QUESTIONS_AND_ANSWERS__4.doc.docx

DOCX document 12 KB Posted

Attached to
SECURITY REPLACEMNT CAMERA SYSTEM, BARNES BUILDING, BOSTON, MA Federal contract opportunity
Solicitation number
W15QKN-19-R-1050
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

About this file

QUESTIONS AND ANSWERS #4 ARE NOW ATTACHED

View the file

Other files for this federal contract opportunity

Other files attached to SECURITY REPLACEMNT CAMERA SYSTEM, BARNES BUILDING, BOSTON, MA, newest first.
File Type Posted
QUESTIONS_AND_ANSWERS_3.docx DOCX document
19-R-1050-0001.pdf PDF
Questions_and_Answers_2.docx DOCX document
QUESTIONS_AND_ANSWERS_1_SECURITY_CAMERAS.docx DOCX document
PRICE_WORKSHEET_16409_Security_Replacement.xlsx XLSX spreadsheet
Drawing_1.pdf PDF
SOLICITATION_W15QKN-19-R-1050_SECURITY_SYSTEM,_BOSTON.docx DOCX document
Drawing_3.pdf PDF
Drawing_4.pdf PDF
Drawing_2.pdf PDF
SOW_MA004-Boston-A04-CSS-16409-SOW-Emergency_Security_Replacement_without_tracked_changes_-_5.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS #4

Question#1 On the recent SOW section 11.5.18 states the following:

Contractor shall furnish and install approximately (5) rack mounted UPS systems to provide back up for all rack mounted video storage systems (VSS) equipment that shall allow the system to operate for 6 hours. The contractor shall verify UPS size based on all equipment associated with VSS in the site design.

UPS shall be located with NVR and POE equipment.

The line item entry on the price breakdown sheet states:

Uninterruptible power supply transformers, single phase 120 volt, .5KVA (which is 500watts.)

5KVA or 500 watts will not provide 6 hours of back up.

Answer #1: The Contractor needs to provide/install a power supply to meet the needs specified in the SOW - continued operation for 6 hours during a power outage. References to power sources in cost breakdown should be ignored.