated 20 August 1996, point-counting was not performed. In order to meet quality assurance/quality control (QA/QC) requirements, triplicate samples were collected from 5% of the sample locations for the overall project. Two of the samples, the normal and duplicate samples, were analyzed by the RJ Lee Group laboratory. The third sample is the QA sample that was sent to the USACE Southwestern Division Laboratory (SWD) in Dallas, Texas.
1.3 Sample Numbering Scheme Unique identification numbers were assigned to each sample using the following numbering scheme:
aaaaa-b-c-xd, where:
aaaaa identifies the five-digit building number;
b identifies the subdivision within that building;
c identifies the homogeneous area;
x identifies the sample type, where:
0 = normal sample
8 = field duplicate (QC sample)
9 = QA sample d identifies the sample number (1,2, or 3)
[Note: “b-c” represents the unique homogeneous area identification (ID) for a particular building. When necessary, “e” is used by the laboratory to identify additional layers of material not separated in the field (e.g., tile and mastic associated with flooring materials).]
2.0
FACILITY DESCRIPTION
Building 1937, encompassing an area of 5427 sq ft, is a Rod and Gun Club built in 1966. A building floor plan is presented in Appendix B.
3.0
DISCUSSION OF RESULTS
Building 1937 was inspected during December 1996. During this inspection, 8 homogeneous areas were identified and 21 normal samples were collected. Table 3-1 presents a summary of ACM and PACM identified during the survey of Building 1937. Appendix A contains a detailed table of homogeneous area descriptions for all SACM and PACM, and PLM analytical results for samples collected in Building 1937. Sample and photograph locations are presented in the Building 1937 floor plan (see Appendix B). Table B-1 contains information regarding inspector, risk assessor, and laboratory licenses for this building survey. Appendix C contains representative photographs of each ACM and PACM identified in Building 1937.
Table 3-1
Summary of ACM and PACM in Building 19371
| Homogeneous Area |
| Area/Length |
| Physical |
ACM
| ID |
| Description & Location |
| Estimate |
| Units |
| Damage |
| Friability |
| Type |
| 1-B |
| 12x12 beige floor tile; throughout interior except women’s and men’s restrooms, kitchen, Storage Rooms #118 and #120, and Janitor's Room #119 |
| 71.9 |
| m2 |
| Minimal |
| None |
| ACM |
| 1-E |
| Building caulkings and putties; interior and exterior windows and doors |
| 0.50 |
| m2 |
| Low |
| None |
| PACM |
| 1-F |
| 9x9 dark brown floor tile; Storage Room #112 |
| 13.9 |
| m2 |
| Minimal |
| None |
| ACM |
1 A complete list of homogeneous areas and detailed analytical results are presented in Appendix A. Sample and photograph locations are shown on the building floor plan in Appendix B. Photographs are shown in Appendix C.
m2 Square meter
Homogeneous areas 1-B, 1-E, and 1-F were identified as containing ACM or PACM. The risk assessment and abatement cost estimates for these materials are further discussed in Sections 4 and 5. All areas of this building were accessible to the inspection team. Interior and incoming electrical wiring appeared to be non-ACM.
A field duplicate (QC) sample was collected at location 1937-1-A-01. The results of analysis for the QC sample indicated asbestos levels less than 1% (non-detect). These results are consistent with the normal sample, which also indicated that asbestos was not measured above 1 percent.
4.0
RISK ASSESSMENT
A risk assessment was conducted for each homogeneous area containing ACM or PACM identified within the building using a modified version of the Air Force Guidance for Rating and Assessing Damage and Exposure (GRADE) evaluation system. This system employs an algorithm that assists the risk assessor in assigning priorities to various situations identified during the inspection. The GRADE system divides the risk into two categories: damage/risk factors (D) and exposure factors (E). These factors are summed and placed in the following equation:
R = 12.0324 - [(0.1683 x D) + (0.1693 x E)].
Table 4-1 was used to establish a priority rating for each homogeneous area, based on the risk rating or “R” value.
Table 4-1
Priority Rating Table for Recommended Response Actions
| Risk Rating (R) |
| Priority |
| Recommended Response Action |
| R < 6 |
| 1 |
| Immediate removal/repair |
| 6 ( R < 8 |
| 2 |
| Planned removal/repair; place in O&M program in interim 1 |
| 8 ( R < 10 |
| 3 |
| Place in O&M program |
| R (10 |
| 4 |
| No action required; place in O&M program as a precaution |
1 If material is repaired, it will remain in the O&M program until it is removed.
O&M Operations and maintenance
R Risk Rating Risk assessments for the homogeneous areas identified as ACM or PACM in Building 1937 are provided in Table 4-2. Appendix D contains a summary of field observations used to determine damage/risk factors (D) and exposure factors (E). The methodology used to determine these factors is also provided in Appendix D. No air sampling was required in this building based on risk assessment models.
Table 4-2
Building 1937 Risk Assessment Results
| Homogeneous Area |
| ACM |
| Risk |
| ID |
| Description & Location |
| Type |
| Rating (R) |
| Priority |
| 1-B |
| 12x12 beige floor tile; throughout interior except women’s and men’s restrooms, kitchen, Storage Rooms #118 and #120, and Janitor's Room #119 |
| ACM |
| 9.33 |
| 4a |
| 1-E |
| Building caulkings and putties; interior and exterior windows and doors |
| PACM |
| 8.31 |
| 4a |
| 1-F |
| 9x9 dark brown floor tile; Storage Room #112 |
| ACM |
| 9.33 |
| 4a |
a Priority rating is 4 because material is not friable.
5.0
ABATEMENT COST ESTIMATES
Abatement cost estimates are based on professional experience and costs from 1996 Fort Hood asbestos abatement contracts. Cost estimates were developed using the unit costs for abatement of the general category of material and the estimated area of identified ACM determined during the survey. Unit rates for abatement include labor, materials, equipment, overhead, insurance, and profit. Abatement unit rates do not include costs for design, air sampling, materials replacement, or off-site disposal. Total costs do not include contract administration costs.
Cost estimates were developed using the assumption that all materials within a building would be abated concurrently. In addition, costs are based on the assumption that all ACM which is friable or which has the potential to become friable during demolition will require removal. Detailed cost estimates for abatement, replacement, and repair of ACM in Building 1937 are presented in Tables 5-1 and 5-2.
Table 5-1
Building 1937 Abatement and Replacement Cost Estimates
| Homogeneous Area |
| Area/Length |
| Unit Cost for |
| Total Cost |
| ID |
| Description & Location |
| Estimate |
| Units |
| Abatement |
| ($) |
| 1-B |
| 12x12 beige floor tile; throughout interior except women’s and men’s restrooms, kitchen, Storage Rooms #118 and #120, and Janitor's Room #119 |
| 71.9 |
| m2 |
| $18.83/m2 |
| $1,354 |
| 1-E |
| Building caulkings and putties; interior and exterior windows and doors |
| 0.50 |
| m2 |
| $107.60/m2 |
| $54 |
| 1-F |
| 9x9 dark brown floor tile; Storage Room #112 |
| 13.9 |
| m2 |
| $18.83/m2 |
| $262 |
| Subtotal |
| $1,669 |
| Design Fee (6%) |
| $100 |
| Air Monitoring Cost (10%) |
| $167 |
| Materials Replacement |
| $1,378 |
| Off-site Disposal Cost |
| $172 |
| TOTAL ESTIMATED ABATEMENT COST |
| $3,487 |
Table 5-2
Building 1937 Repair Cost Estimates
| Homogeneous Area |
| Approximate Damaged Area/Length |
| Unit Cost for |
| Total Cost |
| ID |
| Description & Location |
| Estimate |
| Units |
| Repair |
| ($) |
| 1-B |
| 12x12 beige floor tile; throughout interior except women’s and men’s restrooms, kitchen, Storage Rooms #118 and #120, and Janitor's Room #119 |
| 14 |
| m2 |
| $18.83/m2 |
| $264 |
| 1-E |
| Building caulkings and putties; interior and exterior windows and doors |
| 0.50 |
| m2 |
| $107.60/m2 |
| $54 |
| 1-F |
| 9x9 dark brown floor tile; Storage Room #112 |
| 13.9 |
| m2 |
| $18.83/m2 |
| $262 |
| Subtotal |
| $579 |
| Design Fee (6%) |
| $35 |
| Air Monitoring Cost (10%) |
| $58 |
| Materials Replacement |
| $456 |
| Off-site Disposal Cost |
| $56 |
| TOTAL ESTIMATED REPAIR COST |
| $1,184 |
APPENDIX A
HOMOGENEOUS AREAS AND DETAILED ANALYTICAL RESULTS FOR BUILDING 1937 SURVEY
Table A-1
Building 1937 Homogeneous Areas 1
| Homogeneous Area |
| ACM |
| ID |
| Description & Location |
| Type 2 |
| 1-A |
| 2x4 white ceiling tile; Rooms #107, 111-115, and 117-120 |
| None |
| 1-B |
| 12x12 beige floor tile; throughout interior except women’s and men’s restrooms, kitchen, Storage Rooms #118 and #120, and Janitor's Room #119 |
| ACM |
| 1-C |
| Cove molding mastic; throughout interior at base of walls excluding men’s and women’s restrooms, kitchen, and mechanical room |
| None |
| 1-D |
| Interior wallboard; Rooms #101, 102, 106, 108, 109 and sub-room in #117 |
| None |
| 1-E |
| Building caulkings and putties; interior and exterior windows and doors |
| PACM |
| 1-F |
| 9x9 dark brown floor tile; Storage Room #112 |
| ACM |
| R-A |
| Rolled-on roofing and underlayment |
| None |
| R-B |
| Roof penetration mastics |
| None |
1 Sample and photograph locations are shown on the building floor plan in Appendix B. Photographs of PACM and ACM are shown in Appendix C.
2 ACM types include:
ACM
Materials containing >1% asbestos;
None
Materials containing ( 1% asbestos; and
PACM
Materials presumed to contain >1% asbestos.
ACM
Asbestos-containing material
ID
Identification
PACM
Presumed asbestos-containing material
Table A-2
Building 1937 Asbestos Survey Analytical Results1
| Homogeneous Area |
| Asbestos Results (%) |
| Other Fibrous Materials Results (%) |
| Area ID |
| Sample ID |
| Layer |
| Layer Description |
(from Laboratory)
| Total |
| Act |
| Am |
| Anth |
| Chry |
| Croc |
| Trem |
| Cell |
| Fib |
| M.W. |
| Synth |
| ACM |
Type
| 1-A |
| 1937-1-A-01 |
| NA |
| Tan Ceil Tile/Wht Paint |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 25 |
| ND |
| 60 |
| ND |
| None |
| 1937-1-A-02 |
| NA |
| Tan Ceil Tile/Wht Paint |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 25 |
| ND |
| 60 |
| ND |
| None |
| 1937-1-A-03 |
| NA |
| Tan Ceil Tile/Wht Paint |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 25 |
| ND |
| 60 |
| ND |
| None |
| 1937-1-A-81 |
| NA |
| Tan Ceil Tile/Wht Paint |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 25 |
| ND |
| 60 |
| ND |
| None |
| 1-B |
| 1937-1-B-01 |
| NA |
| Tan Floor Tile |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| None |
| 1937-1-B-02 |
| a |
| Tan Floor Tile |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| None |
| 1937-1-B-02 |
| b |
| Blk Mastic |
| 5.00 |
| ND |
| ND |
| ND |
| 5 |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ACM |
| 1937-1-B-02 |
| NA |
| Total |
| 0.05 |
None
| 1937-1-B-03 |
| NA |
| Tan Floor Tile |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| None |
| 1-C |
| 1937-1-C-01 |
| NA |
| Tan Mat'l |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 0.9 |
| ND |
| ND |
| ND |
| None |
| 1937-1-C-02 |
| NA |
| Tan Mat'l |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| None |
| 1937-1-C-03 |
| NA |
| Tan Mat'l |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| None |
| 1-D |
| 1937-1-D-01 |
| a |
| Tan Plaster |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 3 |
| ND |
| ND |
| ND |
| None |
| 1937-1-D-01 |
| b |
| Tan Paper |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 100 |
| ND |
| ND |
| ND |
| None |
| 1937-1-D-01 |
| NA |
| Total |
| ND |
None
| 1937-1-D-02 |
| a |
| Wht Plaster |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 3 |
| ND |
| ND |
| ND |
| None |
| 1937-1-D-02 |
| b |
| Tan Paper/Tan Paint |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 100 |
| ND |
| ND |
| ND |
| None |
| 1937-1-D-02 |
| NA |
| Total |
| ND |
None
| 1937-1-D-03 |
| a |
| Wht Plaster |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 3 |
| ND |
| ND |
| ND |
| None |
| 1937-1-D-03 |
| b |
| Tan Paper/Tan Paint |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 100 |
| ND |
| ND |
| ND |
| None |
| 1937-1-D-03 |
| NA |
| Total |
| ND |
None
| 1-F |
| 1937-1-F-01 |
| a |
| Brn Floor Tile |
| 4.00 |
| ND |
| ND |
| ND |
| 4 |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ACM |
| 1937-1-F-01 |
| b |
| Blk Mastic |
| 5.00 |
| ND |
| ND |
| ND |
| 5 |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ACM |
| 1937-1-F-01 |
| NA |
| Total |
| 4.01 |
ACM
| 1937-1-F-02 |
| a |
| Brn Floor Tile |
| 4.00 |
| ND |
| ND |
| ND |
| 4 |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ACM |
| 1937-1-F-02 |
| b |
| Blk Mastic |
| 5.00 |
| ND |
| ND |
| ND |
| 5 |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ACM |
| 1937-1-F-02 |
| NA |
| Total |
| 4.01 |
ACM
| 1937-1-F-03 |
| a |
| Brn Floor Tile |
| 4.00 |
| ND |
| ND |
| ND |
| 4 |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ACM |
| 1937-1-F-03 |
| b |
| Blk Mastic |
| 5.00 |
| ND |
| ND |
| ND |
| 5 |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ACM |
| 1937-1-F-03 |
| NA |
| Total |
| 4.01 |
ACM
| R-A |
| 1937-R-A-01 |
| NA |
| Blk Fibr Rf Shngl/Wht Frit |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 2 |
| None |
| 1937-R-A-02 |
| NA |
| Blk Fibr Rf Shngl/Wht Frit |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 2 |
| None |
| 1937-R-A-03 |
| NA |
| Blk Fibr Rf Shngl/Wht Frit |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 2 |
| None |
| R-B |
| 1937-R-B-01 |
| NA |
| Blk Fibr Mat'l |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 45 |
| ND |
| ND |
| ND |
| None |
| 1937-R-B-02 |
| NA |
| Blk Tar |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 0.9 |
| ND |
| ND |
| ND |
| None |
| 1937-R-B-03 |
| NA |
| Blk Tar |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| ND |
| 0.9 |
| ND |
| ND |
| ND |
| None |
1 Sample and photograph locations are shown on the building floor plan in Appendix B. Photographs of ACM and PACM are shown in Appendix C. If a sample contained multiple layers, all layers were analyzed separately. If any layer of a sample from a homogeneous area contained >1% asbestos, then that homogeneous area was classified as ACM. Totals (weighted composite average percent asbestos) are provided for samples with all layers containing >1% asbestos.
Asbestos-containing material
Act.
Actinolite
Am.
Amosite
Anth.
Anthophyllite
Cell.
Cellulose
Chry.
Chrysotile
Croc.
Crocidolite
Fib.
Fiberglass
ID
Identification
M.W.
Mineral wool
NA
Not applicable (sample contained single layer)
ND
Not detected (<1% asbestos)
Synth.
Synthetics
T Total
Trem.
Tremolite
APPENDIX B
BUILDING 1937 FLOOR PLAN
Table B-1
Inspector, Risk Assessor, and Laboratory Licenses for Building 1937
| Building and |
| Analytical Laboratory |
| Building Inspector/Risk Assessor |
| Date |
Homogeneous
Area ID1
| Name |
| TDH License # |
| License Exp. Date |
| Name |
| TDH License # |
| License Exp. Date |
| Inspected/ |
Sampled
| 1937-1-A |
| RJ Lee Group |
| 30-0051 |
| 02/26/97 |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
| 1937-1-B |
| RJ Lee Group |
| 30-0051 |
| 02/26/97 |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
| 1937-1-C |
| RJ Lee Group |
| 30-0051 |
| 02/26/97 |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
| 1937-1-D |
| RJ Lee Group |
| 30-0051 |
| 02/26/97 |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
| 1937-1-E |
| NA |
| NA |
| NA |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
| 1937-1-F |
| RJ Lee Group |
| 30-0051 |
| 02/26/97 |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
| 1937-R-A |
| RJ Lee Group |
| 30-0051 |
| 02/26/97 |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
| 1937-R-B |
| RJ Lee Group |
| 30-0051 |
| 02/26/97 |
| Tom Hughes |
| 60-0885 |
| 10/09/97 |
| 12/13/96 |
1 The sampling information (including laboratory, inspector, risk assessor, and sample date) is the same for all samples associated with a particular homogeneous area. Unique sample identification numbers were assigned to each sample using the following sample numbering scheme:
aaaaa-b-c-xd, where:
aaaaa identifies the five-digit building number;
b identifies the subdivision within that building;
c identifies the homogeneous area;
x identifies the sample type, where:
0 = normal bulk material sample
6 = normal personnel air monitoring sample
7 = normal environmental air monitoring sample
8 = field duplicate bulk material (QC sample)
9 = QA bulk material sample d identifies the sample number (1, 2, or 3);
[Note: “b-c” represents the unique homogeneous area ID for a particular building.]
Asbestos-containing material
ID
Identification
NA
Not applicable. (PACM was not sampled.)
PACM
Presumed asbestos-containing material
QA
Quality assurance
QC
Quality control
TDH
Texas Department of Health
APPENDIX C
REPRESENTATIVE PHOTOGRAPHS OF ACM AND PACM IN BUILDING 1937
APPENDIX D
RISK ASSESSMENT METHODOLOGY AND DATA FOR BUILDING 1937
Appendix D
Risk Assessment Data and Methodology
A risk assessment was conducted for each homogeneous area containing ACM or PACM identified within the building using a modified version of the Air Force Guideline for Rating and Assessing Damage and Exposure (GRADE) evaluation system. This system employs an algorithm that assists the risk assessor in assigning priorities to various situations identified during the inspection. The GRADE system divides the risk into two categories: damage/risk factors (D), and exposure factors (E). These factors are summed and used in the following equation:
R = 12.0324 - [(0.1683 x D) + (0.1693 x E)];
Where D = the sum of the values for the following damage/risk observations:
Material type
Potential for contact
Physical damage
Water damage
Potential for damage by repair/maintenance activities
Asbestos content;
And E = the sum of the values for the following exposure observations:
Area of damaged material
Material friability
Population
Activity/vibration
Ventilation
Air movement
Floors
Walls
Barriers
A further breakdown of the values for the subunits under each category is provided in Tables D-1 and D-2. Summaries of the inspection observations for damage/risk and exposure for the ACM and PACM in Building 1937 are presented in Tables D-3 and D-4.
Table D-1
Damage/Risk Values for Inspection Observations 1
| Material Type |
| Potential for Contact |
| Physical Damage |
| Water Damage |
| Potential for Damage by Repair/Maintenance Activities |
| Asbestos Content |
| Surfacing (4) |
| <10 ft, Low (2) |
| None (0) |
| No (0) |
| None (0) |
| >1-30% (1) |
| TSI, Ventilation (3) |
| <10 ft, Medium (5) |
| Minimal (2) |
| Yes (3) |
| Low (1) |
| >30-50% (3) |
| TSI, Other (1) |
| <10 ft, High (8) |
| Low (3) |
| Moderate (2) |
| >50% (5) |
| Misc., Damaged (1) |
| >10 ft, Low (0) |
| Moderate (4) |
High (3)
| Misc., Undamaged (0) |
| >10 ft, Medium (3) |
| High (5) |
>10 ft, High (5)
1 The value assigned to each category is shown in italics.
TSI
Thermal systems insulation
Table D-2
Exposure Values for Inspection Observations 1 Area of Damaged Material
(m or m2)
| Material Friability |
| Population |
| Activity/ |
Vibration
| Interior Ventilation |
| Air Movement |
| Floors |
| Walls |
| Barriers |
| <3 (0) |
| None (0) |
| None (0) |
| Low (0) |
| None (0) |
| None (0) |
| Smooth (1) |
| Smooth (1) |
| Permanent (1) |
| 3-30 (1) |
| Low (0) |
| 1-9 (1) |
| Occasional (2) |
| Return Only (2) |
| Perceptible (2) |
| Rough, Seamed (2) |
| Moderate (2) |
| Semipermanent (2) |
| 31-300 (2) |
| Moderate (2) |
| 10-200 (2) |
| Constant (5) |
| Supply Only (5) |
| Turbulent (5) |
| Carpet (4) |
| Pitted (3) |
| Minimal (3) |
| >300 (3) |
| High (5) |
| 201-500 (3) |
Supply & Return (7)
| Rough (4) |
| None (4) |
501-1,000 (4)
>1,000 (5)
1 The value assigned to each category is shown in italics.
Table D-3
Summary of Damage/Risk Observations for ACM and PACM in Building 1937
| Homogeneous Area |
| Material Type |
| Potential for Contact |
| Physical Damage |
| Water Damage |
| Potential for Damage by Repair/Maintenance Activities |
| Asbestos Content |
| 1937-1-B |
| Misc., Undamaged (0) |
| <10 ft, Low (2) |
| Minimal (2) |
| No (0) |
| None (0) |
| 1-30% (1) |
| 1937-1-E |
| Misc., Damaged (1) |
| <10 ft, Low (2) |
| Low (3) |
| No (0) |
| None (0) |
| PACM (1) |
| 1937-1-F |
| Misc., Undamaged (0) |
| <10 ft, Low (2) |
| Minimal (2) |
| No (0) |
| None (0) |
| 1-30% (1) |
Table D-4
Summary of Exposure Observations for ACM and PACM in Building 1937
| Homogeneous Area |
| Area of Damaged Material |
(m or m2)
| Material Friability |
| Population |
| Activity |
| Ventilation |
| Air Movement |
| Floors |
| Walls |
| Barriers |
| 1937-1-B |
| 3-30 (1) |
| None (0) |
| 10-200 (2) |
| Low (0) |
| None (0) |
| None (0) |
| Smooth (1) |
| Pitted (3) |
| None (4) |
| 1937-1-E |
| 3-30 (1) |
| None (0) |
| 10-200 (2) |
| Low (0) |
| None (0) |
| None (0) |
| Carpet (4) |
| Rough (4) |
| None (4) |
| 1937-1-F |
| 3-30 (1) |
| None (0) |
| 1- 9 (1) |
| Low (0) |
| None (0) |
| None (0) |
| Smooth (1) |
| Rough (4) |
| None (4) |
PAGE
Asbestos Survey, Fort Hood, Texas iii September 1997
Building 1937 f_1937.doc
File details come from the government source that posted it. Updated .