AMENDMENT 02.docx

DOCX document 16 KB Posted

Attached to
RIGGING SERVICES (XRAY) CRANE, IN Federal contract opportunity
Solicitation number
W519TC23QRIGG
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This amendment modifies the statement of work and pricing sheet for a rigging services contract. The contractor must remove an old x-ray machine from Building 2167 by September 27th and offload and assemble a new x-ray machine at the dock of Building 2167 by 8:00 AM on September 28th. Insurance documentation and a lift plan for any crane usage must be included with proposals. The pricing sheet was revised to add a line item for moving an x-ray machine within Building 165 within 30-45 days of award. The solicitation number is W519TC23QRIGG and is issued by the Department of the Army Materiel Command Contracting Command at Rock Island Arsenal for rigging services related to x-ray equipment at Crane, Indiana. The time for offers was not extended.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 02 NARRATIVE AS FOLLOWS:

1. ATTACHMENT 01, PWS dated 15 AUG 2023 is changed to read:

5.0DELIVERY SCHEDULE
Deliverable
Deliverable due date ETA 28 SEP 2023
Insurance Requirement 3M
Must be provided with its Proposal.
REMOVE OLD XRAY B2167 NLT 27SEP
Work Coord. W/ POC
OFFLOAD/ASSY machine B2167 AT DOCK*
Work Coord. W/POC
Remove X-Ray B165
Work Coord. W/POC

* CURRENT ETA TO OFFLOAD NEW X-RAY EQUIPMENT AT THE DOCK- 28SEP, 8:00AM ET.

Contractor shall plan and make all provisions to meet this date for the contract execution upon award. Note: Rigging Contractor shall be on site to complete the Offload and Assembly of the X-Ray upon the delivery by 8:00 AM ET.

2. ATTACHMENT 02, PRICE SHEET IS CHANGED AND ATTACHED TO INCORPORATE LINE ITEM 002: BLDG 165 movement of X-Ray within 30-45 days of award, based on mutual agreement.

3. Language is added, to include a Work Lift Plan to be provided prior to start of work. This work plan will be required by the Government Safety Office, Crane, IN. A plan shall be provided by the contractor to be accepted by the Government. The plan will be provided with the contractor’s proposal.

Note: If the contractor will be using a crane to load the equipment on a truck once it is outside (or inside) the building, it is responsible for developing a lift plan. If the load will NOT be suspended from a crane or any other machine, then a lift plan is not required.

4. The contractor will return the price sheet (Attachment 02), along with its own documentation indicating that it understands the priority of work as discussed herein, a current lift work plan, required insurance, and its plan to meet below:

REMOVE OLD MACHINE: BLDG 2167 NLT 27 SEP.

OFFLOAD/ASSY new Machine BLGD 2167, 8AM SEP 28.

5. The Time for Offers is not extended.

File details come from the government source that posted it. Updated .