SoW 24JUN22.pdf

PDF 206 KB Posted

Attached to
REPAIR SUBSTATION Federal contract opportunity
Solicitation number
W50S8A-22-B-5204
Issued by
Department of the Army New Hampshire Army National Guard

About this file

This statement of work outlines requirements for a substation repair project at Pease Air National Guard Base in New Hampshire. The contractor will remove an existing failed 3MVA substation transformer and replace it with a new unit of the same size and capacity. The contractor must plan and execute the project, demolish the failed transformer, install and integrate the new transformer, and provide documentation and training upon completion. The contractor will furnish all personnel, equipment, materials, and supervision to complete procurement and installation. The government will provide access to the worksite but no facilities, tools, materials, or utilities. The contractor must follow all safety, security, and environmental regulations and obtain required access credentials for the base.

View the file

Other files for this federal contract opportunity

Other files attached to REPAIR SUBSTATION, newest first.
File Type Posted
Abstract.pdf PDF
Amendment 02.pdf PDF
RFI Responses.pdf PDF
Amendment 01.pdf PDF
Preconstruction Conference sign in.pdf PDF
Business Cards.pdf PDF
SF 1442.pdf PDF
Site visit map.pptx PPTX presentation
SoW (2).pdf PDF
Bid Opening Map.pptx PPTX presentation

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT of WORK

For

SZCQ222305 - REPAIR SUBSTATION

JUNE 2022

157th AIR REFULING WING

NEW HAMPSHIRE AIR NATIONAL GUARD

PEASE AIR NATIONAL GUARD BASE, NEW HAMPSHIRE

FOR UNITED STATES PROPERTY AND FISCAL OFFICER

NEW HAMPSHIRE NATIONAL GUARD

Statement of Work

PEASE AIR NATIONAL GUARD BASE

1.0 Purpose: This project will repair the substation by removing one (1) existing failed

3.0 MVA substation transformer and replace it with a new 3.0 MVA transformer, at Pease

Air National Guard Base (ANGB), New Hampshire. The project will provide a direct replacement (same size, capability, characteristics, capacity and load rating) of the existing, failed unit. The project shall include planning and design, execution strategy , coordination, site evaluation/preparation/modification (as required), disposal of the failed transformer and associated non-reusable materials, placement/installation, connections

(control, line and load), and control and monitoring system integration, to provide full integration of the new transformer into the substation as a complete and usable system.

1.1 Scope: The contractor shall provide all personnel, expertise, equipment, tools, materials, supervision, and quality control necessary to perform procurement and installation as specified in this Statement of Work. The contractor shall provide:

1.1.1 Planning and Design:

1.1.1.1 The Contractor shall provide expertise to plan and execute the entirety of this project.

Select a suitable replacement transformer and identify requirements to upgrade relays, sensors, controls, and components as needed for a successful install and integration of the new transformer. Develop execution plan for the project. The plan will include the schedule and list components and materials for review and acceptance by the COR prior to procurement of components.

1.1.1.2 Create a project schedule identifying the sequence of events from material acquisition through project closeout, identifying all major events, including but not limited to work phases and milestone accomplishments, equipment and material deliveries, and power outage times and durations. Present the plan to the Base Civil

Engineer prior to initiating demolition.

1.1.2 Demolition:

1.1.2.1 Relocate the failed transformer without any further damage outside of the substation fence. The transformer will remain the property of the NH ANG to be refurbished at a future date.

1.1.3 Installation:

1.1.3.1 Replace the existing 3 MVA transformer with a new 3 MVA unit. Make all line, load, controls, and any other connections to provide a full, safe, and properly functioning system. System will be commissioned and tested/operated to industry standard and under full load of the base power grid prior to acceptance. Contractor shall provide the expertise to deliver a safe, proper, fully-functioning system.

1.1.4 Documentation: Provide updated as-built drawings, schematics, manuals & specifications, and manufacturer warranty information.

1.1.5 Turnover: Provide orientation on operation and maintenance of the new equipment to

Pease ANGB maintenance personnel. Contractor will schedule turnover 7 days prior to requested date. The transformer shall be commissioned prior to turnover.

1.2 Background: Pease ANGB receives power from the local electric utility (EverSource) at a substation located within Pease ANGB (see MAP), which is owned and operated by the

157 Air Refueling Wing, NH Air National Guard. The substation consists of two

3000/3750 kVA OA/FA transformers, transforming the incoming 34.5kV to 13.8Y/7.97 KV for distribution. Each transformer serves a bus with 4 feeders; 2 feeders on each bus are spare/future, and the other two serve base loads. The busses can be tied such that one, or both, transformers serve all feeders. As one transformer is presently inoperative, the bus tie is currently closed with the inoperative transformer offline and the second transformer energizing the entire base.

1.2.1 In 2021, following unit failure, a dissolved gas analysis indicated the 30-year old 3

MVA primary transformer had been experiencing significant internal arcing and was “in imminent danger of catastrophic failure”.

1.2.2 The load of Pease ANGB is typically 2.1 MW with peak load 2.6 MW. However, the base is growing. Prior to the failure, the load was distributed in parallel through both transformers simultaneously, and this capability needs to remain available after the replacement.

1.3 General Information:

1.3.1 Place and Performance of Services: Performance shall be at the Pease ANGB substation. Standard Hours of Operation for maintenance performance is Eastern Standard Time

(EST) of 0700 (7:00 a.m.) to 1600 (4:00 p.m.) during the period of performance, except on recognized United States (US) holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the

Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

At the discretion of the Base Civil Engineer on a case-by-case basis, work outside the Standard

Hours of Operation may be authorized for emergency situations or for convenience of the

Government (such as base-wide power outage). Requests to perform work outside the Standard

Hours of Operation should be made as far in advance as possible.

1.3.2 Recognized Holidays: The following are recognized US holidays. The contractor shall not perform services on these day without prior approval:

1.3.2.1 New Year’s Day: 1 January

1.3.2.2 Martin Luther King, Jr.’s Birthday: Third Monday in January

1.3.2.3 President’s Day: Third Monday in February

1.3.2.4 Memorial Day: Last Monday in May

1.3.2.5 Juneteenth 19 June

1.3.2.6 Independence Day: 4 July

1.3.2.7 Labor Day: First Monday in September

1.3.2.8 Columbus Day: First Monday in October

1.3.2.9 Veteran’s Day: 11 November

1.3.2.10 Thanksgiving Day: Third Thursday in November

1.3.2.11 Christmas Day: 25 December

1.3.3 Perform electrical work in accordance with EM 385-1-1, Appendix A, Sections 11 and

12.

1.3.3.1 Conduct of Electrical Work: As delineated in EM 385-1-1, electrical work is to be conducted in a de-energized state unless there is no alternative method for accomplishing the work. In those cases obtain an energized work permit from the

Contracting Officer. The energized work permit application must be accompanied by the

AHA and a summary of why the equipment/circuit needs to be worked energized.

Underground electrical spaces must be certified safe for entry before entering to conduct work. Cables that will be cut must be positively identified and de-energized prior to performing each cut. Attach temporary grounds in accordance with ASTM F855 and

IEEE 1048. Perform all high voltage cable cutting remotely using hydraulic cutting tool.

When racking in or live switching of circuit breakers, no additional person other than the switch operator is allowed in the space during the actual operation. Plan so that work near energized parts is minimized to the fullest extent possible. Use of electrical outages clear of any energized electrical sources is the preferred method. When working in energized substations, only qualified electrical workers are permitted to enter. When work requires work near energized circuits as defined by NFPA 70, high voltage personnel must use personal protective equipment that includes, as a minimum, electrical hard hat, safety shoes, insulating gloves and electrical arc flash protection for personnel as required by NFPA 70E. Insulating blankets, hearing protection, and switching suits may also be required, depending on the specific job and as delineated in the Contractor's

AHA. Ensure that each employee is familiar with and complies with these procedures and 29 CFR 1910.147

1.3.3.2 Electrical work must be performed by qualified personnel with verifiable credentials who are familiar with applicable code requirements. Verifiable credentials consist of

State, National, and Local Certifications or Licenses that a Master or Journeyman

Electrician may hold, depending on work being performed, and must be identified in the appropriate AHA. Journeyman/Apprentice ratio must be in accordance with State and

Local requirements applicable to Newington NH.

1.3.4 Quality Control (QC). The contractor shall develop and maintain an effective QC program to ensure services are performed in accordance with this PWS. Personnel who perform work on the power lines must be qualified to any NEC and/or NFPA standard.

1.3.5 Quality Assurance (QA). The Government will evaluate the contractor’s performance under this contract in accordance with a Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level. Personnel who perform work on the power lines must be qualified to any NEC and/or NFPA standard.

1.3.6 The contractor is responsible to verify all technical details pertaining to the size, location, specification, capability, capacity, load rating, pad mount placement, and bus energization capabilities of the system during the site visit, prior to making a bid. Any information, specification or drawing provided in or attached to the solicitation is for familiarization only and the government will not be responsible for varying site conditions.

1.3.7 The contractor will warranty all work performed under this contract for 365 days from the date of final acceptance of the project. Any defect of equipment, material, workmanship, or design furnished, and further damages caused by these defects, which occur prior to this date, will be the responsibility of the contractor to correct.

1.3.8 The Contractor shall submit invoice consistent with the format of the contract line items.

Contractor shall submit invoice within five (5) calendar days after the completion of each performance period.

1.3.9 The Government will review the invoice and reject or authorize payment as applicable through WAWF.

1.3.10 Security Clearance Requirements. SECRET / TOP SECRET Security Clearances are not required, but background checks are mandatory for installation access. The

Government reserves the right to deny access at any time, without a stated reason.

1.3.10.1 AT Level I Training. This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to

Government Installations, Facilities and Controlled Access areas shall complete AT

Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable.

Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I

Awareness Training is available through ADLS by completing the Force Protection

CBT.

1.3.10.2 Contractor and all associated sub-contractor’s employees shall provide all information required for background checks to meet installation access requirements to be accomplished by 157th Security Forces, Pass and Identification (ID) Office.

Contractor workforce shall comply with all personal identity verification requirements as directed by DOD, United States Air Force (USAF), and local policy. Should the

Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.3.10.3 Entrance to Pease ANGB is controlled and security is strictly monitored. In accordance with the Pease ANGB Policy for Contractor Access, the Contractor shall obtain access Badges. Submissions of required documents should be accomplished prior to the pre-performance conference or 10 calendar days prior to start of work. Any additions or changes shall be submitted to the Contracting Officer’s Representative

(COR) no less than 3 weekdays prior to required period of performance to allow timely processing. Access credentials will only be issued following an approved identification process to include vetting against authoritative government databases from the 157th

Security Forces Pass and ID Office. The Contractor is cautioned that these requirements shall be strictly enforced and any delays and/or costs associated with not adhering to these requirements shall be at the Contractor’s own expense.

1.3.10.4 The Contractor will coordinate with the COR on all security issues and to gain access to the base and all areas necessary to execute this service.

1.3.10.5 The Contractor shall ensure that all employees, suppliers, and subcontractors and their employees comply with established security procedures for entering the installation and its facilities, including special security procedures for entry to restricted or controlled areas.

1.3.10.6 All prospective contractors MUST be U.S. citizens or MUST have established and maintain legal residence in the U.S., and be authorized by the US government to work in the United States (i.e. Green card, worker authorization, etc.). All prospective contractors MUST have at least one form of US government issued photo identification

(driver’s license, US passport, US work visa, etc.) for entry to the installation. Security

Forces will review any questionable identification documents for determination as to whether or not said identification is authorized for access to the installation.

1.3.10.7 All personnel, the vehicles and property under their control are subject to search upon entering or exiting the installation, or at any point while on the installation.

Any vehicles or personnel found in possession of prohibited items will be removed, and/or barred, from the installation and released to the appropriate civil authorities.

1.3.10.8 The Government will not be held liable for any delays or breach of contract caused by refusal of the Security Forces to allow entry.

1.3.10.9 All contractors and their subcontractors who are issued passes to gain access to

Pease ANGB must return all local access credentials to the Contracting Officer

Representative (COR) when the contract is completed or when a contractor employee no longer requires access to the installation (e.g., quits or is terminated). Failure to do so will initiate immediate notification to SF for an appropriate update in Defense

Biometric Identification System (DBIDS) when a contractor refuses to return issued access media. If a local access credential is not returned, the Installation

Commander may consider debarment.

1.3.10.10 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured. The contractor shall ensure that all parts of the facility/substation where work is being performed are adequately protected against vandalism and theft. Further, all areas within the substation shall be left electrically safe when not actively working.

1.3.10.11 Areas controlled by Contractor employees shall comply with installation operations plans/instructions for Force Protection Condition procedures, Random

Antiterrorism Measures (RAMS) and local search /identification requirements. The

Contractor shall be responsible for safeguarding all Government property provided for

Contractor use. At the end of each work shift, all Government facilities, equipment, and materials shall be secured.

1.3.10.12 Anti-Terrorism (AT) Level 1 Awareness Training. All contractor employees, to include subcontractor employees, requiring access to National Guard installations, facilities, and controlled access areas shall complete AT Level 1 awareness training no later than 30 calendar days after contract start date and no later than 30 calendar days of new employees commencing performance. AT level 1 awareness training can be completed at the following website: http://jko.jten.mil/courses/atl1/launch.html or by locally approved training provided by the installation. The contractor shall submit signed certificates validating completion.

1.3.10.13 Identification of Contractor Employees: The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor http://jko.jten.mil/courses/atl1/launch.html products.

1.3.10.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in Federal Acquisition Regulation (FAR) Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the

KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.3.11 Safety and Fire Protection Requirements.

1.3.11.1 Safety Requirements. The contractor shall take all necessary precautions to meet proper safety standards and regulations of all local, state and federal codes and regulations. In performing work under this contract, the contractor shall:

1.3.11.2 Comply with all Occupational Safety and Health Administration (OSHA) regulations and requirements shall apply to all work performed on the Installation.

1.3.11.3 Conform to any additional restrictions outlined by the Base Safety Officer

(BSO) and the 157th ARW Fire Department (FD) during the course of the contract to insure the safety of their employees, government employees and the general public.

1.3.11.4 Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

1.3.11.5 Take such additional immediate precautions as the contracting officer may reasonably require for safety and mishap prevention purposes.

1.3.11.6 Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the Contractor.

1.3.11.7 Record and report promptly (within one hour) to the contracting officer or authorized COR all available facts relating to each instance of damage to government property or injury to either Contractor or government personnel.

1.3.11.8 1.5.12.1.7 In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer. If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.

1.3.11.9 When entering the Installation there are requirements that shall be adhered to.

They are as follows:

1.3.11.10 While on the installation, use of a cell phone while operating a vehicle or other motorized equipment is prohibited by DoD regulations unless the operator is utilizing a hands-free device.

1.3.11.11 The installation speed limit is 25 mph unless otherwise posted. Motor vehicle regulations are strictly enforced and excessive violations may result in the loss of driving privileges on the installation.

1.3.11.12 The Installation speed limit is reduced to 15 mph and strictly enforced adjacent to military troop movements (i.e., personnel, vehicle convoys, etc.) traversing installation roadways.

1.3.11.13 Failure to follow the on base requirements is grounds for removal from the installation.

1.3.11.14 Fire Prevention and Protection Plan. This section covers the responsibility of the

Contractor while performing under this contract. The emergency telephone number for

Pease ANGB is 911.

1.3.11.15 1.5.13 Environmental Protection: This section covers the responsibility of the contractor while performing under this contract.

1.3.11.16 Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, Federal, State, and Local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the KO pursuant to notice requirements and negotiate a modification to the contract.

1.3.11.17 Conservation of Utilities. The contractor shall instruct employees in utilities conservation. The contractor shall operate under conditions that preclude wasting utilities.

1.3.11.18 Contractor Furnished Property, Materials, Equipment (CFP/M/E). Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

2 Government Roles and Responsibilities:

2.1 The Contracting Officer (KO) is the only individual with the authority to authorize changes within this project that will have an effect on the scope and/or monetary value (increase or decrease) of contract.

2.2 The Contracting Officer’s Representative (COR) is the individual designated and authorized in writing by the Contracting Officer at contract award to perform specific technical or administrative functions on contracts. The key role of the COR is to observe, document, and communicate contractor performance to both the KO and Contractor. All coordination and correspondence should be forwarded through the COR to the KO. COR and alternate COR (if applicable) will be responsible for the inspection and acceptance of performance and any deliverables under the scope of this PWS and resulting contract. The COR does NOT have authority to change the terms and conditions of the contract.

2.2.1 All contracting actions and/or correspondence should be forwarded through the COR.

The COR will act as the Contracting Officer’s Representative for technical matters, providing technical direction and discussion as necessary with respect to the SOW, and monitoring the progress and quality of the contractor’s performance . The COR does not have authority to take any action, either directly or indirectly, that would change the pricing, quantity, quality, place of performance, delivery schedule, or any other term and condition of the contract, or to direct the accomplishment of effort that goes beyond the scope of the PWS in the contract. When, in the opinion of the contractor, the COR requests efforts outside the existing scope of the contract, the contractor shall promptly notify the KO in writing. The contractor under such direction shall take no action until the KO has resolved the issue or has otherwise issued a modification to the contract.

2.2.2 In the absence of the COR (due to reasons such as leave, illness, and official travel), all responsibilities and functions assigned to the COR shall be the responsibility of the KO until an alternate is assigned.

2.3 Government personnel other than KOs and the authorized COR, may, with KO coordination, observe Contractor operations. However, these personnel may not interfere with Contractor performance or make any changes to the contract.

2.4 Other Observers. 157th CE Personnel, Military Public Health (MPH) personnel, Inspector

General (IG) Personnel, and other authorized government personnel shall be permitted to observe operations as necessary. These operations include but are not limited to duties at the

Contractor’s facility, transportation from the Contractor’s facility to the installation and return to the Contractor’s facility. Contractors may be requested to provide State and Municipal certificates.

3 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The

Government will provide the facilities, equipment, materials, services, and/or utilities listed below.

3.0 Facilities: There are no facilities available for use. Bringing personnel, supplies, tools and equipment are the responsibility of the contractor. There are locations that equipment can be stored outside but within locked gates, but it is the responsibility of the contractor to maintain the security and safety of those assets. The government will not be responsible for any damage to equipment left on base.

3.1 Equipment: The Government will not provide any tools required to perform this service. The contractor is responsible for furnishing all equipment per paragraph 1.1.

3.2 Materials: The government will not provide any materials for the execution of this project.

It is the responsibility of the contractor to source and provide all materials required to install and commission the transformer, providing a fully functional system in line with the intent of this project.

3.3 Utilities: All utilities will be available for the contractor’s use in the performance of this contract.

3.4 Secret Facility Clearance: The contractor does not require a security clearance for the performance of this work.

4 Definitions and Acronyms.

4.0 Definitions.

4.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

4.2 CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

4.3 CONTRACTING OFFICER'S REPRESENTATIVE. An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

4.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

4.5 DELIVERABLE. Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

4.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

4.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

4.8 QUALITY ASSURANCE. The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

4.9 QUALITY ASSURANCE SURVEILLANCE PLAN. An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

4.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

4.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The

Government does not have privet of contract with the subcontractor.

4.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

4.13 WORK WEEK. Monday through Friday, unless specified otherwise.

Acronyms.

AF Air Force AFARS Army Federal Acquisition Regulation Supplement AFI Air Force Instruction

AFMAN Air Force Manual AGR Active Guard and Reserve ANG Air National Guard AQL Acceptable Quality Level AT Anti-Terrorism BSO Base Safety Officer CFP/M/E Contractor Furnished Property, Materials, Equipment CM Contract Manager CMR Contractor Manpower Reporting CONUS Continental United States (excludes Alaska and

Hawaii) COR Contracting Officer Representative DA Department of the Army DFARS Defense Federal Acquisition Regulation

Supplement DOD Department of Defense EFT Electronic Funds Transfer EST Eastern Standard Time FAR Federal Acquisition Regulation FD Fire Department FSC Federal Service Code FPCON Force Protection Condition GFP/M/E Government Furnished Property, Materials, Equipment HQDAF Headquarters, Department of Air Force ID Identification IG Inspector General IW Intelligence Wing JBCC Joint Base Cape Cod KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs OSHA Occupational Safety and Health Administration POC Point of Contact POP Period of Performance PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Program SAM System for Award

Management TE Technical Exhibit UIC Unit Identification Code US United States USAF United States Air Force WAWF Wide Area Work Flow