RFI Responses.pdf
PDF 75 KB Posted
- Attached to
- REPAIR SUBSTATION Federal contract opportunity
- Solicitation number
- W50S8A-22-B-5204
About this file
This document contains responses to questions regarding a federal solicitation to repair a substation at Pease Air National Guard Base in New Hampshire. The solicitation calls for removing an existing failed 3.0 MVA substation transformer and replacing it with a new transformer of the same specifications, and integrating the new transformer into the substation's electrical system. Questions from potential offerors covered topics such as site access, bid extensions, design requirements, use of existing infrastructure, power outages during work, safety and quality control staffing, and coordination with the local utility. Responses from the agency clarified the scope of work, schedule, and contractor responsibilities for the replacement project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract.pdf | ||
| Amendment 02.pdf | ||
| Amendment 01.pdf | ||
| SoW 24JUN22.pdf | ||
| Business Cards.pdf | ||
| Preconstruction Conference sign in.pdf | ||
| Bid Opening Map.pptx | PPTX presentation | |
| SoW (2).pdf | ||
| SF 1442.pdf | ||
| Site visit map.pptx | PPTX presentation |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI
No. RFI Text
Date Received from CTR Response Text Date Posted
Amendment Number
1 For the lead times on the Transformer, will there be any changes to the solicitation time lines due to the long lead times for the Transformer? 16-Jun-22 Yes - see Amendment 001 27-Jun-22 1
We will also need to know what access there is to the site, how close to the transformer pad could a crane be set up to pick the existing and set the new transformer. 16-Jun-22 27-Jun-22 1
3 Will there be a bid extension? The manufacturers for this type of equipment are taking 4 weeks to put a quote together.. 16-Jun-22 Yes - see Amendment 001 27-Jun-22 1
Requesting a bid extension to July 22 nd per the vendors request for transformer pricing. With the current bid date being so close to the 4 th of July week, they won’t have time to put a price together.
16-Jun-22 see Amendment 001 27-Jun-22 1
Contract extension requested. Transformer vendor has told me that the replacement transformer has a 1- 1/2 year lead-time.
16-Jun-22 Yes - see Amendment 001 27-Jun-22 1
Are there any CAD files available for this project?
16-Jun-22 unknown at this time - scans of original as-built prints are all that are available 27-Jun-22 1
7 Design requirements – Can you provide more details on the design scope requirements for this project?
What submissions should we assume? 30%, 60%, 90% and IFC drawings? Do you have any specific requirements around submissions, design review meetings, design review comments, etc. 16-Jun-22
See SoW section 1.1.1. The Government is only requiring what is listed in this section for the Planning and Design 27-Jun-22 1
8 Do we assume that we can use the same transformer foundation and oil containment for the new transformer? 16-Jun-22 Yes. 27-Jun-22 1
Do we assume that we can use the existing secondary conduit and 15KVA cable?
16-Jun-22
All existing infrastructure (pad, conduit, cables, etc.) can be re-used to install/connect the new transformer as long as all codes and criteria are met. If cable lengths, conduit locations, etc. need to be modified to facilitate installation of the transformer selected by the contractor, the contractor is responsible for modifications as require to complete the installation. All modifications to existing infrastructure must be present to and approved by the Base Civil Engineer. 27-Jun-22 1
At the walkthrough the government indicated this is a one for one replacement of the existing transformer. The statement of work is different than the information provided at the walkthrough. What is the scope of this project?
16-Jun-22
The SOW states: "This project will repair the substation by removing one (1) existing failed 3.0 MVA substation transformer and replace it with a new 3.0 MVA transformer, at Pease Air National Guard Base (ANGB), New Hampshire. The project will provide a direct replacement (same size, Capability, characteristics, capacity and load rating) of the existing, failed unit." The statement of work states that the contractor will remove and replace 1 transformer. All changes or clarifications to the SOW will be in writing and issued by the contracting officer. 27-Jun-22 1
11 The statement of work indicates we are to validate the existing underground oil spill prevention system capacities 16-Jun-22 Secondary Containment Requirement removed from SoW 27-Jun-22 1
12 Can you provide us with any documentation regarding the construction of the existing spill containment? 16-Jun-22 Secondary Containment Requirement removed from SoW 27-Jun-22 1
13 Is the government aware of any reason why the existing spill containment is not adequate or not properly functioning? 16-Jun-22 Secondary Containment Requirement removed from SoW 27-Jun-22 1
14 Is there an oil water separator associated with the spill containment system? Is the oil water separator properly operating? If the oil water separator is not properly operating what known defects are there? 16-Jun-22 Any needed repair to the OWS system is not within the current scope of this contract. 27-Jun-22 1
15 Has the government inspected the existing spill containment system? Can you provide us a copy of the report associated with the inspection? 16-Jun-22 Spill containment system is fully operational. 27-Jun-22 1
16 If the spill containment is found to be inadequate is it part of this project to replace the spill containment? Or are we to inform the government of the inadequacy and a separate project will be undertaken to handle upgrade or replacement to the spill containment? 16-Jun-22
The existing secondary containment system was designed for the existing transformers and is fully operaitonal. Contractors will Bid what is indicated in the SF1442 and SOW. 27-Jun-22 1
RFI Response Repair Substation W50S8A22B5204
The statement of work indicates we are to identify requirements to upgrade relays, sensors, controls, and components for the new transformer:
16-Jun-22
Replacements or upgrades to any ancillary systems (relays, controls, sensors, etc.)
are only required within the scope of this project if they are necessary to install and integrate the new transformer into the existing system, in line with the intent of this project to "provide full integration of the new transformer into the substation as a complete and usable system." Any such modifications to the substation to integrate the new transformer into the system must be detailed to the BCE in a detailed work plan, as stated in 1.1.1.1 of the SoW 27-Jun-22 1
18 Is it the intent of this contract that the above listed items(Questions 12-17) will be evaluated under this project and any replacement of them or upgrade will be performed as a follow on project? Or is it the intent of this project that all sensors, relays, controls and other components associated with the transformer will be replaced as part of this project? 16-Jun-22 Contractors will Bid what is indicated in the SF1442 and SOW. 27-Jun-22 1
Is the government aware of any issue with existing relays, sensors, controls or other components of the system that require upgrading or replacement?
16-Jun-22
No, the substation was fully operational and is currently operational with the exception of the failed transformer. Replacements or upgrades to any ancillary systems (relays, controls, sensors, etc.) are only required within the scope of this project if they are necessary to install and integrate the new transformer into the existing system. 27-Jun-22 1
When was the last time the relays were tested and certified? Can the government provide us with a copy of that report?
16-Jun-22
The substation receives annual recurring maintenance. The substation is operational other than the transformer being inoperable. Replacements or upgrades to any ancillary systems (relays, controls, sensors, etc.) are only required within the scope of this project if they are necessary to install and integrate the transformer provided by the contractor 27-Jun-22 1
21 can the government provide a copy of the one line and three line drawing for the substation, including relays, switches, controls and alarms? A copy of the existing drawing in the substation on the wall would be helpful. 16-Jun-22 unknown at this time - scans of original as-built prints are all that are available 27-Jun-22 1
Is the government anticipating a base wide outage to replace the existing transformer, or will the project be conducted while the remainder of the site is an operation?
16-Jun-22
Contractor should plan power outages as efficiently as possible to keep base wide outage to a minimum. All work that can be performed with substation energized should be done as such. Outages should be scheduled 3 weeks in advance. 27-Jun-22 1
23 If the substation cannot be shut down during the replacement of the transformer, who at the base will provide authorization for working on live equipment in accordance with OSHA regulations? 16-Jun-22
Contractor shall provide expertise to operate within all codes and regulations.
Request power outages no less that 3 weeks in advance through the COR. Power outages must be kept to a minimum 27-Jun-22 1
24 The statement of work calls for safety and quality control to be performed by the contractor. Is the government anticipating a dedicated quality and dedicated safety person who do not perform any other function on the site? Or can these individuals perform construction activities along with their safety and or quality control activities? 16-Jun-22
A person can perform multiple roles as long as they are capable of and qualified to perform all roles which they are assigned. 27-Jun-22 1
25 Does the government have any drawings or submittal information for the existing transformer that we are replacing under this project? 16-Jun-22 unknown at this time - scans of original as-built prints are all that are available 27-Jun-22 1
26 The name plate on the existing transformer was difficult to read. Can the government provide information regarding the weight of this transformer, weight of the oil contained and volume of oil, and weight of the carcass and coil? 16-Jun-22 1,034 gallon transformer oil 27-Jun-22 1
27 In the process of performing this project will the base confer on the contractor the ability to escort subcontractors to the work area or will badges be required for all personnel regardless of the duration they are on the site? In particular what I am thinking about is the rigging contractor who will probably have multiple men on site for a single day 16-Jun-22
The contractor shall obtain badges for all prime and subcontractors working on the base. Escort by the customer will be used on a limited basis and the contractor shall plan and obtain base passes for future work. 27-Jun-22 1
Does the government anticipate professional engineer support for the contractors work on this project? If yes, does the engineer need to be licensed in the state of New Hampshire?
16-Jun-22 Added section 1.3.3 27-Jun-22 1
Does the base provide power to the grid through this substation? If yes, will we be required to interface with Eversource or ISO New England?
16-Jun-22
The grid provides power to the base. Overhead lines are live from the grid, so LOTO of the fuses and coordination with eversource may be required. Contractor to determine and coordinate prior to performing work. BCE Service desk can support with account specific questions. 27-Jun-22 1
30 if there are any utility back charges associated with this work will those charges be handled by the base or should the contractor include them in this project cost? If we should include these in our project cost can the base provide us with their customer service contact and phone number for us to ascertain what those costs might be? 16-Jun-22
Due to the short duration of the actual work PoP in this project, incidental utilities used while working on base will not be billed back to the contractor. Utilities may only be used in direct support of work within SOW. 27-Jun-22 1
Who will be responsible for operating the temporary generators while in operation? 16-Jun-22
Pease ANGB will coordinate all power outages with the contractor. Outages should be kept minimal 27-Jun-22 1
Can you provide dimensions of the gate opening for the substation so that we can determine if a crane can be placed adjacent to the Power Distribution building? 16-Jun-22
The crane will have to be operated from outside the substation fence. Location lf the crane to perform work can be discussed/coordinated once the contractor is on site. 27-Jun-22 1
33 Can you please cite drawing indicating where the existing leak containment subsurface structure is located? We do not want to place a crane on top of this and risk collapsing the structure. 16-Jun-22
The crane will have to be operated from outside the substation fence. Location lf the crane to perform work can be discussed/coordinated once the contractor is on site. 27-Jun-22 1
The statement of work indicates the project is planned for 120 days. Presently delivery of Transformers is running anywhere from one year to 18 months. Can the period of performance be extended? If the period of performance cannot be extended, can the government advised us of any manufacturers who can provide a transformer within the required timeframe? 16-Jun-22 see Amendment 001 27-Jun-22 1
35 Does the government anticipate that the work will occur during normal business hours or is off-hour’s construction required? 16-Jun-22 yes - normal business hours. Request can be made to work outside normal business hours in advance to the KO 27-Jun-22 1
Does the scope of this project include setting, calibrating or certifying the existing relays and controls? If this work is required does it need to be performed by a third party 16-Jun-22
If setting, calibrating or certifying the existing relays and controls is required to integrate the new transformer into the system to provide a fully operational system as required in the SoW, it will be the responsibility of the contractor to perform. 27-Jun-22 1
37 Is the limit of the contract scope include up to the transformer secondary circuit breaker in the switch gear or does the work include distribution Breakers in the switch gear as well? 16-Jun-22
Contractor will perform tasks required to integrate the new transformer into the substation to provide a fully operational system as required in the SoW. 27-Jun-22 1
38 Will the contractor be responsible for providing any temporary power to the base during system outages while replacing the transformer? If yes, can you provide load requirements on which we are to base the temporary generation?
Who will be responsible for fueling the temporary generators while in operation? 16-Jun-22
Contractor should plan power outages as efficiently as possible to keep downtime to a minimum. Outages should be scheduled 3 weeks in advance. Contractor will not be required to provide any temporary power. 27-Jun-22 1