Solicitation W90VN6-22-R-0030 Question & Answer
Q1. The requirement of UNIT and Qty of Clin No. 0001 through 4001 option is 12 Months and FFP. How many working hrs for Months is?
1. Approximately 40-hours per week; 40x4weeks=160 hours.
1. No work during U.S. Federal Holidays and/or days observed by 51FW
Q2. Do you have how many estimated paid off days per year at this contract?
Please let me know your estimated paid off days (the vacation or the sick leave or another issue) per year for this contract period ?
1. 11 (eleven) observed federal holidays
Q3. Is possible to revise Qty and Unit from 12 Months to 1920 hrs ?
1. The 11 federal holidays are included in the 1920 hrs (160x12)
1. w/out the 11 federal holidays, 1920 – 88 = 1,832
1. “12 Months” would provide flexibility