Solicitation Amendment - W50SLF25RA0070001.pdf
PDF 3 MB Posted
- Attached to
- Replace AC Systems, Bldg 501, Maui, HI Federal contract opportunity
- Solicitation number
- W50SLF25RA007
- Issued by
- Department of the Army National Guard
About this file
This is a Request for Proposal (RFP) for the Hawaii Air National Guard, 292nd Combat Communication Squadron (292nd CBCS) to replace AC systems in Building 501 at 75 Kuleana St, Kahului, Maui, Hawaii. The contract is a 100% small business set-aside with a Firm Fixed Price (FFP) arrangement, with a total contract value of USD 19,000,000 and a period of performance of 365 calendar days from the Notice to Proceed.
The project specifically requires removing one existing Carrier Air-Cooled Liquid Chiller serving Building 501 and replacing it with a new 40 Nominal Ton Air-Cooled Chiller, along with replacing two existing close-coupled centrifugal chilled water pump systems. The solicitation includes detailed requirements for technical capabilities, past performance documentation, and pricing submissions. The offer is due on 11 September 2025 at 3:30 PM, with the solicitation issued on 22 August 2025. Wage determinations under the Service Contract Act and Davis-Bacon Act are incorporated, and contractors must comply with various federal regulations and provide comprehensive documentation including product specifications, scheduling methodology, and past project references.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATCH 1. Revised SOW_KABD250001 Replace AC Systems B501 v 3.pdf | ||
| Solicitation Amendment W50SLF25RA0070001 SF 30.pdf | ||
| ATCH 1. Revsied SOW_KABD250001 Replace AC Systems B501 v 3.docx | DOCX document | |
| ATCH 7. Question-Answer_Replace AC Systems B501, Maui HI.docx | DOCX document | |
| ATCH 2. Chiller Specs.pdf | ||
| ATCH 3. Reference Drawings.pdf | ||
| Solicitation - W50SLF25RA007.pdf | ||
| ATCH 1. SOW_KABD250001 Replace AC Systems, B501 v 2.docx | DOCX document | |
| ATCH 4. DETAILED PRICE PROPOSAL OFFER SPREADSHEET.docx | DOCX document | |
| ATCH 6. WD HI20250001, Modification No. 10.pdf | ||
| ATCH 5. Service Contract Act WD # 2015-5739 Rev No. 25.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WOMEN-OWNED SMALL
BUSINESS (WOSB)
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NUMBER 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NUMBER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
REQUEST
FOR QUOTE
(RFQ)
INVITATION
FOR BID
(IFB)
REQUEST
FOR
PROPOSAL
(RFP)
SEE ADDENDUM
19.
ITEM NUMBER
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH
AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND
ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS
SPECIFIED
29. AWARD OF CONTRACT: REFERENCE OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NORTH AMERICAN
INDUSTRY CLASSIFICATION
STANDARD (NAICS):
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
THE DEFENSE PRIORITIES
AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FREE ON
BOARD (FOB) DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3
AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8(A)
ECONOMICALLY
DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.
calls)
Solicitation/Contract Form Continuation
REPLACE AC SYSTEMS, B501, MAUI HI
SOLICITATION CONTRACT FORM
TABLE OF CONTENTS
SECTION - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
SECTION - GENERAL REQUIREMENTS
ATTACHMENT 1 - STATEMENT OF WORK, dated 3 Sep 2025
ATTACHMENT 2 - CHILLER SPECS
ATTACHMENT 3 - REFERENCE DRAWINGS
ATTACHMENT 4 - DETAILED PRICE PROPOSAL OFFER SPREADHEET
ATTACHMENT 5 - Service Contract Act (SCA) Wage Determination, 2015-5739 Rev # 25
ATTACHMENT 6 - Davis-Bacon Act (DBA) Wage Determination, HI20250001 Mod # 10
ATTACHMENT 7 - QUESTIONS AND ANSWERS, dated 3 Sep 2025
NOTES
1. Instructions for the preparation of proposals are located in Section INSTRUCTION, CONDITIONS, AND NOTICE TO OFFERORS.
2. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.
3. Offeror's attention is invited to the insurance requirement contained in this solicitation (FAR Clause 52.228-5 Insurance - Work on a Government Installation). Certification of the required coverage for the prime contractor shall be furnished prior to beginning work on this contract, and the Contracting Officer may request evidence of the required insurance at any time during the life the contract.
4. Reference DFARS Provision 252.236-7008, Contract Prices - Bidding Schedules. The term "Bidding Schedule" shall also be construed to mean "Offer Schedule" or "Schedule". The terms "bid" and "offer", and "bidder" and "offeror" shall be construed as having the same meaning in this solicitation and resulting contract.
SECTION - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
1. SCOPE
1.1. You are invited to submit a proposal in response to our Request for Proposal (RFP) W50SLF-25-R-A007, PROJECT KABD 250001 Replace AC Systems B501 of the Hawaii Air National Guard, 292 Combat Communications Squadron (292nd CBCS), 75 Kuleana St, Kahului, HI 96732. As a result of this solicitation, the Government intends to award a single Firm Fixed Price (FFP) contract.
1.2. This solicitation is set-aside100% for Small Business.
2. STATEMENT OF WORK
2.1. Statement of Work (SOW) for this solicitation is incorporated as an attachment.
3. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS AND AMENDMENTS PRIOR TO DATE SET FOR RECEIPT OF PROPOSALS
3.1. Submit all questions in the format shown below by email to the contracting office at the addresses shown below. Do NOT contact A-E or Engineering personnel directly. Doing so will only delay your answer. All questions must come through the Contracting Office.
Subject Line: Reference No. Solicitation W50SLF-25-R-A007
Email: cezar.y.deveas.mil@army.mil
PRE-PROPOSAL INQUIRY FORMAT
Date of Inquiry: _______________
W50SLF25RA0070001
From: _________________________ Company Name:___________________________
Address: ______________________________________________________________
Phone Number: _________________ Fax Number: ______________________________
Email address: _________________________________________________________
Inquiry: (Please clearly state your question) (If sent via an attachment word docs are preferred to facilitate posting of answers to the master Q&A document.)
3.2. Any explanation desired by offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offeror before the submission of their offer.
3.3. Any changes to the solicitation and SOW will be issued in the form of an amendment. However, any answers that clarify or provide an interpretation will NOT be posted via amendment but rather as a response to the RFI.
3.3.1. Receipt by the offeror must be acknowledged in the space provided on the SF 1449 or by returning a signed copy of the amendment by the time set for receipt of proposals. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding.
3.4. The right is reserved, as the interest of the Government may require, to revise or amend, the specifications or drawings or both prior to and/or after the date set for receipt of proposals as necessary. Such amendments, if any, will be announced by an amendment or amendments to this Request for Proposal. All information relating to this RFP, including pertinent changes/amendments and information prior to the date set for receipt of proposals will be provided via e-mail.
4. WAGE DETERMINATION
4.1. Service Contract Wage Rates are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are 2015- 5739, Rev. No. 25, DATE 07/08/2025
4.2. Davis Bacon Wage Rates are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are HI20250001, Modification No. 10, DATE 08/08/2025
4.3. Applicable wage rates be found at: www.SAM.gov. In the event the current prevailing Wage Determination is changed by the Department of Labor prior to the closing date of this solicitation, it is the offeror's responsibility to insure the most recent determination is used in preparing the proposal. An Amendment will not be issued prior to closing to change Wage Determination dates and/or numbers. Should the wage rate change after closing, but prior to award, the updated Wage Determination will be incorporated by amendment and issued to all offerors. If applicable, offeror will be given a reasonable opportunity to provide revised proposals solely to amend proposals due to Wage Determination changes. If the wage determination modification does not change any affected wage rates, then the provisions of FAR 22.404-5(c)(4) will apply.
5. PROPOSAL SUBMISSION REQUIREMENTS:
5.1. Offeror shall provide all price/cost information necessary to provide a meaningful basis for Government's analysis and evaluation of price/cost for the project. Provide an introductory page to include CAGE Code, DUNS Number, Tax Identification Number (TIN), points of contact, authorized negotiators, contact phone, facsimile numbers, and email addresses.
5.2. Complete in its entirety the "Offeror" portion of the Standard Form (SF) 1449. An official having the authority to contractually bind your company must sign the SF 1449 in accordance with FAR 4.102. One copy of the SF 1449 is required to have an original signature. Insert the price /cost associated with the project in the line items. All line items (CLINs) must be priced.
5.3. Offeror Representations and Certifications - Commercial Products and Commercial Services- insert the required certifications and representations and return the entire Section with your proposal. All other required representations and certifications are to be completed on line in the System for Award Management (SAM) at https://www.sam.gov/portal/public/SAM/.
5.4. SUBMISSION OF TECHNICAL CAPABILITY OF THE ITEM(S) TO MEET THE GOVERNMENT REQUIREMENTS.
(a) The offeror shall provide product specifications for the proposed 40 Nominal Ton Air-Cooled Chiller and Chilled Water Pumps, and warranty information.
(b) Scheduling Methodology: Provide a schedule in a Gantt chart that shows the complete project schedule from Notice to Proceed date of 30 September 2025 (estimated), to include all activities as well as concurrent activities, and outline the critical path activities that will show successful execution of the project within the period of performance requirements outlined in the SOW. Also include a narrative discussing the scheduling processes, resource allocation, list of potential impacts and corrective actions to ensure completion and control of schedule progress from beginning to the end of the project.
(c) Provide a brief outline of resources, subcontractors, and key personnel that would be used to accomplish the contract.
5.5. SUBMISSION OF PAST PERFORMANCE
The offeror shall provide a listing of projects completed within the last three (3) years completed for both Federal, State, Local and private commercial industry clients; Include the following information for each project listed: the type of project, the total dollar value, the contract number, the location of performance, and the point of contact for owner/client, and if the construction on an island environment or similar location with remote logistic concerns and if the construction required tying into an existing facility without interruption to operations. Indicate if your firm was a prime or subcontractor during performance of the listed project, and if your firm was a subcontractor provide the name and point of contact information for the prime contract holder.
6. SUBMISSION REQUIREMENTS FOR PRICING DATA
Price should be provided on the Standard Form (SF) 1449. All amounts shall be rounded to the nearest hundredth decimal place. The offeror shall submit a detailed price proposal on the detailed offer spreadsheet provided. The Government intends to evaluate proposals and award without discussions; therefore proposals should be the Contractor's best pricing.
7. Reserved
8. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS
This RFP does not commit the Government to pay costs incurred in preparation and submission of initial and subsequent proposals or for other costs incurred prior to award of a formal contract.
9. Reserved
10. DISPOSITION OF UNSUCCESSFUL PROPOSALS
In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals. The Government will destroy extra copies of unsuccessful proposals. No destruction certificate will be provided.
11. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES
It has been determined that all temporary utilities shall be the responsibility of the contractor. The contractor will pay all charges (hook up fees, metering, monthly usage, etc.) resulting from temporary utilities. The offerors shall take this into consideration when computing their offers. (FAR Clause 52.236-14, Availability and Use of Utility Services.)
Water Utility. This utility is available for the contractor to tie-in to. For this, the Contractor is to install a backflow preventer with meter from the fire hydrant. The meter will determine water usage that the Govt will invoice the contractor for. For planning/budgeting purposes, the charge rate is $8.72
/KGAL.
Electricity Utility. This utility is available for the contractor to tie-in to. For this, the Contractor is to plan for outage, plan for tie-install, and subsequent removal. The tie-in is to be equipped with a meter. The meter will determine electrical usage that the Govt will invoice the contractor for.
For planning/budgeting purposes, the charge rate is $96.846/MWH.
Sewer Utility. This utility is not available. Contractor to provide for the sewage.
12. Reserved
13. EXCEPTIONS
If the offeror takes exception to any of the requirements specified in this solicitation, the offeror shall clearly identify each such exception and include a complete explanation of why the exception was taken and what benefit accrues to the Government. All exceptions to the solicitation requirements and supporting rationale shall be included in an addendum to the proposal and clearly labeled "Exceptions". An addendum is only required if the offeror takes exception to any requirement in the solicitation. (The Addendum does not have a page limitation, but shall only include information relevant to exceptions taken to the solicitation requirements.) The Government will assume an offeror takes no exceptions to any solicitation requirement if the offeror does not submit an Addendum identifying exceptions. Offeror is advised that solicitation requirements are not necessarily negotiable and such exceptions may render an offeror's proposal unacceptable and ineligible for award.
14. CLAUSES
14.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.
14.2. Clauses and provisions in this document may not appear in consecutive order.
15. BRAND NAME REQUIREMENTS
15.1. There is no Brand Name or Sole Source Justification associated with this project.
16. NATIONAL GUARD PROTEST PROCEDURES
16.1. NG Agency Protest Program is intended to encourage interested parties to seek resolution of their concerns with the National Guard (NG) as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office (GAO) or other external forum.
Contract award or performance is suspended during the protest to the same extent, and within the same time periods as if filed at the GAO. The NG protest decision goal is to resolve protests within 35 calendar days from filing. An agency protest may be filed with either the Contracting Officer or the NG Agency's Protest Decision Authority, but not both, in accordance with NG protest procedures.
To be timely, the protests must be filed with the periods specified in FAR 33.103. To file a protest under the NG Agency Protest Program, the protest must request resolution under that program and be sent to the address below:
National Guard Bureau
Office of the Director of Acquisitions/ Head of Contracting Activity
ATTN: NGB-AQ-O
111 S. George Mason Dr.
Arlington, VA 22204
All other agency-level protests should be sent to the Contracting Officer for resolution at the address in the solicitation. See FAR clause 52.233-2.
END OF SECTION - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
Continuation of Supplies or Services and Prices/Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
KABD250001 REPLACE AC SYSTEMS B501,
MAUI, HI
All work shall be completed as indicated on this SOW, the Contract drawings, and in accordance with specifications and codes.
Product Service Code: 4120 Pricing Arrangement: Firm Fixed Price
1 Job
Continuation of Description
SECTION - GENERAL REQUIREMENTS
1. INSURANCE - MINIMUM AMOUNTS
1.1. Reference Contract Clause titled, "Insurance -Work on a Government Installation (FAR 52.228-5). Kinds and minimum amounts are as follows:
KIND / AMOUNTS (FAR 28.307-2)
Workmen's Compensation / $100,000 (see paragraph 1.2, below)
Comprehensive General Liability / $500,000 per occurrence for bodily injury
Comprehensive Automobile Liability / $200,000 per person and $500,000 per accident for bodily injury and $20,000 for property damage
(If applicable) Aircraft Public and Passenger Liability / $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability and $200,000 per occurrence for property damage; coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats. $200,000 multiplied by the number of seats or passengers, whichever is greater.
1.2. Except in states with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
1.3. NOTE: Before commencing work under this contract, the Contractor shall certify to the Contracting Officer, in writing, that the required insurance has been obtained. The policies referenced in the certification (s) shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the state in which this contract is to be performed prescribe or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer. The Contractor shall maintain a copy of proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
2. ORDER OF PRECEDENCE (REFERENCE FAR 52.236-21)
Any inconsistency in this solicitation or contract will be resolved by giving precedence in the following order:
1) Representations and other instructions,
2) Contract clauses,
3) Other documents, to include special contract requirements, Statement of Work, exhibits, and attachments,
4) The specifications
5) The drawings
3. SCHEDULING
3.1. Normal base work hours for the Contractor will be between the hours of 7:00 AM through 4:30 PM, excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer's Representative (COR) five (5) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces. When the COR determines that they are reasonably available, he may authorize the Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount.
3.2. The following Federal legal Holidays are observed by this base:
New Year's Day, 1 January
Martin Luther King's Birthday, Third Monday of January
President's Day, Third Monday of February
Memorial Day, Last Monday of May
Juneteenth, 19 June
Independence Day, 4 July
Labor Day, First Monday in September
Columbus Day, Second Monday in October
Veteran's Day, 11 November
Thanksgiving Day, Fourth Thursday in November
Christmas Day, 25 December
3.3. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday; holidays falling on a Sunday will be observed on the following Monday.
3.4. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more), commencement of any warranty work, and upon completion of warranty work, the contractor must notify the Contracting Officer (or the Contracting Officer's Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting Officer's Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The purpose of the above precautions is to ensure inspection and recording of work proceedings.
3.5. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.
4. INVOICING AND PAYMENT
4.1. Properly prepared invoices, bearing the contract number, shall be submitted to the Contracting Office, via email to cezar.y.deveas.mil@army.mil and copy to clesson.k.paet.civ@army.mil, and copied to the COR on designated invoice forms provided at the pre-mobilzation meeting PRIOR to uploading in Wide Area Workflow (WAWF) the DFAS paying system. This submission will be for review prior to submitting an electronic invoice through Wide Area Workflow (WAWF). All payments will be made by electronic transfer of funds (EFT).
4.2. To meet compliance with DFARS 252.232-7003, Electronic Submission of Payment Requests, you shall submit your request for payment (invoice) through WAWF. For more information on the WAWF system, including how to register, visit https://wawf.eb.mil. Payment will be made by paying office specified in the contract award.
4.3. The Government will make payment through WAWF upon satisfactory completion of work AND receipt of a proper certification for payment.
Do not input invoice into WAWF until the pre-approval of invoice is received from the contracting officer. This will lessen the need for rejections in
WAWF.
4.4. A release of claims is required for all final payment requests and shall be submitted by the contractor with the final invoice.
5. CONTRACT ADMINISTRATION
5.1. The contracting office of the USPFO for Hawaii is the office having administrative jurisdiction over this contract for all matters. A list of the names and telephone numbers of the Government team comprising the contract administrator, Contracting Officer's Representative (COR), consultant, and point of contact at the project site will be provided at the post-award/pre-mobilization conference.
5.2. All correspondence shall be addressed to the Contracting Officer. A copy of all correspondence shall be furnished to the contracting officer's representative. Enclosures attached to or transmitted with the correspondence shall also be furnished with an original and one copy. Each letter shall make reference to the contract name, contract number, project number, and project title, and shall have only one subject. For tracking purposes, a sequential numbering system should be used for all correspondence.
6. PAPERLESS CONTRACTING
6.1. The National Guard is fully committed to the Federal Government's electronic commerce and paperless contracting initiatives. As such, it is anticipated that to the maximum extent possible to include but not limited to correspondence, modification distribution, etc., to include specifications and drawings, will be issued using electronic methods, i.e., electronic mail (e-mail). Contractors shall have and maintain capability to receive documents in this manner.
6.2. Additionally, it is anticipated that within the life of this contract, other electronic processes will be enacted. These include, but are not limited to, electronic bidding/offers, change order proposals, and electronic invoicing. When implemented by the Contracting Officer, contractors shall participate fully in any of these new requirements at no additional cost to the Government.
7. TELEPHONE COMMUNICATIONS SECURITY MONITORING
All communications with DOD organizations are subject to communications security (COMSEC) review. Contractor personnel must be aware that telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations.
Therefore, civilian contractor personnel are advised that any time they place a call to, or receive a call from, a DOD organization, they are subject to COMSEC procedures. The contractor shall assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with DOD information.
8. UTILITY SERVICES
The Contracting Officer has determined that Government-operated utilities are adequate and will be furnished to the contractor without charge where existing outlets are available. The contractor is responsible for installing temporary service outlets, as necessary, at its expense in accordance with the clause entitled "Availability and Use of Utility Services" (FAR Clause 52.236-14). The following utilities will be available: NONE
9. PREPARATION OF MATERIAL APPROVAL SUBMITTALS
The contractor shall submit all materials and articles requiring approval, as required by the Material and Workmanship Clause, FAR 52.236-5.
Submittals shall be made using AF Form 3000, or approved equal. Submittals shall be processed in accordance with the procedures in Section 01 33 00, Submittals. Submittals shall be given a distinct identification system by CLIN if multiple CLINS are applicable. Individual submittal documents shall not be comprised of items for more than one CLIN. Address for delivery of submittals will be provided at the post award/pre-mobilization conference. The contractor is reminded that an individual within the company who has authority to make the certification must sign the certification on the AF Form 3000.
10. WORK PROGRESS AND PREPARATION OF PROGRESS SCHEDULES AND REPORTS
10.1. A weekly meeting may be held with the Contractor, COR and Contracting Officer (KO), if necessary, to discuss work progress, problems and potential change orders. The Contractor shall attend these meetings at no additional cost to the Government. Prior to beginning work on specific work elements of a project, the contractor shall confer with the COR and agree on a sequence of procedures and means of access to premises and buildings;
space for storage of materials and equipment; delivery of materials; and use of approaches, use of corridors, stairways and similar means of passage.
10.1.1. The contractor shall within five days after work commences on the contract, or another period of time determined by the KO, prepare and submit to the KO for approval three copies of a practicable schedule showing the order in which the contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing features of work. A composite schedule for the overall contract shall also be provided. The schedule shall be on an AF Form 3064, Contract Progress Schedule, or an approved computer generated format similar to the AF Form 3064. The work shall be scheduled so that, upon the start of mobilization, work progresses in a continuous and diligent manner. A schedule which does not reflect steady and reasonable progress throughout the project period will be rejected. Both the Contractor and the COR are required to provide monthly progress reports covering the period from notice to proceed through final inspection. Unless agreement cannot be made on the applicable percentage of progress a joint report will be submitted to the Contracting Officer. This reports shall be submitted on the NGB Contract Progress Report form (similar to an AF Form 3065), or an approved computer generated similar format. These reports shall track progress by CLIN, if contract contains multiple CLINs, multiple AF Form 3064 and NG Contract Progress Reports will also be required for payment purposes.
10.2. Additionally, for projects exceeding $1M, the contractor shall provide a project plan in a commercially available network scheduling software that meets requirements of the specification to define work tasks and track progress. At least five days prior to work initiation, the contractor shall provide the Contracting Officer a hardcopy CPM and a formatted diskette or CD copy, or e-mail file copy, of the plan that shall include definition of rescues. No work may start until the Contracting Officer approves the plan in writing.
10.3. The Contractor shall prepare a work progress schedule required for completion of each of the various divisions of work. Updated plans and Form 3064 showing work progress (hardcopy and formatted diskette or CD, or e-mail file copy), unless otherwise directed by the Contracting Officer, shall be provided monthly. If there are possible deviations from the original plan, those must be noted and approved by the Contracting Officer before work changes are implemented. The schedule shall be submitted to the Contracting Officer, in the number of copies as directed.
11. NOTICE OF COMPLETION OF WORK/PRE-FINAL AND FINAL INSPECTION
11.1. The contractor shall conduct a pre-final inspection in the presence of the Contracting Officer's Representative (COR) prior to the date scheduled for Final Inspection. Any discrepancies noted shall be corrected prior to Final Inspection.
11.2. The contractor shall request scheduling of a final inspection in writing to the Contracting Officer at least ten (10) working days prior to the desired date or as otherwise negotiated with the Contracting Officer.
11.3. Civil Engineering personnel and the Contracting Officer will perform the Final Inspection in the presence of the contractor, and any discrepancies noted shall be corrected within the time specified by the Contracting Officer.
11.4. Final Inspection shall not constitute acceptance of a project unless so stipulated by issuance of a separate acceptance notice.
11.5. The contractor is cautioned to ensure they have completed adequate Quality Control reviews prior to scheduling pre-final or final inspections. In the event the Contracting Officer finds that the project is not ready for the applicable inspection, (too many discrepancies) the contractor may be held liable for the costs of a repeat inspection. If the inspection involves A/E personnel these costs may include additional labor, travel and miscellaneous expenses.
12. DESIGNATION OF TECHNICAL REPRESENTATIVE
The Contracting Officer will appoint a qualified Contracting Officer's Representative (COR) for the purposes of technically administering the contract; however, all matters concerning this contract or any work ordered placed against this contract must first be approved by the Contracting Officer. This in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in terms of the contract.
13. CONTRACTOR STAFF AND EMPLOYEES
13.1. Prior to commencing on-site work, the contractor shall provide the Contracting Officer with a telephone number and FAX number at which the contractor or his representative may be contacted at any time during regular working hours and an emergency number at which the contractor may be contacted in situations requiring immediate attention.
13.2. Supervision. The Government shall not exercise any supervision or control over the contractor employees performing services under this contract; such employees shall be accountable not to the Government, but solely to the contractor, who in turn is responsible to the Government.
13.3. Contractor's Employees. All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may, in writing, require the contractor to remove from the job site, any employee the Contracting Officer deems incompetent, careless or otherwise objectionable.
14. CONTRACTOR OFFICE AND STORAGE
14.1. Parking of contractor vehicles shall be restricted to the contractor's designed on-site area or the work area. The company name shall be prominently displayed on all work vehicles parked on the job site.
14.2. Security of material storage areas on the job site shall be the responsibility of the contractor. The area shall be kept neat and orderly and free of debris.
15. RECORD DRAWINGS
During work of a project and on the job site, the contractor shall maintain a completed record of all changes and corrections from the layout shown on the drawings, if applicable. The contractor shall enter such changes and corrections on contract or record drawings promptly, and submit the "red line" drawings to the Contracting Officer upon completion of the project. The record drawings shall indicate all changes and corrections concerning the actual locations of all sub-surface utility lines. In order for the location of these lines and appurtenances to be determined in the event the surface opening or indictors become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, the end of the each run including each change in direction. Valves splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded. The Government does not guarantee the accuracy of existing record drawings; it is the contractor's responsibility to verify all as-built conditions.
16. VERIFICATION OF DIMENSIONS
The contractor shall be responsible for the coordination and proper relation of all aspects of the work. He/she shall field verify all dimensions and advise the Contracting Officer of any discrepancies prior to proceeding with any phase of the work. Where exact locations are not given for the positioning of equipment and devices, they shall be positioned to permit easy access for maintenance and for removal and replacement of component parts.
17. SECURITY REQUIREMENTS
17.1. The contractor shall comply with all security regulations imposed by the base/post commander and/or agency occupying the space where work is to be performed. Any necessary security clearances shall be obtained prior to commencement of work.
17.2. It is expected that new security requirements to satisfy contractor personal identification requirements in Homeland Security Presidential Directive (HSPD-12), ''Policy for a Common Identification Standard for Federal Employees and Contractors,'' and Federal Information Processing Standards Publication (FIPS PUB) Number 201, ''Personal Identity Verification (PIV) of Federal Employees and Contractors" are incorporated in the life of this contract. Contractor shall comply with all requirements, at no additional cost to the Government.
17.3. The contractor shall ensure that all parts of the facility where work is being performed are adequately protected against vandalism and theft.
17.4. Contractors shall follow instructions provided by the 292nd CBCS Building Manager for access to 292nd CBCS. If a gate pass is not granted to a contractor allowing the delivery of goods, execution of warranty support, or performance of services please contact the contracting officer. Be sure that all of your employees have the proper ID (drivers license, state ID, immigration card, U.S. Passport, etc.). If they do not have the proper ID, they will be turned away.
17.5. The Prime Contractor and all of its subcontractors will be required to wear orange or lime colored safety vests while performing work on the installation.
17.6. U.S. Government will not be held liable for any delays or breach of contract caused by refusal of the Security Forces to allow entry.
17.7. All prospective contractors MUST be U.S. citizens or MUST have established and maintain legal residence in the U.S., and are authorized by the US government to work in the United States (i.e. Green card, worker authorization, etc.). All prospective contractors MUST have at least one form of U.S. government issued photo identification (drivers license, U.S. passport, U.S. work visa, etc.) for entry to the installation. Security Forces will review any questionable identification documents for determination as to whether or not said identification is authorized for access to the installation.
17.8. All prospective contractors/contractor employees, once it has been established that they maintain the appropriate credential as described in one above, are subject to a Criminal History Check.
17.9. Note: For the purposes of Contracting services, it is implied that, that any and all parties agree to a Criminal History Background Check once entered into any contract. Any documents that are provided and found fraudulent to include, but not limited to driver's licenses, contracting licenses, etc., will result in an arrest and potential termination for default from the contract. All contractors are subject to search in order to obtain entry onto the installation and while working on the installation. Any refusal to submit to a search of their person or vehicle will be deemed as a violent act of aggression against the installation and will be cause for dismissal from the installation and revocation of future privileges and installation access.
17.10. AT Level I Training. This provision/contract text is for contractor employees with an area of performance within a National Guard controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to National Guard installations, facilities and controlled access shall complete AT Level I awareness training. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the Contracting Officer's Representative (COR).
17.10.1. AT Level 1 awareness training is available at the following website: https://jko.jten.mil/courses/AT-level1/launch.html
17.11. AT OPSEC Information from the Contract Requirements Package
17.11.1. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer's Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation's Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
17.11.1.1. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (DODIO 2000.16V1_DAFI 31-145, DAFI 31-101 and DODM 5200.08v3_DAFMAN 31- 101v3), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
17.11.2. All contractor employees and associated sub-contractor employees assigned to work on a government site and/ or requiring access to a DoD network will be required to complete the necessary training required of them initially and annually for the duration of the contract (i.e., DoD IAA Cyber Awareness, Protecting Sensitive Information, Force Protection, etc.).
17.11.3. Antiterrorism Awareness Level I Training (AT Level I). This standard language is for contractor employees with an area of performance within a US Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on Joint Knowledge Online (JKO) at https://jkodirect.jten.mil /Atlas2/page/login/Login.jsf. For those without a CAC, select "Non-CAC" user on the JKO site. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.
17.11.4. For contracts that require an OPSEC Plan. The contractor shall develop an OPSEC Plan and provide it to the COR or KO within 30 calendar days of contract award to be reviewed and approved by the responsible Government OPSEC officer, per AFI 10-701, Operations Security. This Plan shall include the government's critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.
For the contractor to effectively comply with OPSEC provisions of the contract, the organization will provide the following guidance: (1) Organization's Critical Information; (2) Adversaries' collection threat information as it applies to the organization's mission and the contract; (3) Operations Security guidance; and (4) Specific OPSEC measures the organization requires (as appropriate).
17.11.4.1. Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 30 days of employees' initial assignment to the contract and prior to having access to any critical information (CI) and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) located on the Defense Counterintelligence and Security Agency website: https://securityawareness.usalearning.gov /opsec/index.htm and the OPSEC Annual training- DAF-Operations Security Awareness Training located on My Learning https://lms-jets.cce.af.mil /moodle/course/view.php?id=11654#section-1
18. REGULATIONS
18.1. The contractor shall comply with all applicable Federal, State, Local, DOD, National Guard Bureau, Army and Air Force regulations pertaining to safety, traffic control and fire prevention.
18.2. The contractor may use the Civil Engineering library, which contains most applicable Army and Air Force publications as well as some commercial project data information, or the Defense Procurement and Acquisition Policy website, http://www.acq.osd.mil/dpap/, which has links for several other sites with available publications, forms and project data information. These may also be acquired from the Government Printing Office website, http://www.gpoaccess.gov/index.html
19. TRANSPORTATION, HANDLING AND STORAGE
19.1. The contractor shall coordinate with suppliers and shippers to ensure that incoming materials are properly identified with the contractor's name, contract number and project title. The contractor shall designate an authorized individual to be available to receive shipment. The Government will not provide storage other than that available at the project site.
19.2. Storage of supplies, materials and equipment on the project site shall be accomplished in such a manner so as to prevent mechanical and climatic damage and loss due to vandalism or theft. Equipment temporarily removed in the performance of work and stored on the job site shall be stored and protected in accordance with previous paragraphs, and shall be replaced in a condition compatible with its original state. Security for equipment and material removed from the job site for temporary storage until reuse shall be the responsibility of the contractor.
20. CLEANUP AND DISPOSAL OF DEBRIS AND FILL MATERIALS
20.1. At the end of each workday, the contractor shall clean up the work and storage areas and stack all materials in a manner approved by the Contracting Officer or his designated representative. Upon completion of a project, the contractor shall ensure that all dirt, trash, and debris resulting from the project operations are removed from the work area. Unless directed otherwise in the contract or by the Contracting Officer, disposal of debris shall be made at the contractor's expense and shall be delivered to a state approved disposal site located off base. Debris shall not be left in such a manner that wind or other weather conditions can cause the debris to be scattered outside the work area (i.e., on nearby runways, ramps or taxiways).
20.2. The hauling and disposal of excess fill material including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be the responsibility of the contractor. Disposal shall be in accordance with applicable state and local regulations.
21. ENVIRONMENTAL IMPACT
All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law. Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.
22. HAZARDOUS MATERIALS
22.1. Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract.
22.2. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos-containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating. Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.
23. POLLUTION ABATEMENT
23.1. All work shall be performed in a manner minimizing pollution of air, water and land as required.
23.2. Transporting materials to or from the site shall be accomplished in a manner preventing materials or particles from becoming airborne. Earth materials shall be wetted or otherwise protected. Gravel, sand and concrete shall be contained within vehicles to prevent spillage. Tarpaulins must be fastened over load before entering surrounding streets. Removal of any materials dropped or blown off vehicles shall be the responsibility of the contractor.
23.3. Burning of any material is strictly prohibited.
23.4. Stream beds, lakes, drainage ways, sanitary and storm sewers, etc., shall not be polluted by fuels, oils, bitumen, acids or other harmful materials.
Grading shall be accomplished to prevent surface drainage from the project site containing harmful amounts of sediment from draining onto adjacent areas.
23.5. Flushing of concrete trucks is restricted to the location specifically designed for this purpose by the Contracting Officer's Representative.
23.6. Excess mortar, plaster or drywall materials shall not be disposed of on Government property. Water utilized for plastering or drywall equipment shall be disposed of in accordance with the instructions of the COR, and under no circumstances shall water be disposed of in areas which are planted or scheduled to be planted.
24. COORDINATION WITH GOVERNMENT ACTIVITIES
24.1. If it becomes necessary to interrupt work activities in buildings and/or areas for project work purposes, permission to do so must be requested in writing to the Contracting Officer fifteen (15) working days prior to commencing work on the planned interruption and shall be subject to Civil Engineering approval. Written requests for street closing shall be submitted for approval of the Civil Engineer fifteen (15) working days prior to closing the street.
24.2. Work in…