FINAL Amendment 4 -Clarification - Questions Answers

View the file

Other files

File Type Posted
Amdment3coverpageTIRNO12R00004.doc DOC document
Amdment2coverpageTIRNO12R00004.doc DOC document
Amendment 2 -correct page 77todeletesentenceL.8.doc DOC document
Question AnswersolicPART2.doc DOC document
TIRNO12R00004 1 .rtf RTF text file
Middleware Performance Based Work Statement - jan62012ED-QUI-corre.doc DOC document
Questions Answers for solicitation TIRNO12R00004Middleware IT OperationJan6.doc DOC document
ITAMS Tickets 1-2-08052011.rtf RTF text file
Middleware Performance Based Work Statement - 101711-Ed-KISAM.doc DOC document
FINAL RFQ Cover Letter middleware2011.doc DOC document
Section 508 Determinationrtx.rtf RTF text file
TIRNO12R00004 1 .rtf RTF text file
hspd_12_piv_procedures_manual-July262011.rtf RTF text file
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FINAL AMENDMENT

Amendment 4

TIRNO-12-R-00004

1.

AMENDMENT RFP ISSUE DATE:

January 20, 2012 2.

ISSUED BY:

Department of Treasury

Internal Revenue Service

ATTN: Laquisha Levy

Constellation Centre (OS:A:P:I:D:B)

6009 Oxon Hill Road

Oxon Hill, MD 20745

3.

FOR INFORMATION CONTACT:

NAME:

Laquisha Levy, Contract Specialist

PHONE:

(202) 283-6838 EMAIL: laquisha.l.levy@irs.gov

FAX:

(202) 283-1290

4. PROPOSAL DUE DATE/TIME: REVISED

Proposals are due by 3pm EST, Tuesday, January 24, 2012.

PAST PERFORMANCE DUE DATE/TIME: REVISED

Past Performance Questionnaires are due by 12pm EST Friday, January 13, 2012

5.

AMENDMENT: The solicitation has been amended to provide clarification.

QUESTIONS

1. Number of resources working on each technology ( MQ Series, WebSphere Application Server, WebMethods, CA siteMinder & eTrust, Business Objects and Informatica)

ANSWER: Please refer to the response to question 50 of Amendment 1 posted on January 6, 2012.

2. Is the Program Manager required to work at on site? If yes, how many hours per week?

ANSWER: The Program Manager job is a full time on site job.