VA255-17-R-0324-00002000.docx
DOCX document 23 KB Posted
- Solicitation number
- VA25517R0324
About this file
VA255-17-R-0324 00002 VA255-17-R-0324 00002.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| VA255-17-R-0324-00002001.pdf | ||
| VA255-17-R-0324-00001000.docx | DOCX document | |
| VA255-17-R-0324-005.pdf | ||
| VA255-17-R-0324-003.docx | DOCX document | |
| VA255-17-R-0324-004.pdf | ||
| VA255-17-R-0324-002.docx | DOCX document | |
| VA255-17-R-0324-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 00002 02-23-2018 657-17-110 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Leavenworth
KS
66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Leavenworth
KS
66048 To all Offerors/Bidders
VA255-17-R-0324
01-11-2018
X X X
03/09/2018 2:00 PM CST
657-17-110, Correct Annual Workplace Findings Over One Year Old
The purpose of this amendment is to provide answers to questions submitted.
1. Questions submitted and the answers are provided below.
2. The attedance sheet for the site visit is attached.
3. The closing date for this solicitation is extended to 09 March, 2018 at 2:00 pm CST.
Kevin Knight Fall Protection Project #657-17-110 Pre-Bid RFI’s
1. Can you give us the heights of all buildings that require fall protection? (R02, R03, R08, R09, R12, R21, R23, R26, R28, R29, R30, and R32).
· Any existing drawings the VA has will be made available to the successful offeror. This is a design-build contract.
2. Can you give us the heights of all abutting buildings? This will determine the fall distance from each roof. This is critical when provided fall protection.
· Any existing drawings the VA has will be made available to the successful offeror. This is a design-build contract.
3. Can you give us the structure of each roof? Concrete/Steel, if concrete how thick, if steel we will need the as-built structural drawing, and roofing insulation thickness (overall). This is critical when determining the attachments and height and type of anchors.
· Any existing drawings the VA has will be made available to the successful offeror. This is a design-build contract.
4. Confirmation of working hours – regular or after hours?
· Normal working hours. Restrictions to building egress and or parking during construction activities may require off-hour work.
5. Drawings indicate guardrail. Should the guardrail consist of two-line pipe rail with kick plate?
· The contractor should refer to OSHA regulations when determining the guardrail. This is a design-build contract and design decisions such as this will be made in conjunction with the VA throughout the process.
6. Can the hand rail be side mounted or top mounted to parapet?
· This is a design-build contract and design decisions such as this will be made in conjunction with the VA throughout the process. Aesthetics will be a consideration as part of this process.
7. Does it matter how the handrail is mounted as long as it meets designed for load purposes?
· This is a design-build contract and design decisions such as this will be made in conjunction with the VA throughout the process. Aesthetics will be a consideration as part of this process.
8. Will you be providing drawings of existing structure where handrail is being installed?
· No. It is the responsibility of the 3rd Party engineer to take the 35% drawings and bring them to 100%. He or she will determine where the handrails will go.
9. What is the material for guardrail, ladders, and stairs that they should be fabricated from and finish.... galvanized or painted steel, aluminum, or stainless rail?
· The fall protection engineer will determine this. This is why these drawings are 35% drawings. This is a design-build contract.
10. Will any of the access ladders require fall protection hardware i.e. ladder safety rail, trolley for safety harness?
· The fall protection engineer will determine this. This is why these drawings are 35% drawings. This is a design-build contract. The intent is to have OSHA compliant roofs upon project completion so that routine maintenance may take place safely.
11. Will all work take place the spring and summer of 2018?
· This is dependent on the actual award date and period of performance in the Contract.
12. Page 3 of Bid Package states that Performance Period is 210 days, Specification section 00 11 21 – 1.2 D states 180 days. Please confirm which is correct.
· 1.2 D states that the anticipated completion is 180 days. Therefore, this may be subject to change.
13. The project Statement of Work “Project Scope Description” including Plans “Proposed Safety Considerations” identify the following items as the intended rooftop safety components to be installed. (New Individual Anchor Points, New Warning Line System, & New Guardrail System). During the Pre-Proposal conference protentional bidders were shown a roof top safety system that did not seem to be similar to any of the aforementioned items. The system shown during the conference consisted of multiple structural anchor points in conjunction with a continuous cable anchoring system. This system would allow rooftop maintenance personal to transverse the entire rooftop while being 100% tied off. The list of components identified in the plans / specs would allow for maintenance personal to transverse the rooftop without being tied off, also giving the ability to tie off at specific identified locations. As we have outlined the differences between the proposed systems and the system shown at the conference, please clarify the below questions:
a. Is the intent to have Maintenance personnel 100% tied off on the roof at all times, or have the ability to freely transverse the roof and only tie off once reaching the equipment needing repair?
· Anyone who is on the roof should be tied off at all times. The fall protection engineer will determine this. This is why these drawings are 35% drawings. This is a design-build contract. The intent is to have OSHA compliant roofs upon project completion so that routine maintenance may take place safely.
b. If the ability to freely transverse the roof is the intent, the safety cabling system would be redundant and not required. Is the design intent to have redundant systems?
· The fall protection engineer will determine this. This is why these drawings are 35% drawings. The intent is to have OSHA compliant roofs upon project completion so that routine maintenance may take place safely.
c. If 100% tie off is desired it would also be redundant to have the Warning Line System, and individual anchor point locations. Would the redundant systems still be desired / required in this instance?
· The fall protection engineer will determine this. This is why these drawings are 35% drawings. This is a design-build contract.
d. Is the Warning Line system shown an item that is to be turned over to the owner for future use or just shown for use during construction? In the event the Warning Line System is utilized and is for owner’s future usage, is it intended to be a permanent / fixed or portable system?
· The fall protection engineer will determine this. This is why these drawings are 35% drawings. This is a design-build contract.
e. Two different types of rooftop safety railings were identified during the conference site walk. First being a portable ballasted system, the other being a permanent / roof penetrating system (See attached photos). Which type system is intended?
· Permanent safety railings. The fall protection engineer will determine this. This is why these drawings are 35% bridging documents for use by a design-build contractor. 100% plans and specifications are to be completed as part of the scope of work.
14. Schematic Design Plan 1-GS-108 has a legend indicating “hatched” sections which need fall protection, however there are numerous roofs that have notes calling for fall protection that do not bear the hatch shown in the legend. Please clarify if both hatched and unhatched areas are to receive fall protect per the plan callouts, and clarify if the hatched areas has any other special relevance to the project?
· Please read the Legend notes on the drawings. They indicate which roofs will be needing fall protection installed. Roofs needing fall protection are listed below.
· JB – Building 1 Roof
· JB – Building 18 Roof
· JB – Building 23 Roof
· JB – Building 24 Roof
· JB – Building 51 Roof
· JB – Building 52 Roof
· JB – Building 53 Roof
· JB – Building 53T Roof
· JB – Building 60 Roof
· JB – Building 60T Roof
· JC – Building 1 – Roof 2
· JC – Building 1 – Roof 3
· JC – Building 1 – Roof 8
· JC – Building 1 – Roof 9
· JC – Building 1 – Roof 11
· JC – Building 1 – Roof 12
· JC – Building 1 – Roof 21
· JC – Building 1 – Roof 23
· JC – Building 1 – Roof 26
· JC – Building 1 – Roof 28
· JC – Building 1 – Roof 29
· JC – Building 1 – Roof 30
· JC – Building 1 – Roof 32
· JC – Building 1 – Roof 38
· JC – Building 2 Roof
· JC – Building 3 Roof
· JC – Building 4 Roof
· JC – Building 14 Roof
15. Will the VA provide additional plans, such as structural or elevations drawing for JC and JB sites.
· VA will provide what drawings are available to the successful offeror.
16. We would like to request an additional site walk thru for the opportunity to investigate the general and local conditions which can affect the work or its cost in accordance with 52.236-3 Site Investigation and Conditions Affecting the Work.
· No additional site visit is authorized.
17. After reviewing the scopes in the RFP for this project I am wondering if there might be an error in Factor 4 – Technical Qualifications of Proposed Design Firm (Page 51 of 67). This factor is asking only for a Civil Engineer resume, but the based on the scopes I would assume that you are wanting a Architectural & Structural Engineer Resume as well. Can you please clarify?
· No. A licensed Civil Engineer is the minimum requirement for the state of Missouri. Missouri does not individually license structural engineers. Licensed Civil Engineers in Missouri are licensed as a Professional Engineer and Structural falls within the Civil discipline.
A.1 List of Attachments
See attached document: 657-17-110 - Pre-Bid Site Visit Sign-In Sheet.