Attachment 01 PWS dtd 15 Aug 23.docx

DOCX document 2 MB Posted

Attached to
RIGGING SERVICES (XRAY) CRANE, IN Federal contract opportunity
Solicitation number
W519TC23QRIGG
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This statement of work outlines requirements for rigging services to move three x-ray systems at Crane Army Ammunition Activity in Crane, Indiana. A certified rigging contractor will provide equipment, materials and personnel to disassemble, pack, protect, rig, move, unpack and reassemble the x-ray machines. One system will be moved from building 2167 to building 3679, another will be moved into building 2167 upon delivery, and a third will be moved from building 165 to building 3679. The contractor must have experience rigging loads of approximately 30,000 pounds and follow all applicable safety standards. The contractor will provide documentation of insurance, signage confirming the moves, and the government technical point of contact will inspect the work. Performance will take place at the specified CAAA buildings. The solicitation number for these rigging services is W519TC23QRIGG.

View the file

Other files for this federal contract opportunity

Other files attached to RIGGING SERVICES (XRAY) CRANE, IN, newest first.
File Type Posted
Amendment 02 - Pricing Sheet.xlsx XLSX spreadsheet
AMENDMENT 02.docx DOCX document
Attachment 01 PWS dtd changes 31 Aug 23.docx DOCX document
Attachment 08 DRAWING SHEET (3 PAGES).pdf PDF
Attachment 07 NSI X5000 XRAY 450KV INSTALLATION GUJIDE.pdf PDF
Attachment 05 FAR 52-212-3-Offeror-Representations-and-Certifications.pdf PDF
Attachment 06 FAR 52-204-24 Full Text Provision Certification.pdf PDF
Attachment 04 52-212-5-Contract-Terms-and-Conditions-.docx DOCX document
Attachment 03 15-4821 (1) Rev 24 dated 30JUN2023.pdf PDF
Attachment 02 Pricing Sheet.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

MOVE X-RAY CABINETS

15 August 2023

Description of Requirement: Crane Army Ammunition Activity (CAAA), Crane, IN, has a requirement to move three x-ray systems:

1. BLDG 2167 NSI Conveyor X-ray system disassembly and move from BLDG 2167 to BLDG 3679 DRMO (approx. 6 miles);

2. New NSI X5000 X-ray system from delivery conveyance into location within BLDG 2167;

3. BLDG 165 X-ray system disassembly and move from BLDG 165 to BLDG 3679 DRMO (approx. 6 miles).

Efforts will include, but not limited to, disassembly to move equipment, rigging, crating, protecting equipment from damage during move, moving equipment, and re-assembly of equipment.

1. SCOPE

1.1 A certified rigging contractor will provide equipment, materials, and manpower for rough disassembly, packing, protecting, rigging, moving, unpacking, general assembly of x-ray equipment.

1.1.1 BLDG 2167 320 kV NSI Conveyor X-ray system disassembly and move from BLDG 2167 to BLDG 3679 DRMO (approx. 6 miles);

1.1.1.1 This task must be complete before moving the new x-ray system into BLDG 2167.

1.1.2 New NSI 450kV X5000 X-ray system from delivery conveyance into location within BLDG 2167;

1.1.2.1 The government will be the liaison to coordinate the moves.

1.1.2.2 Current target delivery date of new x-ray system is 28 SEP 2023.

1.1.2.3 The equipment will be delivered via a dedicated flat-bed, air-ride, Conestoga trailer. The system itself will be loaded directly onto the trailer, with two supporting crates.

1.1.2.4 Appendix A is the x-ray vendor’s customer installation guide.

1.1.3 BLDG 165 X-ray system disassembly and move from BLDG 165 to BLDG 3679 DRMO (approx. 6 miles).

1.2 Each piece of equipment weighs approximately 30,000 lbs.

2. REQUIRMENTS AND TASKS

2.1 REQUIREMENTS

2.1.1The rigging contractor must have functional knowledge of rigging equipment that weighs approximately 30,000 lbs.
2.1.2The rigging contractor must have proven experience moving heavy machinery.

2.1.3 Contractor must be able to provide the equipment, materials, and personnel to successful execute the task(s).

2.2 SPECIFIC TASKS

The rigging contractor shall provide the following general services:

2.2.1 Packing & Crating of machinery parts after disassembly by contractor.

2.2.2 Packing and crating materials.

2.2.3 Rigging the equipment for the moves.

2.2.4 Moving the machines and their accessory parts/pieces out of/ into B2167.

2.2.5 Uncrating of machinery parts (if necessary).

2.2.6 All work needs to be completed in accordance with applicable OSHA standards.

Crane Army Ammunition Activity shall provide the following General Services/Materials:

2.2.7 CAAA maintenance will disconnect power install all necessary power/utilities from the machines prior to the moving date so that the machines can be successfully moved/ installed by the contractor.

2.2.8 CAAA personnel will be the liaison coordination of the moves.

2.3 DOCUMENTATION

The rigging contractor shall provide the following documentation:

2.3.1 Insurance/bonding documentation. The X-Ray equipment is worth $1.5M each.

2.3.2 Receipt stating that the old equipment was physically moved from BLDG 2167 and BLDG 165 to BLDG 3679 DRMO signed by CAAA Technical POC.

2.3.3 Receipt stating that the new equipment was physically moved into BLDG 2167 and assembled signed by CAAA Technical POC.

3.0 PLACE OF PERFORMANCE

Work shall be performed at the following locations:

Crane Army Ammunition Activity Building 2167, Building 165, and DRMO 300 Highway 361 Crane, IN 47522-5001

4.0 FACILITY ACCESS

4.1 The contractor will be granted access to the physical location(s) identified in section 3.0. The Contractor shall access the installation through the Visitors Center and the Crane Gate. The CAAA COR or other NDT personnel will escort contractor to the buildings where these machines are located. Contractor will provide transportation for personnel and equipment required to perform service.

4.2 Access shall be limited to the hours of 6:30 a.m. to 4:30 p.m. EST Monday-Thursday (excluding federal holidays) and Friday if requested in advance.

5.0DELIVERY SCHEDULE
Deliverable
Deliverable due date
Bonding/Insurance information
ETA 28 SEP 2023
Disassemble machines
Same- Date and Work Coord. W/ POC
Move machines
Same- Date and Work Coord. W/POC
Assembly of machine
Same- Date and Work Coord. W/POC

6.0 NOTICE REGARDING LATE DELIVERY

The Rigging Services are required and contingent on delivery of Equipment on/about 28SEP.

Therefore, Services are required in order not to disrupt current delivery schedules affected.

7.0 QUALITY ASURANCE AND MONITORING OF WORK DELIVERABLES

5.1 All work under this contract shall be monitored by the CAAA Responsible Level III listed in section 10 below, who will act as the primary technical representatives for the government. Final inspection and acceptance of all work performed shall be performed at the place of re-assembly by the CAAA Technical POC. The CAAA Technical POC will communicate this information/acceptance to the Contracting Officer Representative (COR) via email.

8.0 PERSONNEL

8.1 Contractor is responsible for providing personnel with the necessary level of expertise to support the activities and requirements of this SOW. Contractor shall provide a single point of contact that shall serve as the project manager for the life of the contract. Contractor personnel are required to follow all OSHA regulations and the EM 385-1-1, Safety and Health Requirements Manual.

9.0 SECURITY CONSIDERATIONS

9.1 Access and general protection policy and procedures: Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (CFR clause 52.204-9, Personal Identity Verification of Contract Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

9.2 Contractor and all associated subcontractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (Army Directive 2014-05/AR 190-13); applicable installation, facility and area commander installation and facility access and local security policies and procedures (provided by Government representative); or, at OCONUS locations, in accordance with status-of-forces agreements and other theater regulations.

10.0 POINTS OF CONTACT

CAAA RL3 Technical POC Dustin Kern (812)-854-3067 dustin.m.kern.civ@army.mil Contracting Officer Representative (COR) Joseph Conner

(812) 854-1618 joseph.r.conner10.civ@army.mil

Contracting Office Rachel Eaggleston U.S. Army Contracting Command - Rock Island Installation Support Contracting Branch, CCRI-AIGC Rachel.J.Eaggleston.civ@army.mil

APPENDIX A: New NSI X5000 X-ray System Installation Guide

Installation shall be in accordance with F455B-Customer Installation Guide – X500 450 and X5000-2020 450kV SYSTEM.SLDDRW

F455B - Customer Installation Guide - X5000 450.pdf

North Star Imaging X5000 / 450kV

Installation Guide

2 North Star Imaging

F455B – X5000 / 450kV Installation Guide 3

Contents Requirements for the operation of an X-ray System

Safety

Shipping

Equipment Considerations

Packaging

Domestic X5000 / 450kV

Domestic X5000 450kV Modular

Domestic X5000 450kV Modular - Continued

International X5000 / 450kV

Standard Cabinet In-Plant Transport

Foundation and Floor Load

Standard System Leveling Feet

Seismic System Leveling Feet

Uncrating Materials

Standard Cabinet

Modular Cabinet

Modular Installation Tooling and Equipment

Modular Installation Process

Electrical Requirements

Workstation Requirements

Environmental conditions for operation

System Heat Load

Support

4 North Star Imaging

North Star Imaging manufactures turn-key industrial 2D & 3D Digital Radiography & Computed Tomography X-ray equipment which is used for R&D, Failure Analysis, Quality Control, Internal Measurements, High-Speed 3D Scanning, 3D Metrology & more. X-ray scanning allows users to inspect the external & internal structures of a part without destroying it.

NSI also offers as-needed X-ray Inspection Services at 6 global sites in Minnesota, California, Massachusetts, Florida, UK, and China and, 24/7 Technical Service and Basic & Advanced NDT classroom and online trainings all year round.

NSI is certified for ISO 9001:2015 QMS and ISO 14001:2015 EMS. Learn more: www.4nsi.com

F455B – X5000 / 450kV Installation Guide 5

Requirements for the operation of an X-ray System NSI cabinet systems are manufactured in accordance with 21 CFR 1020.40 which regulates the certification and requirements of cabinet X-ray systems. NSI system shielding is based on proven designs with more than 30 years of field experience. We inspect 100% of the products we produce to ensure the requirements of 21 CFR 1020.40 are achieved. The federal regulation states maximum radiation leakage allowed is 0.5mr/hr. at 5 cm from the surface of the cabinet.

The certification of the system is represented in the tag that is affixed to the radiation enclosure as indicated in the federal regulation. The language in the federal regulation regarding certification is as follows:

“The certification shall be in the form of a label or tag permanently affixed to, or inscribed on such product, so as to be legible and readily accessible to view when the product is fully assembled for use, unless the applicable standard prescribes some other manner of certification. All such labels or tags shall be in the English language.”

Typically, an X-ray system must be registered with the appropriate state agency. This registration must occur prior to the X-ray system being placed into service. Regulations may require initial and periodic inspections by a government agency or a qualified vendor. In addition, the regulations may require the implementation of standardized operating procedures, specialized training, and posting of radiation exposure warnings and other special notices.

Radiation safety requirements differ significantly from one jurisdiction to another. It is the users' responsibility to ensure the X-ray system is installed and operated in compliance with all applicable governmental regulations. Failure to comply may result in substantial penalties.

Safety The unloading and transport of NSI systems shall be completed by personnel trained and authorized to safely operate the equipment being used. Lifting equipment must be designed to accommodate the size and weight of the transported material. All equipment must be in proper working order and checked in accordance with the applicable standards and directives. NSI is not responsible for damage caused during the offloading or handling of equipment.

Shipping NSI X-ray systems are delivered on dedicated, flat-bed, air-ride, Conestoga style trailers.

Equipment Considerations System weight and lifting height must be used to properly determine the weight capacity requirements of the equipment being used to remove material from the trailer.

6 North Star Imaging

Packaging NSI systems are packaged and delivered in accordance with internal requirements.

Standard domestic shipments are packaged in the following manner:

NSI radiation enclosures are wrapped in polyethylene sheeting to provide some protection from the elements. Shipping channels are affixed to the roof of the enclosure to provide strapping locations for transport. Additionally, 4 swivel hoist rings are provided on the base of the cabinet to provide locations to secure the load.

Two additional wooden crates contain the various system components required. These components are wrapped in VCI poly sheeting to provide moisture protection. The crates are then sealed with a low-density polyethylene material to provide additional moisture resistance and protection.

Upon delivery, the radiation enclosure and system crates should be stored in closed, dry rooms with temperatures between 40 and 104°F (5 to 40°C).

Domestic X5000 / 450kV

Contents Packaging Length Width Height Gross Weight

Radiation Enclosure Pallet 118” 80” 98” 30,500 lbs.

Desk Crate 91” 72” 73” 2,000 lbs.

X-Ray Crate 91” 72” 59” 2,500 lbs.

Actual sizes and weights may vary.

F455B – X5000 / 450kV Installation Guide 7

Modular domestic shipments are packaged in the following manner:

The cabinet radiation enclosure panels are placed and secured onto wooden skids then wrapped in polyethylene sheeting to provide some protection from the elements.

Nine additional wooden crates contain the various system components required. These components are wrapped in VCI poly sheeting to provide moisture protection. The crates are then sealed with a low-density polyethylene material to provide additional moisture resistance and protection.

Upon delivery, the system crates should be stored in closed, dry rooms with temperatures between 40 and 104°F (5 to 40°C).

Domestic X5000 450kV Modular

Desk Crate 91” 72” 73” 2,000 lbs.

X-Ray Crate 91” 72” 74” 2,500 lbs.

Electrical Panel Crate 83” 70” 29” 1,200 lbs.

Electrical Cabinet

Crate 93” 38” 31” 1,500 lbs.

Exterior Skins Crate 96” 60” 29” 1,500 lbs.

Manipulator Base

Crate 141” 68” 43” 2,500 lbs.

Tower

Crate 113” 68” 43” 1,500 lbs.

Tower

Crate 115” 68” 43” 1,500 lbs.

Door Rail / Misc. Crate 109” 31” 28” 1,000 lbs.

Walls Skid 96” 38” 31” 3,000 lbs.

Walls Skid 96” 38” 31” 3,250 lbs.

Walls Skid 96” 38” 31” 4,000 lbs.

Walls Skid 96” 38” 31” 4,250 lbs.

Actual crate quantity, sizes, and weights may vary.

8 North Star Imaging

Domestic X5000 450kV Modular - Continued

Walls Skid 96” 38” 31” 5,250 lbs.

Corners Skid 93” 38” 31” 3,000 lbs.

Door Skid 99” 41” 30” 1,500 lbs.

Roof Skid 96” 44” 22” 4,000 lbs.

Base Skid 96” 44” 25” 3,500 lbs.

International shipments are packaged in the following manner:

NSI radiation enclosures are wrapped in aluminum coated foil, packaged with desiccant, and sealed to provide moisture protection. Shipping channels are affixed to the roof of the enclosure to provide strapping locations for transport. The sealed radiation enclosure is packaged in a wooden shipping crate in conformance with IPPC/ISPM 15 standards. The crate is sealed with a reinforced low-density polyethylene material to provide additional moisture resistance and protection.

Two additional wooden crates contain the various system components required. These components are wrapped in aluminum coated foil, packaged with desiccant, and sealed to provide moisture protection. The crates are then sealed with a reinforced low-density polyethylene material to provide additional moisture resistance and protection.

Upon delivery, the radiation enclosure and system crates should be stored in closed, dry rooms with temperatures between 40 and 104°F (5 to 40°C).

International X5000 / 450kV

Contents Packaging Length Width Height Net Weight Gross Weight

Radiation Enclosure Crate 144” 94” 119” 30,000 lbs. 33,500 lbs.

Desk Crate 91” 72” 73” 1,500 lbs. 2,000 lbs.

X-Ray Crate 91” 72” 59” 2,000 lbs. 2,500 lbs.

Actual sizes and weights may vary.

F455B – X5000 / 450kV Installation Guide 9

Standard Cabinet In-Plant Transport Sufficient floor and ceiling load capacity of the transport routes must be verified prior to moving material. Transport routes must be designed to accommodate the weight of the transported material and transportation equipment.

NSI systems are designed to be lifted only from the base of the enclosure, any other lifting methods may cause damage. NSI is not responsible for damage caused during the offloading or handling of equipment. See Figures 1 and 2 for lifting instructions.

Following movement of the radiation enclosure to the final location, the system’s leveling feet must be installed prior to placement on the ground. The six leveling feet must be installed as shown in Figure 3. Leveling of the cabinet should be completed by the customer during radiation enclosure placement. A contractor grade construction level, 2ft - 4ft in length, should be used in the X (front to back) and Z (left to right) planes to ensure the system is level. Ensure that all mounting feet are in contact with the floor and equal pressure has been applied to each foot.

For systems requiring seismic isolation feet, installation of the concrete anchors must be completed by the customer, see Fig. 4 for details. To determine layout requirements, see provided system specification drawings.

Figure 1 – Lifting should only be completed by areas marked in red.

10 North Star Imaging

Figure 2 – Lifting should only be completed by areas marked in red.

Figure 3 – Distance from base of leveling foot (red) to base of cabinet (green) should be approximately 4”.

F455B – X5000 / 450kV Installation Guide 11

Figure 4 – Orientation of Seismic Feet as shown is required. Anchors may be installed after cabinet is placed in final location.

Foundation and Floor Load The specified surface pressure indicates the maximum load applied to the floor covering. This value must not be used to calculate the permissible floor or ceiling load. The load conditions at the installation sites vary individually and must be clarified and/or calculated by a structural engineer before installation of the NSI system.

Standard System Leveling Feet Mean surface pressure on the 8 support surfaces is approximately 300 PSI, determined from the NSI system weight distributed over the 8 support surfaces.

Seismic System Leveling Feet Mean surface pressure on the 8 support surfaces is approximately 30 PSI, determined from the NSI system weight distributed over the 8 support surfaces. For specific installation instructions, see provided seismic feet drawings.

12 North Star Imaging

Uncrating Materials Standard Cabinet Supporting material crates may be unpackaged, and materials moved to the installation site by the customer. Care should be taken to ensure damage does not occur. Any damage incurred must be immediately communicated to your NSI Project Manager. Disposal of packaging materials and crating is the customer’s responsibility.

Modular Cabinet NSI will uncrate all materials for the installation of the system. Disposal of packaging materials and crating is the customer’s responsibility. Appropriate means of refuse disposal must be supplied while NSI is onsite for installation. Wooden skids and crates contain metal hardware (i.e. lag bolts, metal banding, staples) and may not be accepted by all recycling services.

Modular Installation Tooling and Equipment NSI typically supplies tooling and equipment necessary for the installation of the X5000 modular system. Installation tooling and equipment will be shipped to the site at the commencement of the installation process. Upon installation completion, all NSI equipment and tooling will be shipped back to NSI – Rogers on a dedicated, flat-bed, air-ride, Conestoga style trailer.

Installation Tooling and Equipment

Crate Description Packaging Length Width Height Gross Weight

Rigging Box Skid 55” 36” 51” 900 lbs.

StorageMaster Skid 81” 38” 60” 1,050 lbs.

Tool Chest Crate 77” 42” 83” 1,650 lbs.

Cart and Boom Skid 103” 48” 51” 3,600 lbs.

A-Frame Crate 149” 41” 41” 1,500 lbs.

A-Frame Attachments Crate 144” 39” 41” 1,350 lbs.

Additional equipment necessary for the installation includes a 6,000 lbs. capacity warehouse-style forklift with a minimum of 6’ forks. NSI will need access to the forklift throughout the duration of the installation week. Our entire installation team is forklift certified through a 3rd party agency and can provide proof of certification upon request.

F455B – X5000 / 450kV Installation Guide 13

Modular Installation Process Upon arrival at the site our trained technicians will begin the installation process. A sizeable offload and staging area are required for staging and removal of each component from the transport trucks. Our team requires a free and clear path to the installation location from the staging area. Each component of the assembly will be transported to the final location with the use of a heavy-duty moving cart, as required. Our installation technicians will utilize an A-frame style gantry crane to assemble the cabinet and manipulator in the final location.

The cabinet and manipulator assembly will typically be completed in two days onsite; at which point the electrical provisions will be required, reference “Electrical Requirements” on page 13 for more information.

Electrical Requirements Category Value Line Voltage 230 VAC (L1/N/G) or 240 VAC (L1/L2/G) Frequency 50/60 Hz Current Type Single Phase – L1/N/Ground or L1/L2/Ground Required Fuse 60 Amps Total Amps (FLA) 48 Amps

Due to high leakage current created by operation of the X-ray source, an additional 6 AWG dedicated ground (to structural steel or earth ground) must be supplied to the high voltage generator.

The 60 Amp disconnect shall be placed within 15 feet of the system main electrical cabinet. The power cable/wire will be supplied by and landed in the main electrical cabinet by the customer.

Rigid conduit may also be attached to the cabinet for routing of power and ground wires.

Electrical work shall be performed by a qualified electrician in accordance with state and local code. NSI is not responsible for damage caused by improper wiring.

Continuous power is essential for quality data processing. Other systems with permanent high-power consumption and systems with peak loads should not be connected to the same electrical circuit as the NSI X-ray system. This avoids malfunctions on the NSI X-ray system.

Workstation Requirements NSI provides provisions for power to the acquisition PC to be placed at the supplied ergo desk.

Additional PCs (reconstruction, review, data storage devices, etc.) shall be placed at a location provided by the customer with the required power provisions available.

Additionally, it is the customer’s responsibility to provide means of data transfer between NSI system PCs. This can be accomplished through interfacing with an existing network or direct connection between PCs. NSI system components are networked during start-up by an NSI installation technician in accordance with the applicable specifications and must not be modified by the customer. Any change may lead to connection problems.

An internet connection is not required for NSI system use but is beneficial where available.

14 North Star Imaging

Environmental conditions for operation The following conditions must be met to ensure proper operation of the NSI X-ray system.

Permissible environmental temperature 50-95°F (10-35°C) Permissible humidity (without condensation) 40-70%

System Heat Load

Configuration Total Watts Total BTU/HR 450kV source with DDA 1170 3,990 225kV and 450kV source with DDA 1370 4,675 225kV and 450kV source with DDA and LDA 1380 4,710

Actual output depends on system usage.

Support For additional information, contact your NSI Project Manager.

F455B – X5000 / 450kV Installation Guide 15

Revision History

Revision Effective Date Description of Changes

A 1/10/2022 Initial release – Mike Vojacek author

B 4/13/2023 Renamed document, added modular crating and installation information, revised electrical requirements -Nate Coffin image2.emf

X5000-2020 450kV SYSTEM.SLDDRW.pdf

DOOR

OPENING

DOOR

OPENING

B

POWER REQUIREMENTS 230/240 VAC,

60 AMP, SINGLE PHASE, 50/60Hz DISCONNECT W/IN 15 FEET [4.5 m]

DEDICATED GROUND ROD OR

EQUIVALENT

SERVICE

AREA

REQUIRED

EXAMPLE PLACEMENT ONLY -

ACTUAL PLACEMENT DEPENDENT

ONLY ON CABLE LENGTH NOTED.

CABLE ENTRY POINT

CABLE LENGTH:

10 METERS

FROM ENTRY

POINT

TOUCH SCREEN

EMERGENCY STOP

ERGO CHAIR

MODELS CAN VARY

SEE QUOTATION FOR

OPTIONS ON MONITORS/ERGO

DESK AND ERGO CHAIR

X5500 SHOWN2

NOTE:

NOTED ITEMS MAY NOT BE REQUIRED - (SHOWN IS A DUAL SOURCE SYSTEM)1.

X5500 SYSTEM INCLUDES: ELECTRICAL CABINET (60x13 in) REQUIRING 60x36 in 2.

SERVICE AREA, HMI, 450 I/O BOX, ONE ACCESS DOOR MOTION SAFETY

SWITCH, PREWARN MODULE ~ 3 M (10 FT.) FROM MANIPULATOR; CABLE

LENGTH FROM MANIPULATOR TO ELECTRICAL CABINET ~ 6 FT. [1.83 m]

CABLE LENGTHS APPROX 5 METERS FROM ENTRANCE POINT3.

DIMENSIONS FOR LAYOUT ARE APPROXIMATE ONLY SHOWN IS A MINIMUM 4.

"SPACE LAYOUT"

DIMENSIONS SHOWN WITH [ ] ARE IN MILLIMETERS5.

WEIGHT OF CABINET WITH MANIPULATOR:

APPROX 27500 - 30200 lb (12500-13700 kg.)

WEIGHT OF MANIPULATOR:

APPROX 3000 - 4200 lb (1360 - 1900 kg.)

REVISIONS

REV. DESCRIPTION DATE ENG

A ECO# 162085, INITIAL RELEASE 06-15-2020 GMT

B ECO# 162222, INITIAL RELEASE 08-31-2021 GMT

X5000 450kV SYSTEM- SPECIFICATIONS

THE INFORMATION CONTAINED HEREIN IS

PROPREITARY TO NORTH STAR IMAGING, INC.

AND SHALL NOT BE REPRODUCED OR

DISCLOSED IN WHOLE OR IN PART, NOR USED

FOR ANY DESIGN OR MANUFACTURING

PURPOSES UNLESS AUTHORIZED IN WRITING

BY NORTH STAR IMAGING, INC.

(763) 463-5650

(800) 635-8392

(763) 463-5651

SURFACE ROUGHNESS

UNLESS OTHERWISE

SPECIFIED REMOVE ALL

BURRS AND BREAK SHARP

EDGES .02 MAX.

ALL DIMENSIONING AND

TOLERANCING IN

ACCORDANCE WITH LATEST

ANSI Y14.5 STANDARD

ANGULAR ±1°

.X ±.020 .XXX ± .005

.XX ± .010 .XXXX ± .0005

TOLERANCES

ALL DIMENSIONS ARE IN INCHES

UNLESS OTHERWISE SPECIFIED

05-20-2020

MATERIAL:

FINISH:

Material <not specified>

DESIGNER:

N. Wilson

DO NOT SCALE DRAWING

THIRD ANGLE

PROJECTION

DATE:

PROPRIETARY AND CONFIDENTIAL

DECIMAL

SCALE: 1:36

SIZE DWG. NO.

REV.

SHEET 1 OF 3WEIGHT:

TITLE

19875 S. DIAMOND LAKE ROAD

ROGERS, MINNESOTA 55374

PHONE:

TOLL FREE:

FAX:

WWW.4NSI.COM

X5000-2020 450kV SYSTEM 33386.22220

MAX. VIRTUAL

DETECTOR WIDTH

MAX. VIRTUAL

DETECTOR HEIGHT

DEFINITION OF COORDINATE AXES

TURNTABLE (9 INCH [228] SHOWN)

CONTINUOUS ROTATION

X AXIS

Z AXIS

Y AXIS

93.9

+20°

-20°

MAX. TURNTABLE TRAVEL

MAX. FOCAL DISTANCE

11.8

INTERNAL

TABLE

TRAVEL

23.4

TURNTABLE TRAVEL

EXTENDS TO DOORWAY

FOR PART LOADING

NOTES:

MAXIMUM TURNTABLE TRAVEL DISTANCES ARE WITH THE 1.

TURNTABLE BELOW THE X-RAY SOURCE AND DETECTOR.

ALL TRAVEL DISTANCES DEPEND ON CONFIGURATION 2.

OF SOURCE AND DETECTOR. SEE "X5000 SCANNING

ENVELOPE" FOR DETAILS.

05-20-2020

SCALE: 1:20

SHEET 2 OF 3WEIGHT:

PHONE:

TOLL FREE:

MIN

MINO

PT

IO

N

A

OPTION B

O

PT

IO

N

C

NOTES:

CEILING HEIGHT MINIMUM = 108 IN1

DOOR WIDTH MINIMUM = 30 INCHES 2.

(MUST BE LOCATED IN ONE OF THE

LOCATIONS SHOWN: OPTIONS A, B, C)

ELEVATOR OR PASSAGE WAY MUST FIT 3.

RIGGING BEAM = 12 FT X 4 IN X 4 IN

MINIMUM MODULAR SPACE REQUIREMENTS

06-12-2020

SCALE: 1:20

SHEET 3 OF 3WEIGHT:

PHONE:

TOLL FREE:

Sheet1

Drawing View2

Drawing View3

Drawing View6

Drawing View12

Sheet2

Drawing View7

Drawing View8

Drawing View9

Sheet3

Drawing View10

Drawing View11 image1.emf