Q-As W50S9523B000200001 Q-As.pdf
PDF 130 KB Posted
- Attached to
- Hot Cargo Pad
- Solicitation number
- W50S9523B0002
- Issued by
-
Department of the Army National Guard
About this file
This document contains questions and answers related to a solicitation for construction of a hazardous cargo pad at Joint Base Charleston, South Carolina. The solicitation involves construction of a new hazardous cargo pad, taxiway shoulders, and patrol road, with options for additional work including airfield lighting.
The prime contractor must provide quality control specialists and managers for civil works, concrete/pavements, soils, and environmental work who are separate from the overall CQC system manager. Inspections will be required during construction. The pre-bid meeting is not mandatory. The grading limits for the hazardous cargo pad if the access road option is excluded would be updated to tie into existing grades near station 56+00. Silt fence and removal is required for batch plant areas. Driver training and escort procedures are outlined. Clarification is provided on pavement section details and shoulder slopes.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question # Question Answer
During the site visit on 8/3/23 the existing patrol road to be relocated appeared to be a mixture of gravel and organic material/grasses rendering it an unsuitable material based on Plan Sheet CD101 (Note 2) which states that the contractor may reuse existing patrol road aggregate to construct the proposed patrol road as long as proper precautions are taken to keep aggregate clean from underlying organic material. Should we assume all new aggregates for the relocated section of the patrol road?
It is the intent that the Contractor can reuse the existing material as much as possible. If the material is contaminated with existing organic material or it occurs as a result of the Contractor’s operation, new crushed aggregate base course will need to be provided by the Contractor. The area of the patrol road that will be relocated has minimal reusable gravel.
Plan sheet GC141 States Work Areas 1 & 2 can be completed concurrently. It also states that Work Area 1 shall be completed in 80 Days and Work Area 2 shall be completed in 21 Days. Please confirm that Work Areas 1 & 2 when performed together shall be completed in 101 Days with the work in area 2 to be limited to no more than 21 Days within the overall 101 Day duration
Work Areas 1 and 2 will have 106 Calendar Days to complete the work. Work Area 1 has 80 days, Work Area 2 has 21 Calendar Days + 5 nights. All work within Work Area 2 disturbing the existing runway shoulder which includes grading, excavation, and backfill and paving with appropriate materials shall be completed within that original 21 days. Once the concrete pavement and asphalt has fully cured out, 5 additional nights will be allowed to finish the electrical installation, pavement markings, joint sealing, etc. that would have affected the regular runway operations.
If Phase 1 (Submittal Phase – 180 Calendar Days) is completed earlier, will bidding contractors be allowed to use the extra time saved in Phase 1 and apply to the Phase 2 construction phase?
365 days is for both phases; and if phase 1 is completed earlier than projected that would allow more time for phase 2
4 Will an option for electronic bid submission be allowed? All bids should be either mailed or dropped off in person prior to bid opening.
Standard form 1442 Box 8 states to address offers to ‘USPFO SC 169 Mission Support Contracting 1325 South Carolina Road, Eastover, SC 29044’. Page 9 or 82 from the solicitation paragraph 5.1 state to address offers to “USPFO SC, Purchasing and Contracting, 9 National Guard Road, Columbia, SC 29201’. Please clarify the correct location in which to address offers.
All bids should be either mailed to 9 National Guard Rd or dropped off in person to 1 National Guard Rd Columbia, SC
Note 2 on sheet GC111 of the plans state "Taxiway shoulders will be constructed to a width of 10' wide and the shoulders around the Hazardous Cargo Pad will be constructed to 25' wide under the Base Bid." Sheet CP302 shows details for 25' wide shoulders at the Taxiway and 50' wide shoulders at the Hazardous Cargo Pad. Please provide details for 10' wide shoulders at the Taxiway and 25' wide shoulders at the Hazardous Cargo Pad.
The provide Detail 1 shall be utilized for both the Base Bid and Option #4. For the base bid the width of the asphalt shoulder should be reduced from the provided 25’ to 10’.
The provide Detail 2 shall be utilized for both the Base Bid and Option #4. For the base bid the width of the asphalt shoulder should be reduced from the provided 50’ to 25’.
The lights and asphalt pavement section shall remain the same regardless of shoulder width. The proposed surface and grades will be updated once the project is awarded, and final options selected.
Paragraph 3.6.1 of specification section 01 50 00 requires that the contractor provide the Government Resident Engineer with an office. Please confirm that this office will be required. Office will be required for inspector
Paragraph 3.5.4 of specification section 01 50 00 requires a temporary 6' high chain link fence with green strip inserts around trailers and material storage areas. Is the 6' chain link fence with green strip inserts required on this project?
No, Temporary security fence will be at the contractor’s discretion. Previous contractor did not install security fence at batch plant site. It is the responsibility of the Contractor, not the Government or Base, to secure/protect their batch and storage facilities
In the Solicitation on pages 4 of 82 and 5 of 82 for Item No's 0002, 0003, 0004 and 0005 starting with the third line it states "Contractor shall furnish all necessary equipment, labor, materials, tools and transportation needed to accomplish additional brick masonry IAW attached Drawings and Specifications." There is not any brick masonry shown on the documents. Please clarify. There is no brick masonry on the project. Disregard this reference to brick masonry
Will the government provide a full geotechnical report to accompany the soil borings included in the plans? The soil boring log reports will be provided for the project
Construct Hazardous Cargo Pad PSTE 159098 McEnture JNGB, Eastover, SC 29044
W50S9523B00020001
In the contract specifications paragraph 1.6.2 of section 01 30 00 requires a superintendent with 10 years’ experience in construction and at least 5 years’ experience as a superintendent on projects similar in size and complexity. Paragraph 1.6.1 of section 01 35 26 requires a Site Safety and Health Officer (SSHO) that has the training, experience, and qualifications in accordance with EM 385‐1‐1 Section 01.A.17 and all associated subparagraphs. The SSHO must be onsite at all times when work is in progress. Per paragraph 1.6.1.1.1 the SSHO May not serve as the Quality Control Manager or as the superintendent. Paragraph 3.4.2 of section 01 45 00.00 states that a CQC System Manager must be provided for this project and this person can have no other duties. The CQC System Manger is required to be a graduate engineer or a graduate of construction management with a minimum of 10 years construction experience on airfield construction similar to this Contract. Please confirm that all 3 of the positions above are separate full time individuals and are all required to be present on site when work is in progress. Yes, each position is required as stated in the specifications
In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires an Electrical Quality Control Specialist. This paragraph further requires that this Electrical QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site during work on the specialized personnel's area of responsibility. The Electrical QC Specialist must be a graduate electrical engineer with 3 years related experience or a person with 5 years of experience supervising electrical features of work in the field with a construction company. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Electric QC Specialist and that the Electrical QC Specialist has to be a separate individual from the CQC System Manager. Yes, the CQC System Manager cannot fill the specialist roles
In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires a Civil Quality Control Specialist. This paragraph further requires that this Civil QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site at all times during which work within his or her area of responsibility is taking place. The Civil QC Specialist must be a graduate civil engineer or construction manager with 10 years of experience in the type of work being performed on this project or a technician with 10 years related experience. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Civil QC Specialist and that the Civil QC Specialist has to be a separate individual from the CQC System Manager. Yes, the CQC System Manager cannot fill the specialist roles
In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires an Environmental Quality Control Specialist. This paragraph further requires that this Environmental QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site at all times during which work within his or her area of responsibility is taking place. The Environmental QC Specialist must be a graduate environmental engineer with 3 years of experience. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Environmental QC Specialist and that the Environmental QC Specialist has to be a separate individual from the CQC System Manager. Yes, the CQC System Manager cannot fill the specialist roles
In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires a Concrete/Pavements and Soils Quality Control Specialist. This paragraph further requires that this Concrete/Pavements and Soil QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site at all times during which work within his or her area of responsibility is taking place.
The Concrete/Pavements and Soils QC Specialist must be a materials technician with 5 years of experience in the area of specialty. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Concrete/Pavements and Soils QC Specialist and that the Concrete/Pavements and Soils QC Specialist has to be a separate individual from the CQC System Manager. Yes, the CQC System Manager cannot fill the specialist roles
In the contract specifications paragraphs 1.5.1.a and 1.5.1.b of Section 32 13 14.13 require a Concrete Paving CQC Manager. These paragraphs require that the Concrete Paving CQC Manager is a separate person and is in addition to the CQC System Manager. The Concrete Paving CQC Manger must have a minimum of 10 years airfield concrete paving experience similar to work required under this contract with a minimum of 4 years in a concrete paving CQC role and be an ACI Concrete Transportation Inspector. Please confirm that the Concrete Paving CQC Manager can be the same person as the Concrete/Pavement and Soils QC Specialist required in paragraph 3.4.3 of section 01 45 00.
Yes if workload allows it. If paving and soil work is ongoing at the same time, one person can likely not be filled by the same individual
In specification section 32 12 15.13 paragraph 1.5.a requires an Airfield Asphalt Pavement QC Manager, paragraph 1.5.b requires an Airfield Asphalt Pavement Inspector and paragraph 1.5.c requires an Airfield Asphalt Pavement Laboratory Technician. Can these three positions be filled by one individual provided he or she has all the required certifications? No
In specification section 32 12 15.13 paragraph 1.5.a requires an Airfield Asphalt Pavement QC Manager, paragraph 1.5.b requires an Airfield Asphalt Pavement Inspector and paragraph 1.5.c requires an Airfield Asphalt Pavement Laboratory Technician. Please confirm that these three positions can be the same person as the Concrete/Pavement and Soils QC Specialist required by paragraph 3.4.3 of section 01 45 00.
No. Airfield Asphalt Pavement QC manager, Airfield Asphalt Pavement Inspector, and Airfield Asphalt Pavement Laboratory Technician should be individuals. Those roles can serve as specialist roles if time allows. Shall asphalt paving, concrete paving, and soils work are all ongoing at one time, one individual can not serve as the CQC specialist for all three items
In the solicitation a list of required documents was not provided to ensure a complete bid package submission. Can this list be provided?
Drawing GC142, “Runway and Taxiway Marking, Lighting, Signs, and Visual Navaids” note C states that for temporary runway closures, the contractor will “mark the runway with closure crosses in accordance with the detail to be provided at that point”. Please provide details and information on the requirements for closure crosses for the runway closures required for this project with additional clarifications as follows: Are lighted closure crosses required for runway closures on this project? If they are required, will the contractor be responsible for providing, placing, and maintaining the lighted closure crosses? If fabric closure crosses are required for runway closures, please provide a detail for the fabric closure crosses.
The runway is not anticipated to be closed during operations. However if the runway is needed to be closed during construction as a result of construction operations, the runway closure markers shall meet requirements as mentioned in UFC 3‐260‐04 Airfield and Heliport Marking or FAA AC 150/5340‐1, Standards for Airport Markings, and FAA AC 150/5345‐55, Lighted Visual Aid to Indicate Temporary Runway Closure
21 Is the Pre‐Bid mandatory? No
Since the HCP & Access Road intersect, what are the limits of grading that should be included in Item 0001 – Construct Hazardous Cargo Pad (in the event that Item 0004 – Construct Paved Access Road is not awarded)?
If Item 4 is not awarded, the grading will be updated appropriately to tie into the existing ground to remain approximate near STA 56+00. If the access roadway is not constructed, the roadway “berm” and culvert pipe will not be needed. The underdrain outlet pipe will need to have an endwall installed in the bank similar to the other underdrain outlet pipe and endwall at STA 19+61.68 OFF 360’.
Item 0001 (Base bid) references electrical infrastructure and Item 0002 (Option1) references “…runway and taxiway lights, etc”. Should Item 0002 only include the overhead lighting and associated electrical?
Item 0001 (Base Bid) shall include the items called out in Note 1 on GC111 included blank cover plates in the event that Item 0002 (Option1) is not awarded. Item 0002 (Option 1) shall include the items called out in Note 3 on GC111. The intent is to include the electrical infrastructure that needs to be installed prior to pavement and final grading as part of Item 0001 (Base Bid). The electrical fixtures and cables for the taxiway lights can be installed separate along with the electrical components of the overhead lighting system. Blank cover plates will need to be installed under Item 0001 (Base Bid) but wouldn't be necessary if Item 0002 (Option 1) is awarded.
24 Will silt fence be required at the Batch Plant/laydown area? Yes. Silt fence is required and is required to be removed at completion 25 How much time does it take for driver training for the base? About one hour.
Can the contractor escort delivery drivers, mechanics, etc.? If so, can more than one vehicle be escorted? Yes and Yes.
27 Will the 6” and 8” water lines be removed and relocated under Item No. 0004?
No. The removal and relocation of the 6” and 8” water lines shall be included under Item No. 3
For the proposed Patrol Road, Detail 4 indicates topsoil placement at variable width, CG114 grading limits do not include topsoil placement for a majority of the length of the patrol road. Should the grading limits as shown be used to determine the quantity of topsoil placement?
Yes. Portions of the patrol road will be able to be built to existing grades and not warrant much if any salvaged topsoil work along the edges of it.
The proposed patrol road has no proposed grades for most of its length. Will the existing grade be the proposed grade? Yes
Detail 2 on CP302 and Detail 2 on CU521 do not match. CP302 shows the shoulder CABC bottom extending below the bottom of the stabilized drainage layer edge and CU521 shows the bottom of the CABC matching the top of the stabilized drainage layer. Please clarify.
Shoulder pavement section shall be constructed as shown on Details #1 and #2 on CP302. The depth of the CABC will be determined by the width of the shoulder awarded.
The callout indicating “15” to 22.5” ABC does not match the detail, as the ABC is shown at the top of the drainage layer. 15” also does not match details 1 & 2 on CP302 (7”). Please clarify.
Shoulder pavement section shall be constructed as shown on Details #1 and #2 on
CP302.
The shoulder CABC thicknesses do not match the 5% slopes shown for the shoulder subgrade. Should 7” (or 15”) be used as the outside edge thickness or should the 5% grade be held?
The Crushed Aggregate Base Course shown in Details #1 and #2 shall be offset from
HMA Surface by 2 FEET not 2 INCHES as stated on the details.
The intent is that the CABC material is graded to drain back to the underdrain trench at .5% not the 5% as stated on the details. The depth of CABC computes correctly if using the .5% instead of the 5% slope.
33 What is the depth of the existing aggregate on the patrol road?
Portion of patrol road that will be relocated has minimal gravel that is suited for reuse.
34 Is there a disposal area for excess soils and 1500 cy of unsuitable soils?
The base will (at the discretion of the contracting officer) accept suitable soil stockpiled for future use and will allow spreading of soil with appropriate erosion control in designated areas.