T2924 Final State Supplied Price Sheet 10.30.25~4.xlsx
XLSX spreadsheet 383 KB Posted
- Attached to
- Contract RFP/SC-SBE NJ|24-GNSV1-122684
- Contract number
- 24-GNSV1-122684
- Issued by
- New Jersey
About this file
This is a State-Supplied Price Sheet for Bid Solicitation #23DPP00860 issued by the New Jersey Department of Transportation (NJDOT) for snow plowing services organized by geographic maintenance areas. The solicitation is designated as T2924 and requires bidders to submit unit pricing for services across three regional divisions: North Region, Central Region, and South Region.
The contract encompasses snow plowing and related maintenance services across 13 maintenance areas throughout New Jersey, with pricing required for two service categories per area: truck and snow plowing equipment hourly rates and truck-only hourly rates. For each service category, bidders must provide all-inclusive hourly rates for snow plowing supervisors (capped at 30 percent of the plowing rate) and standby rates (set at 50 percent of the plowing rate). The maintenance areas range from 14 to 21 trucks required per area, organized into teams of seven trucks each. Specific maintenance areas include Area 24 (Columbia, Port Colden, Yellow Frame, Netcong) requiring 21 trucks in the North Region; Areas 33 through 38 in the Central Region; and Areas 43 through 47 in the South Region, each requiring 14 trucks. The price sheet contains 84 line items total, with all pricing calculations to be completed automatically once unit prices are provided by the bidder in the designated highlighted cells.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATTACHMENT 5 Northern Regional Road Coverage by Area.xlsx | XLSX spreadsheet | |
| JK Toro_OandA Redacted.pdf | ||
| ATTACHMENT 7 Southern Regional Road Coverge by AREA.xlsx | XLSX spreadsheet | |
| SST & Cs 2.8.2024 SIGNATURE BLOCK~1.pdf | ||
| T2924 Bid Amendment 1 ~1.docx | DOCX document | |
| ATTACHMENT 6 Central Regional Road Coverage by Area~2.xlsx | XLSX spreadsheet | |
| T2924 Bid Amendment 2 5.28.2024~1.docx | DOCX document | |
| T2924 Final Bid Solicitation 10.30.25~4.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
State-Supplied Price Sheet Bid Solicitation #23DPP00860 T2924: Snow Plowing Services by Area - NJDOT Bidder Name:
| Instructions: | Refer to Bid Solicitation Section 3.21 for Bidder instructions. The Bidder must provide Unit Pricing in the highlighted cells below. The rest will calculate automatically. | ||
| Line No | Commodity-Service Description | Unit | Unit Price |
| NORTH REGION | |||
| 1 | MAINTENANCE AREA 24: COLUMBIA, PORT COLDEN, YELLOW FRAME, NETCONG |
NUMBER OF TRUCKS REQUIRED: 21 (3 Teams of 7 trucks)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 2 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 24 - Not to exceed 30% of the Plowing Rate listed on price line 1 | HOUR |
| 3 | All-Inclusive Hourly Rate - Standby for Area 24 - 50% of the Plowing Rate |
4 MAINTENANCE AREA 24: COLUMBIA, PORT COLDEN, YELLOW FRAME, NETCONG
NUMBER OF TRUCKS REQUIRED: 21 (3 Teams of 7 trucks)
NUMBER OF TEAMS REQUIRED FOR AREA 24: 3
TRUCK ONLY
| HOURLY - Per Truck | ||
| 5 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 24 - Not to exceed 30% of the Plowing Rate listed on price line 4 | HOUR |
| 6 | All-Inclusive Hourly Rate - Standby for Area 24 - 50% of the Plowing Rate |
7 MAINTENANCE AREA 25: SUMMIT, ELIZABETH, NEWARK
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 8 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 25 - Not to exceed 30% of the Plowing Rate listed on price line 7 | HOUR |
| 9 | All-Inclusive Hourly Rate - Standby for Area 25 - 50% of the Plowing Rate |
10 MAINTENANCE AREA 25: SUMMIT, ELIZABETH, NEWARK
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 11 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 25 - Not to exceed 30% of the Plowing Rate listed on price line 10 | HOUR |
| 12 | All-Inclusive Hourly Rate - Standby for Area 25 - 50% of the Plowing Rate |
13 MAINTENANCE AREA 26: RAMSEY, FORT LEE, LODI, SEACAUCUS, JERSEY CITY
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 14 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 26 - Not to exceed 30% of the Plowing Rate listed on price line 16 | HOUR |
| 15 | All-Inclusive Hourly Rate - Standby for Area 26 - 50% of the Plowing Rate |
16 MAINTENANCE AREA 26: RAMSEY, FORT LEE, LODI, SEACAUCUS, JERSEY CITY
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 17 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 26 - Not to exceed 30% of the Plowing Rate listed on price line 13 | HOUR |
| 18 | All-Inclusive Hourly Rate - Standby for Area 26 - 50% of the Plowing Rate |
19 MAINTENANCE AREA 27: PATERSON, TOTOWA, WEST ORANGE, HANOVER
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 20 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 27 - Not to exceed 30% of the Plowing Rate listed on price line 19 | HOUR |
| 21 | All-Inclusive Hourly Rate - Standby for Area 27 - 50% of the Plowing Rate |
22 MAINTENANCE AREA 27: PATERSON, TOTOWA, WEST ORANGE, HANOVER
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 23 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 27 - Not to exceed 30% of the Plowing Rate listed on price line 22 | HOUR |
| 24 | All-Inclusive Hourly Rate - Standby for Area 27 - 50% of the Plowing Rate |
25 MAINTENANCE AREA 28: RIVERDALE, ROCKAWAY, BRANCHVILLE, SUSSEX
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 26 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 28 - Not to exceed 30% of the Plowing Rate listed on price line 25 | HOUR |
| 27 | All-Inclusive Hourly Rate - Standby for Area 28 - 50% of the Plowing Rate |
28 MAINTENANCE AREA 28: RIVERDALE, ROCKAWAY, BRANCHVILLE, SUSSEX
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 29 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 28 - Not to exceed 30% of the Plowing Rate listed on price line 28 | HOUR |
| 30 | All-Inclusive Hourly Rate - Standby for Area 28 - 50% of the Plowing Rate |
| CENTRAL REGION | |
| 31 | MAINTENANCE AREA 33: SAND HILL, COLLEGE FARM, SAYREVILLE, KEASBEY |
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 32 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 33 - Not to exceed 30% of the Plowing Rate listed on price line 31 | HOUR |
| 33 | All-Inclusive Hourly Rate - Standby for Area 33 - 50% of the Plowing Rate |
34 MAINTENANCE AREA 33: SAND HILL, COLLEGE FARM, SAYREVILLE, KEASBEY
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 35 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 33 - Not to exceed 30% of the Plowing Rate listed on price line 34 | HOUR |
| 36 | All-Inclusive Hourly Rate - Standby for Area 33 - 50% of the Plowing Rate |
37 MAINTENANCE AREA 34: WALL TOWNSHIP, LAKEWOOD, TOMS RIVER, MANAHAWKIN
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 38 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 34 - Not to exceed 30% of the Plowing Rate listed on price line 37 | HOUR |
| 39 | All-Inclusive Hourly Rate - Standby for Area 34 - 50% of the Plowing Rate |
40 MAINTENANCE AREA 34: WALL TOWNSHIP, LAKEWOOD, TOMS RIVER, MANAHAWKIN
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 41 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 34 - Not to exceed 30% of the Plowing Rate listed on price line 40 | HOUR |
| 42 | All-Inclusive Hourly Rate - Standby for Area 34 - 50% of the Plowing Rate |
43 MAINTENANCE AREA 35: WEST TRENTON, LAWRENCE, HAMILTON, WEST AMWELL
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 44 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 35 - Not to exceed 30% of the Plowing Rate listed on price line 43 | HOUR |
| 45 | All-Inclusive Hourly Rate - Standby for Area 35 - 50% of the Plowing Rate |
46 MAINTENANCE AREA 35: WEST TRENTON, LAWRENCE, HAMILTON, WEST AMWELL
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 47 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 35 - Not to exceed 30% of the Plowing Rate listed on price line 46 | HOUR |
| 48 | All-Inclusive Hourly Rate - Standby for Area 35 - 50% of the Plowing Rate |
49 MAINTENANCE AREA 36: FLEMINGTON, BRIDGEWATER, BLOOMSBURY, CLINTON, BEDMINSTER
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 50 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 36 - Not to exceed 30% of the Plowing Rate listed on price line 49 | HOUR |
| 51 | All-Inclusive Hourly Rate - Standby for Area 36 - 50% of the Plowing Rate |
52 MAINTENANCE AREA 36: FLEMINGTON, BRIDGEWATER, BLOOMSBURY, CLINTON, BEDMINSTER
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7 trucks)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 53 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 36 - Not to exceed 30% of the Plowing Rate listed on price line 52 | HOUR |
| 54 | All-Inclusive Hourly Rate - Standby for Area 36 - 50% of the Plowing Rate |
55 MAINTENANCE AREA 38: HAZLET, FREEHOLD, OCEAN, WASHINGTON TOWNSHIP
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 56 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 38 - Not to exceed 30% of the Plowing Rate listed on price line 55 | HOUR |
| 57 | All-Inclusive Hourly Rate - Standby for Area 38 - 50% of the Plowing Rate |
58 MAINTENANCE AREA 38: HAZLET, FREEHOLD, OCEAN, WASHINGTON TOWNSHIP
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 59 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 38 - Not to exceed 30% of the Plowing Rate listed on price line 58 | HOUR |
| 60 | All-Inclusive Hourly Rate - Standby for Area 38 - 50% of the Plowing Rate |
| SOUTH REGION | |
| 61 | MAINTENANCE AREA 43: PENNSAUKEN, CHERRY HILL, WEST DEPTFORD, DEPTFORD, BORDENTOWN |
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 62 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 43 - Not to exceed 30% of the Plowing Rate listed on price line 61 | HOUR |
| 63 | All-Inclusive Hourly Rate - Standby for Area 43 - 50% of the Plowing Rate |
64 MAINTENANCE AREA 43: PENNSAUKEN, CHERRY HILL, WEST DEPTFORD, DEPTFORD, BORDENTOWN NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 65 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 43 - Not to exceed 30% of the Plowing Rate listed on price line 64 | HOUR |
| 66 | All-Inclusive Hourly Rate - Standby for Area 43 - 50% of the Plowing Rate |
67 MAINTENANCE AREA 44: ELMER, BUENA, RED LION, MOUNT LAUREL
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 68 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 44 - Not to exceed 30% of the Plowing Rate listed on price line 67 | HOUR |
| 69 | All-Inclusive Hourly Rate - Standby for Area 44 - 50% of the Plowing Rate |
70 MAINTENANCE AREA 44: ELMER, BUENA, RED LION, MOUNT LAUREL
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 71 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 44 - Not to exceed 30% of the Plowing Rate listed on price line 70 | HOUR |
| 72 | All-Inclusive Hourly Rate - Standby for Area 44 - 50% of the Plowing Rate |
73 MAINTENANCE AREA 45: BRIDGEPORT, GLASSBORO, DEEPWATER
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 74 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 45 - Not to exceed 30% of the Plowing Rate listed on price line 73 | HOUR |
| 75 | All-Inclusive Hourly Rate - Standby for Area 45 - 50% of the Plowing Rate |
76 MAINTENANCE AREA 45: BRIDGEPORT, GLASSBORO, DEEPWATER
NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 77 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 45 - Not to exceed 30% of the Plowing Rate listed on price line 76 | HOUR |
| 78 | All-Inclusive Hourly Rate - Standby for Area 45 - 50% of the Plowing Rate |
79 MAINTENANCE AREA 47: BERLIN, POMONA, CUMBERLAND, MIDDLE TOWNSHIP, MAYS LANDING NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK AND SNOW PLOWING EQUIPMENT
| HOURLY - Per Truck | ||
| 80 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 47 - Not to exceed 30% of the Plowing Rate listed on price line 79 | HOUR |
| 81 | All-Inclusive Hourly Rate - Standby for Area 47 - 50% of the Plowing Rate |
82 MAINTENANCE AREA 47: BERLIN, POMONA, CUMBERLAND, MIDDLE TOWNSHIP, MAYS LANDING NUMBER OF TRUCKS REQUIRED: 14 (2 Teams of 7)
TRUCK ONLY
| HOURLY - Per Truck | ||
| 83 | All-Inclusive Hourly Rate - Snow Plowing Supervisor for Area 47 - Not to exceed 30% of the Plowing Rate listed on price line 82 | HOUR |
| 84 | All-Inclusive Hourly Rate - Standby for Area 47 - 50% of the Plowing Rate |
Sheet2
File details come from the government source that posted it. Updated .