This is a Request for Information (RFI) document containing two contractor inquiries and government responses regarding a gas meter replacement project at McConnell Air Force Base, Kansas.

The first question addresses Modbus addresses and equipment lead times, asking whether the Government will provide Modbus addresses immediately upon contract award to prevent manufacturing delays, given the 60-day period of performance. The Government responded that the Modbus address is "20" but did not directly confirm immediate provision. The second question requests clarification on whether the 60-day period of performance should commence after equipment delivery rather than award, given that the specified Sierra Instruments meter model (620S-BT-L04-M0-ENZ-24V-V3-DD-9-MB-M1) may have substantial factory lead times. The Government responded that the Notice to Proceed will be issued after performance payment bonds are received and all equipment and materials are delivered, taking lead times into consideration. This response indicates the Government recognizes potential lead time constraints but ties NTP issuance to delivery completion rather than extending the stated 60-day performance window. The underlying solicitation (W50S7X26Q0011) is a small business set-aside (100%) for removal and replacement of six gas meters on a firm fixed-price basis, with an organized site visit scheduled for 19 September 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionAnswer
1Modbus Addresses and Equipment Lead Time The Statement of Work (SW-3) states that coordination with CE will be required for providing the Modbus address to the factory prior to ordering. Since the Period of Performance is 60 days from the date of award, will the Modbus addresses be provided immediately upon award so as not to delay the manufacturing process?The Modbus address is 20
2Period of Performance (PoP) vs Factory Lead Times Given that the specified Sierra Instruments meters (620S-BT-L04-M0-ENZ-24V-V3-DD-9-MB-M1) may have factory lead times that could consume a significant portion of the 60-day PoP, would the Government consider issuing the Notice to Proceed (NTP) or starting the 60-day PoP after the equipment has been delivered to the site?The NTP will be issued after perfromance payment bonds and delivery of all equipment of materials considereding the lead times