VA797H-17-R-0015-00004001.docx

DOCX document 15 KB Posted

Attached to
St. Albans RFP VA797H-17-R-0015
Solicitation number
VA797H17R0015
Issued by

About this file

VA797H-17-R-0015 00004 VA797H-17-R-0015 - Corrections to April 24 questions and answers.docx

View the file

Other files

File Type Posted
36H79718C0010-000.docx DOCX document
VA797H-17-R-0015-00005000.docx DOCX document
VA797H-17-R-0015-00005001.pdf PDF
VA797H-17-R-0015-00004002.docx DOCX document
VA797H-17-R-0015-00004000.docx DOCX document
VA797H-17-R-0015-00003000.docx DOCX document
VA797H-17-R-0015-00002000.docx DOCX document
VA797H-17-R-0015-00001003.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

St. Albans corrections to answers:

QUESTION 5: If the answer is yes to questions (2), (3), or (4) can structural drawings of the roof and floor/foundation be supplied?

ANSWER CORRECTION: Contractor can supply structural drawings of the roof and floor/foundation along with calculations to support the drawings with their proposal. The VA has no drawings or any knowledge of what the roof and floor can handle. The contractor shall supply structural drawings to show that the equipment offered can be supported by the floor and roof.

VA will not supply structural drawings of the floor or roof.

QUESTION 22: Page 22 of 89 in the main solicitation, item 17. States, the textile facility will be closed during the project for no more than 90 days. The contractor will have 24-hour access to the laundry facility, seven days a week. Can you confirm there will be no laundry employees in the facility during that time?

ANSWER CORRECTION: During installation, there will be 7 to 10 laundry employees in the facility to receive linen.