Approved_Amendment_2.pdf

PDF 30 KB Posted

Attached to
Replace HVAC System in Building 1937 Federal contract opportunity
Solicitation number
W91151-17-B-0006
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood

View the file

Other files for this federal contract opportunity

Other files attached to Replace HVAC System in Building 1937, newest first.
File Type Posted
Abstract_of_Bids-17-B-0006_(IFB).pdf PDF
Asbestos_Survey.doc DOC document
C-103_Revised_Drawings.pdf PDF
Approved_Amendment_1.pdf PDF
Site_Visit_Sign_in_Sheet.pdf PDF
Approved_Solicitation.pdf PDF
Attachment_1-_Specifications_Appendix_A_04-Aug-2016.pdf PDF
TECH_EXHIBIT_A_-_Specifications.pdf PDF
TECH_EXHIBIT_B_-_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0010983285 CA093390P

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

a) This amendment is issued to answ er Request for Information (RFI) questions from industry.

b) This amendment also provides revised draw ings and an asbestos survey to be included in this solicitation.

c) All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Jul-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91151-17-B-0006

X 9B. DATED (SEE ITEM 11)

20-Jun-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Jul-2017

CODE

MISSION AND INSTALLATION CONTRACTING

MISSION CONTRACTING OFFICE (MCO)

36000 DARNALL LOOP, ROOM 1300B

FORT HOOD TX 76544-5095

W91151 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91151-17-B-0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

RFI RESPONSES

1. Solicitation Description of Work, first paragraph on 4th page, states that the building will be occupied during the performance of the work. Will temporary cooling/heating be required while new condensing unit and air handler are being installed?

A: No, there will be a 4 week shutdown of the facility. The exact time will be coordinated with the occupant through the COR. At the conclusion of the 4 week outage, power will need to be restored to the facility and cooling/heating will need to be functional.

2. Solicitation, page 3, what is CLIN 0002 for?

A: All Army contracts are now required to collect manpower data on its contracts. Therefore, contractors must utilize the contractor manpower reporting website as provided in the solicitation, to input its manpower data. The associated cost with providing this data, if any, will be reflected in CLIN 0002 of your bid.

3. Confirm that adequate QC only is required – not dedicated full time?

A: Adequate QC is required.

4. Section 00100 Instructions to Offerors Note 1: With a hard dollar bid what is the purpose of a line item estimate?

A: Section 00100, Instructions to Offerors, paragraph 1, Submission of Bids, is revised to delete the requirement for a complete line item breakout of tasks, quantities and unit prices that reflects the complete work effort required by the contract.

5. The existing chiller is supported by a concrete beam at one end and the sidewalk on the other. The sidewalk concrete finish is higher than the beam at the other end. A 2” x 6” wood board is laid on top of the concrete beam to raise the chiller to level it. Drawing M-501 calls for a new 6” high concrete pad to be constructed under the chiller. Please confirm that this is required? At the site visit we were asked to submit an RFI about this question.

A: Yes, the contractor shall install a new 6” concrete pad for the chiller.

6. Drawing M-501 calls for a new 6” high concrete pad under the new Air Handler Unit. Again, we were asked to submit this question in an RFI.

A: Interior housekeeping equipment pads are to be 4”.

7. Will a dig permit be required? Will the piping from the chiller to the mechanical room be surface mounted?

A: A dig permit will likely be required for installation of the new housekeeping pad, but piping from the chiller to the mech room will be surface mounted.

8. Please provide the asbestos survey for this building.

A: See attached.

9. Please provide a copy of the site visit sign in sheet.

A: A copy of the sign-in sheet has been posted on the FBO.gov website.

10. The existing power lines above the chiller are very low. There will not be a 10’ clearance between the chiller and the power lines. We will not be allowed to use a crane to lift the new equipment into place. Can the power supply from the power pole to the building be turned off while this work is in progress?

A: Yes, there will be electrical changes in the contract. See revised/additional electrical drawings/scope of work.

11. The existing chiller is 3’ away from the adjacent wood building. Apparently the minimum clearance between the chiller and an adjacent obstacle is 4’. Can the new chiller be moved over slightly to get the required clearance?

A: Yes

12. General Note 3 on sheet D101A, “Demo gypsum board ceiling in men and women restrooms (for access to remove and replace the exhaust fans and associated accessories)”. At the site visit we were told that the entire ceilings need not be demo’ed if the removal and replacement of the exhaust fans can be done through a smaller opening. Please confirm that this is still so?

A: The exhaust fans are located on the roof. The contractor should demo and replace only the portion of ceiling required to make the specified changes; demo and replacement of the entire latrine ceiling is not required.

13. Detail 6 on sheet M-503 shows new 4” concrete pad under new AHU-1. Sheet M-501 detail 1 indicates 6” concrete pad under AHU-1. Which is it to be?

A: Only 4” pads are required on interior housekeeping pads.

14. The existing ACT ceilings in the building are in bad condition. Will the scope be increased to replace them?

A: No.

15. Has an asbestos survey be completed on this building, if so, please provide a copy 2. Should the exhaust fan in the restrooms be connected to the existing duct work or is new duct works required?

A: A copy of the asbestos survey will be provided. Reconnect fans to the existing ductwork.

16. Plans show demo of the sheetrock wall in the Mechanical room but no build back, is this correct?

A: There is no sheetrock wall in the mechanical room.

17. Will temporary cooling be required during the work?

A: No facility will be closed for 4 weeks to allow work to be completed.

18. The existing concrete pad is in very poor condition, should the existing pad be extended or replaced? A:

Replaced.

19. There are existing power lines over the chiller, these power lines need to be disconnected and removed to set the new chiller, will the government od this or should the contractor include this work? The new chiller is 92 1/2" tall, will this allow sufficient clearance below the power line after installation?

A: Reference the attached changes in scope for the electrical portion of this project.

20. Will commissioning be required for the chiller?

A: Yes.

SECTION 00010 - SOLICITATION CONTRACT FORM

TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Technical Exhibit A -

Specifications

3313 20-JAN-2017

Attachment 2 Technical Exhibit B - Drawings

16 19-JAN-2017

Attachment 3 Attachment 1 Specifications Appendix A

120 04-AUG-2016

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit _ Revised Drawings C-103 1 24-JUL-2017 Attachment 4 Asbestos Survey 21 24-JUL-2017

Attachment 5 Technical Exhibit B - Drawings

16 19-JAN-2017

Attachment 6 Technical Exhibit A - Specifications

3313 20-JAN-2017

Attachment 7 Attachment 1 Specifications Appendix A

120 04-AUG-2016

(End of Summary of Changes)