Text version

Performance Requirements Summary

TECHNICAL EXHIBIT A

Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective (The Service required—usually a shall statement)

Standard
Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)

Method of Surveillance

PRS # 1.

Fire Extinguisher Annual Inspection & Maintenance in accordance with PWS Section 5.4.1 NFPA 10 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 2

Fire Sprinkler Annual Inspection & Maintenance in accordance with PWS Section 5.4.2 NFPA 25 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 3

Fire Alarm Annual Inspection & Maintenance in accordance with PWS Section 5.4.3 NFPA 72 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 4

Kitchen Fire Suppression Annual Inspection & Maintenance in accordance with PWS Section 5.4.4 NFPA 96 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 5

Fire Hydrant Annual Inspection & Maintenance in accordance with PWS Section 5.4.5 NFPA 25 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 6

Fire Suppression Water Storage Tanks Inspection & Maintenance in accordance with PWS Section 5.4.6 NFPA 25 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 7

Fire Pumps Inspection & Maintenance in accordance with PWS Section 5.4.7 NFPA 25 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 8

Hazardous Materials Storage Sheds Inspection & Maintenance in accordance with PWS Section 5.4.8 NFPA 17 – Latest Published Edition

100% Compliance
Review & verification of submitted report

PRS # 8

Hazardous Materials Storage Sheds Inspection & Maintenance in accordance with PWS Section 5.4.8 NFPA 25 – Latest Published Edition

100% Compliance
Review & verification of submitted report