- Repair Corrosion Control Facility Federal contract opportunity
- Solicitation number
- W50S8B-21-B-0001
- Issued by
- Department of the Army National Guard
About this file
This document contains details for a federal contract solicitation to repair a corrosion control facility. The solicitation is a 100% small business set-aside between $500,000 to $1 million to reconfigure 2,500 square feet of space at a military facility. The scope of work requires providing all materials, equipment, labor, and supervision to complete and ready the bath/locker room and shop area. The contractor must designate a dedicated superintendent through project completion. The award will be a stand-alone contract, not a task order. The selected contractor must submit a critical path method construction schedule within five days of award and all personnel accessing the secure base will require a background investigation in accordance with security regulations.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 SF1442 ATTACHMENT SCHEDULE (Updated 13 Sep 20)
W50S8B20B0001 Beddown Global ASNT
ATTACH # TITLE SECTION
| 1 | Schedule of Attachments | 00010 - Notes |
| 2 | Section 00010 - Notes | 00010 - Notes |
| 3 | Section 00100 - Instruction to Offerors | 00100 - Notes |
| 4 | Scope of Work | 00800 - Special Contract Requirements |
| 5 | Project Specifications | 00800 - Special Contract Requirements |
| 6 | Project Drawings | 00800 - Special Contract Requirements |
| 7 | DOL Wage Determination | 00800 - Special Contract Requirements |
| 8 | Insurance Requirements | 00800 - Special Contract Requirements |
| 9 | PWS AT Statement | 00800 - Special Contract Requirements |
| 10 | JB MDL Antiterrorism Awareness for Contractors | 00800 - Special Contract Requirements |
| 11 | Appendix 4 to Annex C - Contractor Appendix | 00800 - Special Contract Requirements |
| 12 | RFI Questions & Answers Log - updated 13 Sep 20 | 00800 - Special Contract Requirements |
| 13 | Davit Crane Information - 6 Sep 20 | 00800 - Special Contract Requirements |
| 14 | Boring Log - 10 Sep 20 | 00800 - Special Contract Requirements |
| 15 | Pre-Bid Conference Slides | |
| 16 | Pre-Bid Conference Sign-In Sheet |
Sheet3 SF1442 ATTACHMENT SCHEDULE (Updated 23 Apr 21)
W50S8B21B0001 Repair NJANG Corrosion Control Facility
ATTACH # TITLE SECTION
| 1 | Schedule of Attachments | 00010 - Notes |
| 2 | Section 00010 - Notes | 00010 - Notes |
| 3 | Section 00100 - Instruction to Offerors | 00100 - Notes |
| 4 | Scope of Work | 00800 - Special Contract Requirements |
| 5 | Project Specifications | 00800 - Special Contract Requirements |
| 6 | Project Drawings | 00800 - Special Contract Requirements |
| 7 | DOL Wage Determination | 00800 - Special Contract Requirements |
| 8 | Insurance Requirements | 00800 - Special Contract Requirements |
| 9 | PWS AT Statement | 00800 - Special Contract Requirements |
| 10 | JB MDL Antiterrorism Awareness for Contractors | 00800 - Special Contract Requirements |
| 11 | Appendix 4 to Annex C - Contractor Appendix | 00800 - Special Contract Requirements |
| 12 | Pre-Bid Conference Slides | 00800 - Special Contract Requirements |
| 13 | Pre-Bid Conference/Site Visit Attendance | 00800 - Special Contract Requirements |
| 14 | RFI & Answers - Contracting | 00800 - Special Contract Requirements |
| 15 | RFI & Answers - CES | 00800 - Special Contract Requirements |