This is a bid proposal for Delaware Department of Transportation (DelDOT) Contract T202466302 for the Adams Street Pathway Phase II project, a federally-assisted construction project located in New Castle County, Wilmington, Delaware. The project consists of furnishing all labor and materials to develop a shared use pathway and ADA improvements along Adams Street from 6th Street to the Riverfront. Bids are due November 17, 2026, prior to 2:00 p.m. local time, with submission via internet through bidx.com/de or paper bid delivery to the DelDOT Administration Building, 800 Bay Road, Dover, Delaware. No pre-bid meeting is scheduled. All work must be completed within 229 calendar days, with an estimated Notice to Proceed on or about March 1, 2027. Bids will be publicly opened and read aloud at the stated address, with call-in access available at (302) 504-8986, access code 651 529 280#.
The project is funded under Federal Aid Project No. CRP-2024(19), CFDA 20.205, and is subject to Buy America requirements and domestic material specifications. There is no Disadvantaged Business Enterprise (DBE) goal established, as all DelDOT DBEs were decertified effective September 30, 2025, pending recertification. Bidders must provide a surety bond or security equal to at least 10% of the bid amount, register with DelDOT, comply with Delaware's Contractor Registration Act, and submit a mandatory drug testing affidavit. No retainage will be withheld unless applied through the Performance-Based Rating System. Road User Costs (RUC) penalties apply for failure to reopen lanes on schedule, with varying rates for different roadways ranging from $10 to $5,200 per 15-minute increment. Contractors must provide an ACI or NRMCA certified concrete flatwork technician and comply with prevailing wage requirements, including flagger wages at minimum equal to laborer wage rates. The project is governed by Delaware's Standard Specifications for Road and Bridge Construction, January 2026, and revised inspection framework requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF DELAWARE
DEPARTMENT OF TRANSPORTATION
BID PROPOSAL
CONTRACT T202466302
ADAMS STREET PATHWAY PHASE II
Federal Aid No. CRP-2024(19)
CFDA: 20.205
Advertisement Date: October 19, 2026
INCLUDED IN THIS DOCUMENT: ADDITIONAL BID PROPOSAL ITEMS:
BID PROPOSAL:
GENERAL DESCRIPTION
PROSPECTIVE BIDDERS NOTES
GENERAL NOTICES
PREVAILING WAGES
SPECIAL PROVISIONS
STATEMENTS
QUANTITY SHEET SUMMARY
ATTACHED OR POSTED DOCUMENTS:
PROJECT PLANS
QUESTIONS & ANSWERS (if posted)
BIDDERS LIST
PAPER BIDDERS CONTACT DELDOT
FOR BID SUBMITTAL DOCUMENTS:
DRUG TESTING AFFIDAVIT
CERTIFICATION FORM
BID BOND FORM
CD FOR BID PRICE ENTRY & PRINTING
BIDDERS LIST
This Bid Proposal and related documents can be viewed on bids.delaware.gov and bidx.com/de/
Internet Bids for Bidders with Bid Express® accounts can be submitted at BIDX.com/de; OR;
Paper Bids with CD will be received in the Bidder's Room at the DelDOT Administration Building, Dover, DE;
ALL BIDS DUE PRIOR TO 2:00 P.M. Local Time, NOVEMBER 17, 2026 https://bids.delaware.gov/ https://bidx.com/de/main
Contract No. T202466302
DIGITAL ACCESSIBILITY NOTICE
The Delaware Department of Transportation (DelDOT) is committed to ensuring that its digital services, content, and documents are accessible to all users and is actively working to comply with applicable federal and state accessibility requirements. DelDOT continues to make improvements over time, with current efforts focused on programs, applications, content, and documents that are actively in use and available to the public.
Due to the nature and complexity of certain materials, including construction plans, technical drawings, historical documents, maps, and other graphic-intensive files, some documents may not currently be fully digitally accessible or compliant with current accessibility standards. In some cases, these documents are provided for historical, reference, informational, or procurement purposes only.
If you require an accessible version of a document or need assistance accessing any content, please contact DelDOT at (302) 760-2031 or DOT.ask@delaware.gov, and reasonable efforts will be made to provide the information in an accessible format upon request. DelDOT appreciates your patience and understanding as accessibility improvements continue to be implemented.
Adams Street Pathway Phase II Federal Aid Project No. CRP-2024(19)
GENERAL DESCRIPTION
A. BIDS DUE: NOVEMBER 17, 2026 PRIOR TO 2:00 P.M. Local Time – unless changed via Addendum.
BIDS MUST BE SUBMITTED VIA:
(a) Internet - Bidders with DelDOT Bid Express® accounts can submit bids at bidx.com/de/.
OR:
(b) Paper Bid Delivered To: Delaware Department of Transportation (DelDOT), Administration Building
North Entrance, Bidders Room, 800 Bay Road, Dover, DE 19901
For paper bids, contact DelDOT at dot-ask@delaware.gov or (302) 760-2031 to request a CD for bidding, required forms, and instructions. Bidders enter their Bid Item prices onto the supplied CD then print the form and deliver in a sealed envelope; the Bid Form, completed CD, and required documents prior to the Bid due date and time.
(CD’s cannot be used to submit bids to bidx.com)
Do not submit both Internet and Paper Bids. If so, the Internet bid and documents will be rejected.
BID OPENING: Bids will be publicly opened and read aloud at the Date and Time of the Bid Opening. The Bid
Opening will be held at the ‘Paper Bid Delivered To’ address shown above. Bidder bears the risk of late delivery, bids received after the stated time will be returned unopened.
Attendance is not required. DelDOT offers a call-in number to hear the Bid Opening telephonically.
The telephone number to call is (302) 504-8986.
When prompted, enter Meeting number (access code): 651 529 280#
It is anticipated the telephone access information will remain the same for all Bid Openings.
B. PRE-BID MEETING: No
C. DBE GOAL: 0% Disadvantaged Business Enterprise Goal.
Pursuant to the Interim Final Rule (“IFR”) issued by the United States Department of Transportation (“U.S. DOT”) on September 30, 2025, this letting does not have a DBE participation goal as all DelDOT DBEs were decertified by the IFR. DelDOT is undertaking the recertification process for DBEs pursuant to the IFR requirements. As
DelDOT currently has no certified DBEs, it is not feasible to impose or enforce a DBE participation goal for this letting. Upon completion of DelDOT’s DBE recertification process, or upon any modification of the IFR, whether through amendment, clarification, or judicial action, DelDOT reserves the right to revise or reestablish a DBE participation goal for this letting as may be directed by the U.S. DOT and in accordance with applicable federal regulations.
D. OJT TRAINEES: n/a
E. LOCATION: New Castle County
These improvements are more specifically shown on the Location Map(s) of the attached Plans.
F. DESCRIPTION: The improvements consist of furnishing all labor and materials for the proposed work which will include the development of a shared use pathway and ADA improvements within the City of Wilmington along Adams
Street from 6th Street to the Riverfront. Follow other incidental construction in accordance with the location, notes and details shown on the plans, and as directed by the Engineer.
G. BUY AMERICA REQUIREMENTS APPLY – Build America, Buy America Act, refer to ‘GENERAL NOTICES’.
H. COMPLETION TIME: All work on this contract must be complete within 229 Calendar Days.
Extensions of contract time due to weather are specified in the Standard Specifications Section 108.7F, weather days.
It is estimated a Notice to Proceed is issued such that work starts on or about March 1, 2027.
mailto:dot-ask@delaware.gov
I. SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION, DELAWARE DEPARTMENT OF
TRANSPORTATION, JANUARY 2026 apply to this Bid Proposal and Project. The Contractor shall make himself aware of any revisions and corrections and apply them to the applicable item(s) of this contract. The Standard
Specifications can be viewed here. Units of Measure can be found at 101.4.
J. ATTACHMENTS: Included as part of this Bid Proposal are; Project Plans; Questions & Answers (if posted);
Addenda, Referenced Documents, Documents Posted with this Bid Proposal; and Bid documents mailed to contractors.
K. ADDENDA: All Addenda are posted on the internet at bids.delaware.gov, and bidx.com/de/ and are included as part of the Bid Proposal. The Bidder is responsible to check the Website as needed to ensure that the Bidder is aware of
Addenda that are included in the Bid Proposal. If Addenda are issued, the final Addendum will be posted no later than the end of the day two business days prior to the bid date. Each Addendum number and issue date must be entered on the submitted Certification Form. This original Bid Proposal will not be updated, you must refer to each Addendum.
L. QUESTIONS: E-MAIL TO; dot-ask@delaware.gov
Questions regarding this project are to be e-mailed to the above address no less than six business days prior to the bid opening date in order to receive a posted response. Please include the Contract number in the subject line. Questions and responses are posted at bids.delaware.gov, and bidx.com/de/. The date of the final posted Questions and Answers document must be entered on the submitted Certification Form.
M. ROAD USER COSTS:
FAILURE TO OPEN PROJECT TO UNRESTRICTED HIGHWAY TRAFFIC ON TIME
Late Opening of Temporary Lane Closures
Interim Road User Costs (RUC) for delays in opening lanes will be assessed according to the below charts. Refer to the Allowable Lane Closure matrix in the Maintenance of Traffic (MOT) plans for start and end times of allowable lane closures.
Table 1
Adams Street
(Monday through Friday)
Contractor Penalties for Failure to Reopen Lanes
Time All Lanes Reopened
("Verizon Time") Single Lane Closure
1st 15-minute increment $20
2nd 15-minute increment $40
3rd 15-minute increment $60
4th 15-minute increment $80
5th 15-minute increment $95
6th 15-minute increment $110
7th 15-minute increment $125
8th 15-minute increment $140
*After the first two hours beyond the allowable lane closure hour limit, RUC will accrue at $15 per 15 min, up to a day total of $260. The RUC values within the chart are not cumulative, payments made after the first two hours are.
remainder of page is blank http://www.deldot.gov/Publications/manuals/standard_specifications/index.shtml https://bids.delaware.gov/ https://bidx.com/de/main mailto:%20dot-ask@delaware.gov https://bids.delaware.gov/
Table 2
Northbound I-95 Off Ramp/Adams Street and Maryland Avenue
(Monday through Friday)
Contractor Penalties for Failure to Reopen Lanes
Time All Lanes Reopened
("Verizon Time") Single Lane Closure
1st 15-minute increment $700
2nd 15-minute increment $1,400
3rd 15-minute increment $2,100
4th 15-minute increment $2,800
5th 15-minute increment $3,400
6th 15-minute increment $4,000
7th 15-minute increment $4,600
8th 15-minute increment $5,200
*After the first two hours beyond the allowable lane closure hour limit, RUC will accrue at $500 per 15 min, up to a day total of $9,200. The RUC values within the chart are not cumulative, payments made after the first two hours are.
Table 3
Jackson Street
(Monday through Friday)
Contractor Penalties for Failure to Reopen Lanes
Time All Lanes Reopened
("Verizon Time") Road Closure
1st 15-minute increment $10
2nd 15-minute increment $20
3rd 15-minute increment $30
4th 15-minute increment $40
5th 15-minute increment $50
6th 15-minute increment $60
7th 15-minute increment $70
8th 15-minute increment $80
*After the first two hours beyond the allowable lane closure hour limit, RUC will accrue at $10 per 15 min, up to a day total of $160. The RUC values within the chart are not cumulative, payments made after the first two hours are.
Examples of calculations for assessment of Road User Cost:
For the use of both examples, the lane closure matrix on the MOT plans will have a lane open time of 7:00 AM.
1) Failure to reopen Adams Street until 7:35 AM, during the 3rd 15-minute increment, local time:
Per Table 1, a RUC of $60.00 will be assessed.
2) Failure to reopen Adams Street until 9:35 AM, during the 11th 15-minute increment, local time:
Per Table 1:
$140 for the first two hour period
9:00 AM to 9:35 AM = $15 x (3) 15min increments = $45
A RUC of $185 will be assessed.
A RUC of $390 will be assessed for each calendar day 3rd Street from Jackson Street to Adams Street is not fully opened to traffic in excess of the allowable closure duration identified in the Plans. The full daily RUC is assessed regardless of what time of day the road is reopened, starting at 12:00 AM. As such, no consideration will be given for partial calendar days.
A RUC of $50 will be assessed for each calendar day Carpenter Street from Adams Street to Monroe Street is not fully opened to traffic in excess of the allowable closure duration identified in the Plans. The full daily RUC is assessed regardless of what time of day the road is reopened, starting at 12:00 AM. As such, no consideration will be given for partial calendar days.
A RUC of $50 will be assessed for each calendar day 5th Street from Adams Street to Monroe Street is not fully opened to traffic in excess of the allowable closure duration identified in the Plans. The full daily RUC is assessed regardless of what time of day the road is reopened, starting at 12:00 AM. As such, no consideration will be given for partial calendar days.
Example of calculation for assessment of Road User Cost:
The duration of the detour according to the Plans is 65 calendar days. If the 3rd Street is reopened at 1:05 AM on day
66, the full amount of the $390 RUC will be assessed.
Assessment of the RUC will be made through Item 763525 – Road User Cost. The engineer will be the sole approving authority as to when the project is complete after traffic is returned to the ultimate alignment and when the contractors work activities will permit highway traffic ultimate lane width and shoulder widths.
N. FLAGGERS:
A. Included in the Bid Proposal are the prevailing wages for highway construction as determined by the Department of Labor of the State of Delaware in accordance with Title 29 Del. C. §6960, relating to wages and the regulations implementing that Section.
B. Flaggers must be bid at a minimum equal to the Laborer wage rate and may be bid up to, but not to exceed, 3 times the Laborer wage rate in accordance with the County where the Work is being performed.
C. Flagger overtime must be bid at minimum of 1.45 times, and may be bid up to a maximum of 4.35 times, the Laborer wage rate in accordance with the County where the Work is being performed.
D. When a Contract for a Project contains both Federal Davis-Bacon and State of Delaware prevailing wage standards, the employer’s minimum wage obligations are determined by whichever standards are higher.
E. If the Contractor’s Bid Price is not within the limits set forth in Section C and Section D of this General Notice, the
Department will adjust the bid to the minimum for prices bid below the minimum acceptable bid and to the maximum for prices bid above the maximum allowable bid prior to award of the Contract.
F. Overtime:
1. Payment for overtime will be considered on a weekly basis for time worked in excess of 40 hours for a continuous 7 day period beginning Monday and ending Sunday inclusive.
2. Time worked on other Projects or Work activities other than flagging will not be counted in the normal 40 hours or the overtime.
G. The cost of the flagging operation when performed by others who are not the Contractor’s employees will not be included in the 50% subcontracting limit as outlined in Section 108.1.
O. PROSPECTIVE BIDDERS NOTES:
1. BIDDERS MUST BE REGISTERED with DelDOT in order to submit a bid. Registrations are now completed online through SimpliGov. To complete registration or for more information, click here.
2. SURETY BOND - Each proposal must be accompanied by a deposit of either surety bond or security for a sum equal to at least 10% of the amount bid.
https://www.delcode.delaware.gov/ https://deldot.gov/Business/bids/index.shtml?dc=const_contractor_reg
3. DELAWARE’S CONTRACTOR REGISTRATION ACT - 19 Del.C. §§ 3601 et seq, requires all contractors and subcontractors to register with the Delaware Department of Labor before performing construction services or maintenance. Refer to the GENERAL NOTICES section for further information.
4. DRUG TESTING - Regulation 4104; The state Office of Management and Budget has developed regulations that require Contractors and Subcontractors to implement a program of mandatory drug testing for Employees who work on
Large Public Works Contracts funded all or in part with public funds pursuant to 29 Del.C. §6908(a)(6). Refer to the full requirements at the following link:
https://regulations.delaware.gov/AdminCode/title19/4000/4100/4104.shtml#TopOfPage
Note a few of the requirements;
* At bid submission - Each bidder must submit with the bid a single signed affidavit certifying that the bidder and its subcontractors has in place or will implement during the entire term of the contract a Mandatory Drug Testing
Program that complies with the regulation (a blank affidavit form is attached);
* At least two business days prior to contract execution - The awarded Contractor shall provide to DelDOT copies of the Employee Drug Testing Program for the Contractor, each participating DBE firm, and all other listed
Subcontractors;
* Subcontractors - Contractors that employ Subcontractors on the job site may do so only after submitting a copy of the Subcontractor's Employee Drug Testing Program along with the standard required subcontractor information. A Subcontractor shall not commence work until DelDOT has approved the program in writing.
5. PERFORMANCE-BASED RATING SYSTEM - 29 Del.C. §6962 (c)(12)(a) requires DelDOT to include a performance-based rating system for contractors. The Performance Rating for each Contractor shall be used as a prequalification to bid at the time of bid. Refer to 'General Notices' for details.
6. NO RETAINAGE will be withheld on this contract unless through the Performance-Based Rating System.
7. EXTERNAL COMPLAINT PROCEDURE can be viewed on DelDOT’s Website, Contractor Compliance/EEO -
Delaware Department of Transportation calling (302) 760-2035
REVISED
8. DBE PROGRAM REQUIREMENTS As a result of the Issuance of the IFR on September 30, 2025, all of DelDOT
DBEs were decertified. DelDOT is undertaking the recertification process for DBEs pursuant to the IFR requirements.
As DelDOT currently has no certified DBEs, it is not feasible to require the submission of a DelDOT DBE Project
Participation Affidavit for this letting. Companies bidding on this letting are NOT required to submit a DBE Project
Participation Affidavit with their bid. Once DelDOT has recertified DBEs using the IFR requirements, this requirement will be reinstated.
9. DelDOT CERTIFIED DBE UTILIZATION COMMITMENT STATEMENT As a result of the Issuance of the
IFR on September 30, 2025, all DelDOT DBEs were decertified. DelDOT is undertaking the recertification process for DBEs pursuant to the IFR requirements. As DelDOT currently has no certified DBEs, it is not feasible to require the submission of a DelDOT Certified DBE Utilization Commitment Statement for this letting. Companies bidding on this letting are NOT required to submit a DelDOT Certified DBE Utilization Commitment Statement with their bid.
Once DelDOT has recertified DBEs using the IFR requirements, this requirement will be reinstated.
10. FLATWORK CONCRETE TECHNICIAN CERTIFICATION TRAINING:
Section 501.3, 503.3, 505.3, 610.3, 701.3 and 702.3 of the 2026 Standard Specifications require contractors to provide an American Concrete Institute (ACI) or National Ready-Mix Concrete Association (NRMCA) certified concrete flatwork technician to supervise all finishing of flatwork concrete.
11. NOTE that FHWA Form 1273 (attached) has been modified effective June 25, 2026. Changes are reviewed here.
https://regulations.delaware.gov/AdminCode/title19/4000/4100/4104.shtml#TopOfPage https://deldot.gov/Business/cc/ https://deldot.gov/Business/cc/ https://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf
12. SIGNAGE LANGUAGE:
In order to maintain effective communication with the traveling public, only place signs, banners, flags, or other displays within the projects limits that meet the requirements of the latest version of the Delaware Manual on Uniform Traffic
Control Devices. Any signs or other materials which deviate from the MUTCD, must be preapproved by the Engineer.
The only signage and materials which may be displayed upon vehicles and equipment within the Project area are signs denoting the name of the Contractor and any subcontractors and other signs and/or materials required and approved pursuant to the MUTCD and the Engineer. Contractor shall immediately remove any signs or materials within the
Project that does not meet these requirements immediately upon notification by the Engineer. Failure to remove signs or other materials following notification from the Engineer will result in Liquidated Damages being assessed in the manner and amount specified in the Standard Specifications section 108.9.A.
13. Bidders List Requirement:
Under 49 CFR 26.11 DelDOT must collect bidders list information from ALL contractors and subcontractors who seek to work on federally assisted contracts. The submitted information must be complete and must include the required information for the prime and all (DBE and non-DBE) subcontractors, service providers, manufacturers, distributors, and suppliers.
ALL bidders must complete the Bidders List Form (attached as an exhibit) and submit it at the time of bid.
Late submission of this information will not be accepted. Submitted information must include the following for those being proposed to work on the contract if awarded:
▪ Firm name;
▪ Firm address including ZIP code;
▪ Firm's status as a DBE or non-DBE (SEE NOTE BELOW effective 10-1-2025);
▪ NAICS code applicable to each scope of work the firm sought to perform in its bid;
▪ Age of the firm; and
▪ The annual gross receipts of the firm shown as an approximate range (i.e., $1-3 million)
This information will be maintained as confidential to the extent allowable by federal and state law.
NOTE: Based upon the IFR issued September 30, 2025, all DelDOT certified DBEs have been decertified. As such, for this letting, bidders should NOT identify in the bidders list whether a proposed contractor or subcontractor is a
DBE as no companies have currently been certified as a DBE under the new IFR requirements. That block should be left blank. Bidders will be advised once DBE’s have been re-certified pursuant to the requirements of the IFR at which time bidders will be required to provide this information.
Additionally, pursuant to the IFR, and the guidance letter issued by U.S. DOT on September 30, 2025, DelDOT has been directed not to use race or sex as presumptions for consideration of a company as a DBE. As such, bidders should
NOT identify in the bidders list a proposed contractor or subcontractor’s sex or race. Those blocks should be left blank. DelDOT anticipates providing a revised Bidders List Form in the near future, which contains only those sections required by the IFR.
Failure to submit the required bidders list documentation at the time bid will result in the bidder being deemed non-responsive and therefore ineligible for award of the contract.
14. APPENDIX A - DECORATIVE SECURITY FENCE – AMTRAK Is posted and part of this Bid Proposal.
15. REVISED SPEC LANGUAGE:
The Revised Inspection Framework – January 2026 (2026 Inspection Framework) shall apply to this contract.
https://www.ecfr.gov/current/title-49/subtitle-A/part-26/subpart-A/section-26.11 https://deldot.gov/Business/bids/index.shtml?dc=const_proj_bid_info https://deldot.gov/Business/drc/pd_files/plan_development/Revised%20Inspection%20Framework%20-%20January%202026.pdf?cache=1770037794995
Delete from Section 101.3
Primary inspection. The inspection (formerly referred to as Final Inspection) conducted by the engineer to determine if the contractor has satisfactorily completed the project, or a portion of the project, in accordance with the contract.
Insert within Section 101.3
Acceptance Inspection. The inspection (formerly referred to as Primary Inspection) conducted by the
Administering Section, contractor, and accepting section confirming that primary inspection punch list items have been addressed.
Primary inspection. The inspection (formerly referred to as initial inspection) conducted by the Department to review all contract work has been completed in accordance with the Plans, Standard Specifications, Special
Provisions, and Standard Construction Details. The inspection is confirmation of the work completed per the contract documents.
Project Acceptance. The Department’s notification to the Contractor that the time charges will cease, and construction activities are completed, releasing the contractor from liability and repairs or maintenance to the completed work.
Revise Section 104.12.A as follows.
A. Before acceptance inspection, clean rubbish, excess materials, temporary structures, and equipment from the project, from any publicly owned borrow source used to complete the work, and from areas affected by the contractor in connection with the work within the right-of-way. Cut all grass and weeds taller than 6-inches. The cost of the final cleanup is incidental to Item 763000, Initial Expense, De-
Mobilization.
Revise Section 105.4.F as follows.
F. Submit copies of manufacturer’s catalog cuts, drawings, wiring diagrams, and other relevant documents with working drawings for electrical and mechanical equipment. After the Department has reviewed all items of a particular system, prepare an instruction book for the particular system. Fasten and bind the items listed below in a leather or heavy plastic cover book with a title clearly shown.
Provide five copies of the book to the engineer before acceptance inspection. Make the books available when connecting and energizing electrical and mechanical systems. Ensure that the final bound copies reflect changes or adjustments made during the work. Include the following in the instruction book:
1. An equipment list.
2. A complete description of the equipment.
3. The sequence of operation including inter-locking and protective features.
4. The use of by-pass switches.
5. A detailed description of all wiring circuits.
6. A recommended spare parts list.
7. Renewal parts bulletins.
8. Instruction bulletins for the provided equipment.
9. Diagrams and drawings of reduced size suitable for binding.
10. An index listing all items.
Revise Section 105.13.D as follows.
D. Include the cost of maintenance work during construction and before completion of the acceptance inspection punch list in the proposal. The Department will pay the cost of maintenance work occurring after completion of the acceptance inspection punch list.
Revise Section 105.14.A as follows.
A. The engineer may order opening of certain sections of the work to traffic or other use before the contractor completes the work or before the engineer accepts the work. The Department will not consider opening sections of the work as constituting acceptance of the work or a waiver of any contract provisions. The engineer will pay the cost of repairing damage to the work caused by opening work to vehicular traffic unless opening the roadway is due to the fault, or inactivity of, the contractor or the contractor caused the damage. All other maintenance costs including, but not limited to, mowing grass and general cleanup are the contractor’s responsibility until completion of the acceptance inspection punch list to the Department’s satisfaction. Maintenance costs for work involving landscaping and vegetative growth are the contractor’s responsibility until final acceptance.
Revise Section 105.16 as follows.
A. Partial Acceptance.
1. The decision to partially accept a portion of the project is solely at the discretion of the engineer.
The engineer may partially accept portions of the work. The Department will not consider partial acceptance as constituting acceptance of the work that has not been partially accepted or a waiver of any contract provisions. The Department will maintain the partially accepted portion of the project, including repairing damage caused by the public.
B. Project Acceptance
1. The Department will cease counting contract time when the project reaches substantial completion as defined in Section 101.3, Definitions.
2. Substantial Completion Verification
a. Upon receiving the contractor’s notice of substantial completion of the project, the Department will verify all contract items are complete as defined in Section 101.3, Definitions. Items not deemed complete shall be completed by contractor prior to Department issuance of Substantial
Completion.
b. After issuance of Substantial Completion, request Primary Inspection from the Department.
c. The Department will schedule the Primary Inspection within 30 calendar days of the request.
3. Primary Inspection
a. The Department/Administering Section will conduct a Primary Inspection with the completion of 105.16.2 Substantial Completion Verification. The Administering Section will note and provide a written punch list by stations and in detail identifying work or conditions requiring correction. The punch list will include ADA inspection deficiencies.
b. Perform the corrective work noted on the punch list within 30 calendar days upon receipt of the punch list created by the Administering Section, unless the parties mutually agree to extend the time frame.
c. Upon completion of the primary inspection punch list, request an acceptance inspection from the Department. Prior to acceptance inspection scheduling, the Administering Section will confirm and annotate the primary inspection punch list and ensure ADA Inspection deficiencies have been addressed and documented.
d. The Administering Section will schedule Acceptance inspection with the Maintenance District within 30 days of confirmation of primary punch list item completion.
4. Acceptance (formerly primary) Inspection.
a. The Department will conduct an acceptance inspection with the completion of 105.16.B.3, primary inspection. The Administering Section will provide a written punch list identifying deficiencies not satisfactorily addressed from the primary inspection punch list within 7 calendar days of the acceptance inspection.
b. Perform the corrective work noted on the punch list within 15 calendar days upon receipt of the punch list created by the Administering Section, unless the parties mutually agree to extend the time frame.
c. The Administering Section will verify remediation work and will provide a list with dates that remedial activities were resolved to the Maintenance District when requesting Project
Acceptance.
C. Project Acceptance
1. The Administering Section will notify the Maintenance District that acceptance inspection punch list items have been addressed.
2. The Maintenance District and/or other accepting entities will verify acceptance inspection punch list items have been addressed within 30 calendar days of notice from the Administering Section.
D. Final Acceptance
1. The engineer will provide final acceptance in writing that will state the acceptance date as defined in Section 101.3, Definitions.
E. Project Closeout
1. Upon final acceptance, provide the exempted documents, certificates, or proofs of compliance within 90 calendar days.
2. The Department will not issue the final payment until the contractor executes and delivers the required documents.
Revise Section 108.8.K as follows.
K. Once the Department determines that the work is substantially complete, the Department will suspend time charges and the assessment of liquidated damages. Failure to complete all punch list work identified during the primary and acceptance inspections within the timeframes allotted, will result in the Department restarting liquidated damages in accordance with the chart specified in Section 108.9, Schedule of Liquidated Damages. The assessment of post-substantial-completion liquidated damages will continue until project completion.
Revise Section 610.3.9.A.2 as follows.
2. The engineer will measure the width, length, and depth of each crack and establish the precise location of the crack termination points relative to permanent reference points on the member. The engineer will monitor and document the growth of individual cracks at an inspection interval the engineer will choose to determine if cracks are active or dormant after acceptance inspection.
Revise Section 722.3.2.A as follows.
A. Provide on-site field instruction by the system manufacturer, at a location determined by the engineer.
Provide a minimum of 2 training sessions consisting of installation training before beginning cable barrier construction and maintenance training before acceptance inspection. The manufacturer shall establish the training duration and shall provide field training on all aspects of the system. Coordinate the training schedule and location with the engineer. The engineer will advise the appropriate department staff, including construction inspectors and maintenance personnel regarding the training location and schedule. Provide all training materials in both hard copy and electronic PDF format.
Revise Section 722.3.2.C.1 as follows.
1. Hold the maintenance training a minimum of 7 calendar days before acceptance inspection of the system. Submit the proposed training date to the engineer a minimum of 14 calendar days prior to the training session date for review and approval. Include the following participants:
a. District Maintenance Engineer, or designated representative;
b. District Maintenance Superintendent, or designated representative;
c. Area Yard Supervisor, or designated representative; and
d. District maintenance personnel.
Revise Section 722.3.3.L as follows.
L. Within 10 calendar days of the primary inspection, supply spare parts for the HTCB system. Deliver the parts to the DelDOT maintenance facility as directed by the engineer. Provide an extra supply of the following:
1. Socketed-type line posts, including post hardware, caps, reflective sheeting, straps, spacers, and socket covers. Include 200 posts and accessories.
2. Rigging screws and threaded terminals. Provide enough materials to complete 8 turnbuckle assemblies.
3. Anchor posts including post hardware and caps, reflective sheeting, straps, fittings, spacers, and socket covers. Provide enough materials to complete 3 end anchor installations.
4. Fitting gaskets or socket covers. Provide 100 socket covers.
Revise Section 843.3.5.C as follows.
C. Repair defects identified by the Department during periodic or primary inspections in accordance with this specification, including all highway lighting systems and components within the project limits.
Begin highway lighting system repairs immediately following notice of the lighting system defect unless weather limitations prevent the corrective work. Provide notification to the Department before beginning corrective work.
Revise Section 843.3.5.D as follows.
D. The Department will not consider the highway lighting system as substantially complete until correction of the deficiencies noted during the primary and acceptance inspections. Provide a maintenance bond for item 843001 – Electrical Testing upon substantial completion. Provide a maintenance bond meeting the following requirements:
1. A bond sum equal to 100 percent of the value of all highway lighting system items the Department paid to the contractor;
2. With original signatures, in ink, and not mechanical reproductions or facsimiles of any kind, naming the contractor as the principle;
3. term of 1-year beyond the completion of the highway lighting system work; and
4. written by a surety or insurance company licensed to write surety bonds in the State of Delaware by the Delaware Department of Insurance.
Revise 911.3.6.G as follows.
G. Water bi-weekly during the period June 15 through October 1. Continue watering, without interruption, until completing watering of all the plants on the project. Use water in accordance with Section 911.2.9.
The Department will allow use of tree watering bags as a part of the watering operation. Remove the tree watering bags before acceptance inspection.
- end –
GENERAL NOTICES
CONTRACTOR REGISTRATION ACT
On July 1, 2021, the Contractor Registration Act, as codified in 19 Del.C. §§ 3601 et seq, took effect. This law requires all contractors to register with the Delaware Department of Labor before performing construction services or maintenance. The
Contractor Registration Act applies to all contractors that engage in construction and maintenance within the State of
Delaware. Additionally, it requires contractors to have Delaware workers’ compensation insurance where required, compliance with labor laws, and proof of a state business license. The Delaware Department of Labor’s Office of Contractor
Registration is responsible for enforcement of the requirements of the Contractor Registration Act. If you have any questions about the contractor registration process, please call 302-430-7739 or email Contract.Registry@delaware.gov. Registration at https://onestop.delaware.gov/.
BUY AMERICA REQUIREMENT REVISED
The Build America, Buy America Act (BABA), enacted as part of the Bipartisan Infrastructure Law (BIL) requires iron, steel, manufactured products, and construction materials used in infrastructure projects funded by Federal financial assistance to be produced in the United States.
In accordance with 23 U.S.C. 313 and 23 CFR 635.410, all iron and steel materials permanently incorporated into this project will be produced in the United States and all manufacturing processes involving these materials will occur in the
U.S., except that a minimal amount of foreign steel or iron materials may be used, provided the cost of the foreign materials does not exceed 0.1 percent of the total Contract cost or $2,500.00, whichever is greater. If such minimal amount of foreign steel is used, the Contractor shall maintain a record of the costs to ensure that the allowable limit is not exceeded.
In accordance with 23 CFR 635.410, all manufactured products will be manufactured in the U.S. and the cost of components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product. Iron or steel components of precast concrete products and cabinets or enclosures of any intelligent transportation systems and other electronic hardware systems classified as a manufactured product which is permanently incorporated into this project will be produced in the U.S. and all manufacturing processes involving the iron and steel will occur in the U.S., except that a minimal amount of foreign steel or iron materials may be used, provided the cost of the foreign materials does not exceed 0.1 percent of the total Contract cost or $2,500.00, whichever is greater. If such minimal amount of foreign steel is used, the Contractor shall maintain a record of the costs to ensure that the allowable limit is not exceeded.
In accordance with 2 CFR 184, all non-ferrous metals, plastic and polymer-based products, glass, fiber optic cable, optical fiber, lumber, drywall and engineered wood construction material will be produced in the U.S.
DelDOT maintains a list of all pay items, the applicable BABA category designation, and additional guidance at the following address: https://deldot.gov/Business/prodlists/index.shtml?dc=buyAmerica.
By signing and submitting this proposal, the bidder certifies that:
“All materials that will be permanently incorporated into this project will meet the Buy America material requirements. At the Department's request, I/we will provide manufacturer's/supplier's documentation verifying domestic origin as defined in the Contract. All Materials accepted on the basis of such Certificate of Compliance may be sampled by the Department and tested at any time. Use of Material on the basis of Certificate of Compliance shall not relieve the Contractor of responsibility for incorporating Material in the Project conforming to the requirements of the Contract. Any Material not conforming to such requirements will be subject to rejection whether in place or not. The Department reserves the right to refuse to permit the use of Material on the basis of Certificate of Compliance.”
mailto:Contract.Registry@delaware.gov https://onestop.delaware.gov/ https://deldot.gov/Business/prodlists/index.shtml?dc=buyAmerica
DOMESTIC MATERIAL REQUIREMENT NEW
All materials permanently incorporated into this project must comply with the applicable domestic material requirements of 23 U.S.C. § 313 and the Build America, Buy America Act, as codified in 41 U.S.C. § 8301 note, and as implemented by
23 CFR 635.410 and 2 CFR Part 184.
In accordance with 23 CFR 635.410, all iron and steel materials permanently incorporated into this project will be produced in the U.S. and all manufacturing processes involving these materials will occur in the U.S., except that a minimal amount of foreign steel or iron materials may be used, provided the cost of the foreign materials does not exceed 0.1 percent of the total Contract cost or $2,500.00, whichever is greater. If such minimal amount of foreign steel is used, the Contractor shall maintain a record of the costs to ensure that the allowable limit is not exceeded.
In accordance with 23 CFR 635.410, all manufactured products permanently incorporated into this project will have their final manufacturing process be performed in the U.S. and have the cost of components of the manufactured product that are mined, produced, or manufactured in the U.S. be greater than 55 percent of the total cost of all components of the manufactured product. Iron or steel components of precast concrete products and cabinets or enclosures of any intelligent transportation systems, and other electronic hardware systems classified as a manufactured product which is permanently incorporated into this project will be produced in the U.S., and all manufacturing processes involving the iron and steel will occur in the U.S., except that a minimal amount of foreign steel or iron materials may be used, provided the cost of the foreign materials does not exceed 0.1 percent of the total Contract cost or $2,500.00, whichever is greater. If such minimal amount of foreign steel is used, the Contractor shall maintain a record of the costs to ensure that the allowable limit is not exceeded.
In accordance with 2 CFR Part 184, all non-ferrous metals, plastic and polymer-based products, glass, fiber optic cable, optical fiber, lumber, drywall and engineered wood construction material permanently incorporated into this project will be produced in the U.S.
DelDOT maintains a list of pay items, their applicable material classifications, and additional guidance at the following website: https://deldot.gov/Business/prodlists/index.shtml?dc=buyAmerica.
By signing and submitting this proposal, the bidder certifies that:
“All materials that will be permanently incorporated into this project will meet the domestic material requirements established in this proposal. I/we will provide documentation verifying material domestic origin as required by the Contract and upon Department request.”
SPECIFICATIONS :
The Delaware specifications entitled "Standard Specifications for Road and Bridge Construction January, 2026", with the applicable version defined in the ‘GENERAL DESCRIPTION’ and hereinafter referred to as the Standard Specifications;
shall govern the work to be performed under this contract. The Contractor shall make itself aware of these specifications, revisions and corrections, and apply them to the applicable item(s) of this contract.
CLARIFICATIONS :
Under any Section or Item included in the Contract, the Contractor shall be aware that when requirements, responsibilities, and furnishing of materials are outlined in the details and notes on the Plans and in the paragraphs preceding the " Basis of
Payment" paragraph in the Standard Specifications or Special Provisions, no interpretation shall be made that such stipulations are excluded because reiteration is not made in the "Basis of Payment" paragraph.
DelDOT requires the use of various electronic applications for various documentation processes.
These processes will be identified, and the Contractor's required use will be detailed during the Preconstruction Meeting.
No additional payments will be made to the contractor to use or interface with the applications.
https://deldot.gov/Business/prodlists/index.shtml?dc=buyAmerica
ATTESTING TO NON-COLLUSION :
DelDOT requires as a condition precedent to acceptance of bids a sworn statement executed by, or on behalf of, the person, firm, association, or corporation to whom such contract is to be awarded, certifying that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with such contract. The form for this sworn statement is included in the proposal and must be properly executed in order to have the bid considered.
QUANTITIES :
The quantities shown are for comparison of bids only. DelDOT may increase or decrease any quantity or quantities without penalty or change in the bid price.
PERFORMANCE-BASED RATING SYSTEM
29 Del.C. §6962 (c)(12)(a) requires a DelDOT project, excluding a municipal street aid contract, to include a performance-based rating system. At the time of bid, the Performance Rating for each Contractor shall be used as a prequalification to bid.
Bidders with Performance Rating scores equal to or greater than 85% shall be permitted to bid. Bidders with scores of less than 85% who comply with the retainage requirements of 29 Del.C. §6962 shall be permitted to bid provided the Agreement to Accept Retainage (located on the Certification Page) is executed and submitted with the bid. Lack of an executed
Agreement to Accept Retainage will result in the rejection of the bid by DelDOT. Successful bidders awarded DelDOT contracts who have no performance history within the last five (5) years will be assigned a provisional Performance Rating of 85% at the date of advertisement.
Notification of Performance Rating. DelDOT shall post publicly the Performance Rating for all Contractors on DelDOT’s website. DelDOT will complete performance-based evaluations on the construction company contracted by DelDOT to build the project (the "Contractor"). Provisions to appeal Performance Ratings are described in the regulations. The regulations are set forth in Section 2408 of Title 2, Delaware Administrative Code, found here.
EQUALITY OF EMPLOYMENT OPPORTUNITY ON PUBLIC WORKS :
Delaware Code, Title 29, Chapter 69, Section 6962, Paragraph (d), Subsection (7) states;
a. As a condition of the awarding of any contract for public works financed in whole or in part by State appropriation, such contracts shall include the following provisions:
During the performance of this contract, the contractor agrees as follows:
1. The contractor will not discriminate against any employee or applicant for employment because of race, creed, color, sex, sexual orientation, gender identity or national origin. The contractor will take positive steps to ensure that applicants are employed and that employees are treated during employment without regard to their race, creed, color, sex, sexual orientation, gender identity or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The contractor agrees to post in conspicuous places available to employees and applicants for employment notices to be provided by the contracting agency setting forth this nondiscrimination clause.
2. The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to race, creed, color, sex, sexual orientation, gender identity or national origin.
3. The contractor will ensure employees receive equal pay for equal work, without regard to sex. Employee pay differential is acceptable if pursuant to a seniority system, a merit system, a system which measures earnings by quantity or quality of production, or if the differential is based on any other factor other than sex.
https://www.deldot.gov/Business/bids/PreQual/index.shtml http://regulations.delaware.gov/register/february2019/final/22%20DE%20Reg%20691%2002-01-19.htm
TAX CLEARANCE :
As payments to each vendor or contractor aggregate $2,000, the Division of Accounting will report such vendor or contractor to the Division of Revenue, who will then check the vendor or contractor's compliance with tax requirements and take such further action as may be necessary to ensure compliance.
LICENSE :
A person desiring to engage in business in this State as a contractor on a project designated to include federal funds, shall obtain a Delaware business license upon making application to the Division of Revenue. Proof of said license compliance to be made prior to, or in conjunction with, the execution of a contract to which he has been named.
SUBCONTRACTOR LICENSE: 29 DEL. C. §6967:
(c) Any contractor that enters a public works contract must provide to the agency to which it is contracting, within 30 days of entering such public works contract, copies of all occupational and business licenses of subcontractors and/or independent contractors that will perform work for such public works contract. However, if a subcontractor or independent contractor is hired or contracted more than 20 days after the contractor entered the public works contract the occupational or business license of such subcontractor or independent contractor shall be provided to the agency within 10 days of being contracted or hired.
DIFFERING SITE CONDITIONS:
SUSPENSIONS OF WORK and SIGNIFICANT CHANGES IN THE CHARACTER OF WORK:
Differing site conditions: During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before they are disturbed and before the affected work is performed.
Upon written notification, the engineer will investigate the conditions, and if he/she determines that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding loss of anticipated profits, will be made and the contract modified in writing accordingly. The engineer will notify the contractor of his/her determination whether or not an adjustment of the contract is warranted.
No contract adjustment which results in a benefit to the contractor will be allowed unless the contractor has provided the required written notice. No contract adjustment will be allowed under their clause for any effects caused on unchanged work.
Suspensions of work ordered by the engineer: If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result…