Attachment__7_-_Submital_Register_CEFOP_Popayan.pdf

PDF 176 KB Posted

Attached to
Fusion and Operations Center (CEFOP) Construction - Popayan Colombia Federal contract opportunity
Solicitation number
SWHARC15R0009
Issued by
Department of State Office of Acquisition Management

About this file

Attachment 7

View the file

Other files for this federal contract opportunity

Other files attached to Fusion and Operations Center (CEFOP) Construction - Popayan Colombia, newest first.
File Type Posted
Attachment__3_-_POPAYAN_CEFOP_DRAWINGS-SMALL.pdf PDF
SWHARC-15-R-0009_SF_1442_CEFOP_Popayan.pdf PDF
Attachment__2_-_CEFOP_POPAYAN_BID_CHART.pdf PDF
Attachment__1_-_CEFOP_Popayan_Specifications.pdf PDF
FS-102.pdf PDF
Contractor_Questions_-_CEFOP_Popayan_-_Final.doc DOC document
AmendmentA002-AttachmentA.doc DOC document
AmendmentA002-SF30.doc DOC document
AmendmentA001SF30-Q-A.doc DOC document
Attachment__7_-_Submital_Register_CEFOP_Popayan.pdf PDF
SWHARC-15-R-0009_SF_1442_CEFOP_Popayan.pdf PDF
cover_letter_SWHARC-15-R-0009.docx DOCX document
Attachment__3_-_POPAYAN_CEFOP_DRAWINGS-SMALL.pdf PDF
Attachment__8_-_SAMRegistration.pdf PDF
Attachment__6_-_PastPerformance.pdf PDF
CEFOP_Popayan_-_Solicitation_SWHARC15R0009_draft_June_02_2015.docx DOCX document
Attachment__2_-_CEFOP_POPAYAN_BID_CHART.pdf PDF
Attachment__4_-_BondsandInsurance.pdf PDF
Attachment__5_-_FirmandProjectInformation.pdf PDF
Attachment___1.PDF PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 38 PAGES

CEFOP BUILDING

01 32 16.00 20 SD-01 Preconstruction Submittals 1.3Construction schedule

Submittal Register 01 33 00 SD-01 Preconstruction Submittals

1.6Submittal Register 01 50 00 SD-01 Preconstruction Submittals

1.4Construction site plan 01 78 00 SD-03 Product Data

As-Built Record of Equipment and Materials

1.5.1Warranty Management Plan 1.5.4Warranty Tags

Spare Parts Data SD-08 Manufacturer’s Instructions

1.4Preventative Maintenance 1.4Condition Monitoring (Predictive

Testing) 1.4Inspection 1.5.1Instructions

SD-10 Operation and Maintenance Data

1.6Operation and Maintenance Manuals

SD-11 Closeout Submittals 1.3.1Record Drawings

02 41 00 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 38 PAGES

02 41 00 1.8 GExisting Conditions SD-07 Certificates

1.2.1 GDemolition Plan

1.6 GNotification

03 11 13.00 10 SD-02 Shop Drawings

3.1.1 GFormwork

SD-03 Product Data 1.2Design 2.1Form Materials 2.1.6Form Releasing Agents

SD-04 Samples

1.4 GSample Panels

SD-06 Test Reports 3.5Inspection

3.4.1 GFormwork Not Supporting Weight

of Concrete SD-07 Certificates Fiber Voids

03 20 00.00 10 SD-02 Shop Drawings 3.1Reinforcement

SD-03 Product Data 1.3.1Welding

Butt-Splices Material

SD-04 Samples Reinforcement Bars

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 38 PAGES

03 20 00.00 10 SD-06 Test Reports Material Tests, Inspections, and Verifications

SD-07 Certificates 2.3Reinforcing Steel

03 30 00 SD-02 Shop Drawings 1.6.2.1Fabrication Drawings 1.6.2.2Formwork 1.6.2.2Formwork 1.6.2.1Special Construction

1.6.2.3 GReinforcing steel

SD-03 Product Data 2.4.7Materials for curing concrete 2.4.9Joint sealants 2.4.8Joint filler 2.4.1Cement 2.4.1.1Portland Cement 2.3.2Ready-Mix Concrete 2.4.6Vapor barrier 2.6Bonding Materials 2.3.3Concrete Curing Materials 2.5Reinforcement 1.6.2.1Reinforcement Materials 2.4.10Epoxy bonding compound 2.4.9.3Waterstops

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 38 PAGES

03 30 00 3.13.2Waterstops 2.1.1Wood Forms 2.4.11Biodegradable Form Release

Agent SD-04 Samples

1.6.5.1Slab finish sample 2.4.9.3Dumbbell Type 2.4.9.3Rubber 2.4.9.3Polyvinylchloride (PVC)

SD-05 Design Data

2.3.1 Gmix design

1.6.1.1Calculations

SD-06 Test Reports

1.6.4.1 GConcrete mix design

1.6.4.2Aggregates 3.9.2.1Tolerance report 3.11.2.3Compressive strength tests 2.8.4Slump 2.8.1Air Entrainment

SD-07 Certificates 1.6.3.1Curing concrete elements 1.6.3.3Finishing plan 1.6.3.6Material Safety Data Sheets 2.5.5Steel Bar

04 20 00 SD-02 Shop Drawings 1.4.4Detail Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 38 PAGES

04 20 00 SD-03 Product Data 2.4.2Cement 2.5Water-Repellant Admixture

SD-04 Samples 2.2Concrete Masonry Units (CMU) 2.7Anchors, Ties, and Bar

Positioners 2.10Expansion-Joint Materials 2.8Joint Reinforcement 1.4.2Portable Panel

SD-05 Design Data 2.4.3Pre-mixed Mortar 1.2.1.1Unit Strength Method

SD-06 Test Reports 3.15.1Field Testing of Mortar 3.15.2Field Testing of Grout 3.15.3Prism tests 1.4.3Masonry Inspector Qualifications 3.15.4Single-Wythe Masonry Wall

Water Penetration Test SD-07 Certificates

2.2Concrete Masonry Units (CMU) 2.4.1Admixtures for Masonry Mortar

05 05 23 SD-03 Product Data 1.5Welding Procedure Qualifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 38 PAGES

05 05 23 1.5.5Welder, Welding Operator, and Tacker Qualification

1.5.6Inspector Qualification 1.5.2Previous Qualifications 1.5.3Pre-qualified Procedures

SD-06 Test Reports 3.2Quality Control 3.3.1Nondestructive Examination 1.5.1Certified Welding Procedure

Specifications (WPS) 1.5.1Certified Procedure Qualification

Records (PQR) 1.5.1Certified Welder Performance

Qualifications (WPQ) 05 12 00 SD-02 Shop Drawings

1.5.2.1Erection Plan 1.5.1Fabrication drawings

SD-03 Product Data 2.4Shop primer 2.3.1Welding electrodes and rods 2.2.5Load indicator washers

SD-06 Test Reports 2.4Class B coating 2.2Bolts, nuts, and washers

SD-07 Certificates 2.1Steel

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 38 PAGES

05 12 00 2.2Bolts, nuts, and washers 1.5.2.2Welding procedures and qualifications 05 50 13 SD-02 Shop Drawings

2.7structural steel door frames 2.3Access doors and panels 2.4Cover plates and frames

SD-03 Product Data 2.3Access doors and panels 2.4Cover plates and frames

Control-joint covers 2.7Structural steel door frames

05 50 14 SD-02 Shop Drawings 1.3.2Detail Drawings

SD-03 Product Data 2.2.2.1Welding of Structural Steel 2.3.4Structural Steel Welding Repairs

Materials Orders 2.1.1Materials List

Shipping Bill SD-06 Test Reports

2.3Tests, Inspections, and Verifications

SD-07 Certificates 1.3.1Qualification of Welders and

Welding Operators

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 38 PAGES

06 20 00 SD-02 Shop Drawings 1.3Detail Drawings

SD-03 Product Data 2.1.13Siding

2.1.13.9Epoxy-Aggregate Panels 2.1.13.7Wood

SD-04 Samples 2.1.13Siding

2.4Wood Shingles 2.1.13.9Moldings 2.3Fascias and Trim

SD-07 Certificates 1.4Certificates of grade 1.4Certificates of compliance

07 21 16 SD-03 Product Data 2.1Blanket insulation

SD-08 Manufacturer’s Instructions 3.3.1Insulation

07 41 63 SD-01 Preconstruction Submittals 1.5.1Qualification of Manufacturer 1.5.3Qualification of Manufacturer 1.5.1Qualification of Installer

SD-02 Shop Drawings 1.5.1Roofing Panels

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 38 PAGES

07 41 63 1.5.1Flashing and Accessories 1.5.1Gutter/Downspout Assembly

SD-03 Product Data 1.5.1Factory Color Finish 1.5.1Sub-girts and Formed Shapes 1.5.1Closure Materials 1.5.1Insulation 1.5.1Pressure Sensitive Tape 1.5.1Sealants and Caulking 1.5.1Galvanizing Repair Paint 1.5.1Aluminized Steel Repair Paint 1.5.1Accessories

SD-04 Samples 1.5.1Roofing Panels 2.2.2Fasteners 2.4.1Metal Closure Strips 1.5.1Insulation 1.5.1Manufacturer s color charts and chips SD-05 Design Data

1.5.1Wind design analysis SD-07 Certificates

2.2.2Fasteners 1.5.1Enamel Repair Paint

SD-08 Manufacturer’s Instructions

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 38 PAGES

07 41 63 1.5.1Installation of Roof panel assemblies

SD-11 Closeout Submittals 1.8Warranty 1.5.1Instructions 1.5.1Material Safety Data Sheets

07 60 00 SD-02 Shop Drawings 3.1.7Gutters 3.1.8Downspouts 3.1.11Flashing at roof penetrations 3.1.9Eave flashing

07 92 00 SD-03 Product Data 2.1Sealants 2.2Primers 2.3Bond breakers 2.4Backstops

SD-07 Certificates 3.3.6Sealant

08 11 13 SD-02 Shop Drawings 2.1Doors 2.1Doors 2.4Frames 2.4Frames 2.3Accessories 2.5Weatherstripping

SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 38 PAGES

08 11 13 2.1Doors 2.4Frames 2.3Accessories

08 51 13 SD-02 Shop Drawings 2.1Windows 1.10Fabrication Drawings

SD-03 Product Data 2.1Windows 2.2.2.1Hardware 2.2.4Screens 2.2.2Accessories 1.11.4Thermal performance

SD-04 Samples 1.4.2.1Finish Sample 1.4.2.2Window Sample

SD-10 Operation and Maintenance Data

2.1Windows 08 71 00 SD-02 Shop Drawings

1.3Hardware schedule 2.3.5Keying system

SD-03 Product Data 2.3Hardware items

SD-08 Manufacturer’s Instructions 3.1Installation

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 38 PAGES

08 71 00 SD-10 Operation and Maintenance Data

1.3Hardware Schedule SD-11 Closeout Submittals

1.4Key Bitting 08 81 00 SD-03 Product Data

1.3Glazing Accessories SD-04 Samples

2.3.1Glazing Compound 2.3.2.1Sealant

08 91 00 SD-02 Shop Drawings 1.4Wall louvers 1.5Wall louvers

SD-03 Product Data 2.2Metal Wall Louvers

SD-04 Samples 1.4Wall louvers 1.5Wall louvers

09 06 90 SD-04 Samples 2.2Color Schedule

09 24 23 SD-02 Shop Drawings 3.2Lath

SD-03 Product Data 3.4Proportions and Mixing

SD-04 Samples 2.2Colored Stucco Finish Coat

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 38 PAGES

09 24 23 1.3Sample Panel 09 26 00 SD-03 Product Data

2.1.4Gypsum base 2.1.5Gypsum veneer plaster

09 29 00 SD-03 Product Data 2.1.3Water-Resistant Gypsum

Backing Board 2.1.1Gypsum Board 2.1.7Accessories

SD-07 Certificates 2.1Asbestos Free Materials

SD-08 Manufacturer’s Instructions Material Safety Data Sheets

SD-10 Operation and Maintenance Data Manufacturer maintenance instructions

Waste Management SD-11 Closeout Submittals

2.1.1Gypsum Board Adhesives

09 30 00 SD-02 Shop Drawings 1.4Detail Drawings

SD-03 Product Data 2.1Tile 2.2Setting-Bed

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 38 PAGES

09 30 00 2.4Mortar, Grout, and Adhesive Certification

SD-04 Samples 2.1Tile

Accessories Marble Thresholds

2.4Grout SD-07 Certificates

2.1Tile 2.4Mortar, Grout, and Adhesive

09 51 00 SD-02 Shop Drawings 1.2Approved Detail Drawings

SD-03 Product Data Acoustical Ceiling Systems Certification

SD-04 Samples 2.1Acoustical Units

09 90 00 SD-02 Shop Drawings 3.11Piping identification 3.11stencil

SD-03 Product Data Certification

2.1Coating 2.1Manufacturer's Technical Data

Sheets SD-04 Samples

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 38 PAGES

09 90 00 1.9Color 1.4.2Textured Wall Coating System 1.4.3Sample Textured Wall Coating

System Mock-Up SD-07 Certificates Applicator's qualifications

1.4.1.2Qualification Testing SD-08 Manufacturer’s Instructions Application instructions

3.7.2Mixing 1.7.2Manufacturer's Material Safety

Data Sheets SD-10 Operation and Maintenance Data

2.1Coatings:

10 28 13 SD-03 Product Data

2.1.2Finishes 2.2Accessory Items

SD-04 Samples 2.1.2Finishes 2.2Accessory Items

SD-07 Certificates 2.2Accessory Items

10 44 16 SD-02 Shop Drawings 2.1Fire Extinguishers

Accessories

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 38 PAGES

10 44 16 2.4Cabinets 2.5Wall Brackets

SD-03 Product Data 2.1Fire Extinguishers

Accessories 2.5Wall Brackets

SD-04 Samples 2.1Fire Extinguisher 2.5Wall Brackets

Accessories SD-07 Certificates

2.1Fire Extinguishers 2.1Manufacturer's Warranty with

Inspection Tag 12 21 00 SD-02 Shop Drawings

3.3Installation SD-03 Product Data

2.1Window Blinds 3.3Installation

Certification SD-04 Samples

2.1Window Blinds SD-06 Test Reports

2.1Window Blinds SD-08 Manufacturer’s Instructions

2.1Window Blinds

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 38 PAGES

12 21 00 SD-10 Operation and Maintenance Data

2.1Window Blinds 12 36 00 SD-02 Shop Drawings

2.2Fabrication 3.1Installation Drawings

SD-03 Product Data Synthetic resin Tile

SD-04 Samples 2.2Countertop 2.2Backsplash, 2.4Accessories and Hardware 2.1Manufacturer's Standard Color

Charts SD-08 Manufacturer’s Instructions

2.1Manufacturer's Instructions 13 48 00 SD-03 Product Data

3.1Bracing 1.3Equipment Requirements

22 00 00 SD-02 Shop Drawings 3.6.1Plumbing System

SD-03 Product Data 2.4Fixtures 2.4.2Flush valve urinals 2.4.3Flush tank water closets

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 38 PAGES

22 00 00 Wall hung lavatories 2.4.4Countertop lavatories

Kitchen sinks Service sinks Water heaters Shower Faucets

3.6.1Plumbing System SD-06 Test Reports

3.6Tests, Flushing and Disinfection SD-07 Certificates

1.3Materials and Equipment 2.1.1Bolts

SD-10 Operation and Maintenance Data

3.6.1Plumbing System 23 00 00 SD-02 Shop Drawings

1.4.5 GDetail Drawings

SD-03 Product Data

2.7.1.1Axial Flow Fans 2.7.1.2Ceiling Exhaust Fans

2.8.1 GRoom Fan-Coil Units

1.4.6Test Procedures

1.2.1.2 GDiagrams

SD-06 Test Reports

3.9 GPerformance Tests

SD-08 Manufacturer’s Instructions

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 38 PAGES

23 00 00 3.2Manufacturer's Installation Instructions

3.11.2Operation and Maintenance Training

SD-10 Operation and Maintenance Data

3.11.1Operation and Maintenance Manuals

2.7.1.1 GAxial Flow Fans

2.7.1.2 GCeiling Exhaust Fans

2.8.1 GRoom Fan-Coil Units

23 05 48.00 40 SD-02 Shop Drawings 1.2Installation Drawings 1.2Outline Drawings

SD-03 Product Data 1.2Equipment and Performance

Data 2.3Isolators

SD-06 Test Reports Type of Isolator Type of Base Allowable Deflection Measured Deflection

23 07 00 SD-03 Product Data GPipe Insulation Systems

SD-04 Samples

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 38 PAGES

23 07 00 2.2.1.2 GThermal Insulation SD-08 Manufacturer’s Instructions

GPipe Insulation Systems GDuct Insulation Systems

23 23 00 SD-02 Shop Drawings

2.2 GRefrigerant Piping System

SD-03 Product Data 2.2Refrigerant Piping System

1.3.1 GQualifications

3.4 GRefrigerant Piping Tests

3.1Verification of Dimensions

SD-06 Test Reports 3.4Refrigerant Piping Tests

SD-07 Certificates

2.1 GService Organization

SD-10 Operation and Maintenance Data

1.5Maintenance 23 34 23.00 40 SD-02 Shop Drawings

1.5Shop Drawings 3.1Installation Drawings 1.5Record Drawings

SD-03 Product Data 1.1Equipment and Performance

Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 38 PAGES

23 34 23.00 40 1.5Equipment and Performance Data

1.1Manufacturer's Catalog Data 1.5Manufacturer's Catalog Data 2.2Housing 2.3Fan 2.5Motor 2.6Bases 2.7Roof Curbs 2.8Dampers 2.9Screens 2.10Sound Baffles

SD-06 Test Reports 3.2Tests

23 81 00.00 20 SD-02 Shop Drawings 2.3.2Field-assembled refrigerant piping 1.3.2Control system wiring diagrams

SD-03 Product Data 2.1Air conditioners 2.3Refrigerant piping and accessories SD-06 Test Reports

3.5.3Start-up and initial operational tests

SD-08 Manufacturer’s Instructions

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 38 PAGES

23 81 00.00 20 2.1Air conditioners 2.3Refrigerant piping and accessories SD-10 Operation and Maintenance Data

2.1Air conditioners SD-11 Closeout Submittals

1.3.4Posted operating instructions 23 82 02.00 10 SD-02 Shop Drawings

1.4Drawings SD-03 Product Data

2.1Materials and Equipment 1.6Spare Parts 3.4Posted Instructions 3.1Verification of Dimensions

Coil Corrosion Protection 3.6System Performance Tests

3.4 GDemonstrations

SD-06 Test Reports

3.5 GRefrigerant Tests, Charging, and

Start-Up

3.6 GSystem Performance Tests

SD-07 Certificates 2.1Materials and Equipment 2.1.1Service Organization

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 38 PAGES

23 82 02.00 10 SD-10 Operation and Maintenance Data

3.4Operation and Maintenance Manuals

26 05 00.00 40 SD-01 Preconstruction Submittals 2.1Material, Equipment, and Fixture

Lists SD-03 Product Data

2.1.1Conduits and Raceways 2.1.3Wire and Cable 3.2.1.9Splices and Connectors 2.1.4Switches 2.1.5Receptacles 2.1.6Outlets, Outlet Boxes, and Pull

Boxes 2.1.8Circuit Breakers 2.1.7Panelboards 2.1.9Lamps and Lighting Fixtures 2.1.12Dry-Type Distribution

Transformers SD-06 Test Reports

3.3Continuity Test 3.3Phase-Rotation Tests 3.3Insulation Resistance Test

SD-07 Certificates 1.4Certification

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 38 PAGES

26 05 00.00 40 SD-08 Manufacturer’s Instructions Part 2Manufacturer's Instructions

26 20 00 SD-02 Shop Drawings

2.12 GPanelboards

2.20 GWireways

SD-03 Product Data

2.11 GReceptacles

2.12.3 GCircuit breakers

2.10 GSwitches

GTransformers

2.13 GEnclosed circuit breakers

2.15.1 GCATV outlets

2.16.3 GGrounding Busbar

2.22 GSurge protective devices

SD-06 Test Reports

3.5.2 G600-volt wiring test

3.5.4 GGrounding system test

GTransformer tests

3.5.3 GGround-fault receptacle test

SD-09 Manufacturer’s Field Reports Transformer factory tests

SD-10 Operation and Maintenance Data

1.5.1 GElectrical Systems

26 24 16.00 40 SD-02 Shop Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 38 PAGES

26 24 16.00 40 2.1.1Detail Drawings 2.1.1Outline Drawings

SD-03 Product Data 1.3Panelboards 2.1.1Panelboards

SD-06 Test Reports 3.2Continuity Tests 3.2Insulation Tests

SD-07 Certificates 1.4Statements

SD-08 Manufacturer’s Instructions 1.3Panelboards 2.1.1Panelboards

26 28 01.00 10 SD-03 Product Data 2.10Fault Current Analysis 2.10Protective Device Coordination

Study 2.1Equipment 1.4.1System Coordinator 3.3.5Protective Relays 3.2Installation

SD-06 Test Reports 3.3Field Testing

SD-07 Certificates 1.6Devices and Equipment

26 28 21.00 40 SD-02 Shop Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 38 PAGES

26 28 21.00 40 2.1Connection Diagrams 2.1Fabrication Drawings 2.1Installation Drawings

SD-03 Product Data 2.1Equipment and Performance

Data 2.3.1Contacts 2.3.2Indicating Lights 2.3.3Terminal Board 2.2.2Enclosures 2.5Accessories

SD-06 Test Reports 1.3Qualification Testing 1.3Operation Tests

SD-08 Manufacturer’s Instructions 2.3.2Automatic Transfer Switch

26 32 14.00 10 SD-02 Shop Drawings 1.4.3Detailed Drawings 3.10Acceptance

SD-03 Product Data 2.4Manufacturer's Catalog 3.9Instructions 1.4.2Experience 3.2General Installation 3.1Site Visit

SD-05 Design Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 38 PAGES

26 32 14.00 10 2.8Sound Limitations 2.14Generator 2.5.4Integral Main Fuel Storage Tank

Power Factor 2.7.2Heat Exchanger 2.18.5Time-Delay on Alarms 2.7Cooling System 1.2.5Vibration Isolation

SD-06 Test Reports 3.5.6Performance Tests 3.5Onsite Inspection and Tests

SD-07 Certificates 1.2.5Vibration Isolation 3.4Prototype Tests 1.2.6Reliability and Durability 2.11Emissions 2.8Sound limitations 2.14.1Current Balance 2.3Materials and Equipment 2.27Factory Inspection and Tests 3.5.4Inspections 2.7Cooling System

SD-10 Operation and Maintenance Data

1.6.1Operation Manual 1.6.2Maintenance Manual

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 38 PAGES

26 32 14.00 10 1.6.3Extra Materials 26 32 33.00 10 SD-02 Shop Drawings

1.2UPS System 3.2Installation

SD-03 Product Data 1.2.4Performance Requirements 1.7Spare Parts

3.5 GField Training

SD-06 Test Reports 2.12Factory Testing 3.3Field Supervision, Startup and

Testing SD-10 Operation and Maintenance Data

3.5Operating and Maintenance Manuals

26 51 00.00 40 SD-03 Product Data

2.2.1 GFluorescent Lighting Fixtures

2.2.1.1 GFluorescent Electronic Ballasts

GFluorescent Electromagnetic Ballasts

2.2.1.2 GFluorescent Lamps

1.3.1 GEnergy Efficiency Data

GEnclosed and Gasketed Vapor-Tight Fixtures

2.4.1 GLowering Devices

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 38 PAGES

26 51 00.00 40 SD-04 Samples GLighting Fixtures

SD-07 Certificates GEnergy Star Documentation

SD-10 Operation and Maintenance Data

1.3.1Operational Service 26 56 00 SD-01 Preconstruction Submittals

GPhotometric Plan SD-02 Shop Drawings

1.5.1.1 GLuminaire drawings

SD-03 Product Data

2.2 GFluorescent, Luminaires

2.2.2 GLuminaire Light Sources

2.2.3 GLuminaire Ballasts,

2.3.1 GPhotocell

SD-05 Design Data

1.5.2 GDesign Data for luminaires

SD-06 Test Reports 3.2Operating test

SD-07 Certificates GLuminaire Useful Life Certificate

SD-10 Operation and Maintenance Data

1.6.1Electronic Ballast Warranty Operational Service

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 38 PAGES

27 10 00 SD-02 Shop Drawings

1.6.1.1 GTelecommunications drawings

1.6.1.2 GTelecommunications Space

Drawings SD-03 Product Data

2.4 GTelecommunications cabling

2.5.5 GPatch panels

2.6 GTelecommunications

outlet/connector assemblies GEquipment support frame

SD-06 Test Reports

3.5.1 GTelecommunications cabling

testing SD-07 Certificates

1.6.2.1 GTelecommunications Contractor

1.6.2.2 GKey Personnel

1.6.2.3 GManufacturer Qualifications

1.6.3 GTest plan

SD-09 Manufacturer’s Field Reports

2.12.1 GFactory reel tests

SD-10 Operation and Maintenance Data

1.10.1 GTelecommunications cabling and

pathway system

SD-11 Closeout Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 38 PAGES

27 10 00 1.10.2 GRecord Documentation 27 41 16 SD-02 Shop Drawings

Shop and Integration Drawings 1.3.3As-built Drawings

SD-03 Product Data Product Data Video Wall Video Wall Support System Video Wall Controller Video Switcher Audio Switcher Speakers Microphones wired and wireless Monitors

SD-05 Design Data Design Data

SD-06 Test Reports Test Reports Integration Plan Final acceptance test and operational test procedure

SD-10 Operation and Maintenance Data Maintenance Manuals

SD-11 Closeout Submittals 1.3.3As-built Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 38 PAGES

27 41 16 Training Certificates 28 23 23.00 10 SD-02 Shop Drawings

1.4.2.4Graphics 1.3.3As-built Drawings

SD-03 Product Data 1.4CCTV Technical Data Packages 3.6.9Software Updates

SD-06 Test Reports 1.4.2Performance Verification Test 1.3.2Test Procedures and Reports

SD-08 Manufacturer’s Instructions 1.4.3Group V Technical Data Package

SD-10 Operation and Maintenance Data

1.4.2.1Operation and Maintenance Manuals

3.4.2Operator's Training Report SD-11 Closeout Submittals

1.4.2.3Data Entry 28 31 00.00 10 SD-02 Shop Drawings

1.6.5Detail Drawings SD-03 Product Data

2.4Storage Batteries 1.2.2Low Battery Voltage 1.5Spare Parts

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 38 PAGES

28 31 00.00 10 1.7 GTechnical Data and Computer Software

3.6Training 3.7Testing

SD-06 Test Reports 3.7Testing

SD-07 Certificates 1.2Equipment 1.6.1Qualifications

SD-10 Operation and Maintenance Data

1.4Operating and Maintenance Instructions

1.7Technical Data and Computer Software

31 00 00 SD-01 Preconstruction Submittals

3.5 GShoring

SD-03 Product Data 3.9Utilization of Excavated Materials

SD-06 Test Reports 3.17Testing 2.1Borrow Site Testing

SD-07 Certificates 3.17Testing

31 11 00 SD-03 Product Data 3.6.1Nonsaleable Materials

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 38 PAGES

31 23 00.00 20 SD-06 Test Reports 1.6Borrow Site Testing 3.11.2.1Fill and backfill 3.11.2.2Select material 3.11.2.3Porous fill 3.11.2.4Density tests 3.11.2.5Moisture Content Tests

31 60 00 SD-03 Product Data 3.2.1.1Tools

32 92 23 SD-03 Product Data 2.3Fertilizer

SD-06 Test Reports Topsoil composition tests

SD-07 Certificates 2.1sods

33 11 00 SD-03 Product Data 2.1.1Piping Materials 2.1Water distribution main 2.2Water service line

Corporation stops 2.1.2.2Valve boxes 2.2.2.2Valve boxes

SD-06 Test Reports 2.2.2.4Disinfection

SD-07 Certificates 2.1Water distribution main

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 38 PAGES

33 11 00 2.2Water service line Displacement Type Meters Compound Type Meters

SD-08 Manufacturer’s Instructions 1.3Delivery, storage, and handling

Installation 33 30 00 SD-01 Preconstruction Submittals

Existing Conditions SD-02 Shop Drawings

1.4.1Drawings 2.3.1Precast concrete manhole 2.3.3.1Frames, covers, and gratings

SD-03 Product Data 2.1Pipeline materials

SD-06 Test Reports 2.4Reports

SD-07 Certificates Gaskets

33 40 00 SD-03 Product Data 3.3Placing Pipe

SD-04 Samples 2.1Pipe for Culverts and Storm

Drains SD-07 Certificates

2.1.1Resin Certification 3.7Pipeline Testing

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 38 PAGES

33 40 00 3.6.5Determination of Density 2.3.5Frame and Cover for Gratings

33 70 02.00 10 SD-02 Shop Drawings

1.4.1 GDetail Drawings

1.4.2 GAs-Built Drawings

SD-03 Product Data

2.2 GNameplates

2.1 GMaterial and Equipment

3.2 GInstallation Requirements

SD-06 Test Reports Factory Tests

3.9Field Testing 3.9.8Operating Tests 3.3.1.4Cable Installation

SD-07 Certificates 2.1Material and Equipment 3.10.2Installation Engineer

SD-10 Operation and Maintenance Data

3.10.1Operation and Maintenance Manuals

33 71 01.00 40 SD-03 Product Data

2.6 GConductors

2.5 GInsulators

2.2.1 GConcrete poles

2.17 GNameplates

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 38 PAGES

33 71 01.00 40 GPole top switch GRecloser GSectionalizer

2.12 GCutouts

2.14 GTransformer

GMetering equipment GMeters

2.11 GSurge arresters

2.7Guy strand 2.9Anchors

SD-05 Design Data

2.2.1 GConcrete poles

SD-06 Test Reports GField Test Plan

3.6 GField Quality Control

1.5.3 GGround resistance test reports

SD-07 Certificates

2.2.1 GConcrete poles

2.14.1 GTransformer Losses

SD-09 Manufacturer’s Field Reports

2.18.2 Groutine and other tests

SD-10 Operation and Maintenance Data

1.6.1 GOperation and Maintenance

Manuals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 38 OF 38 PAGES

33 71 01.00 40 SD-11 Closeout Submittals

2.18.1 GTransformer test schedule

33 71 02 SD-03 Product Data Low voltage cable Low voltage cable terminations Sealing Material

2.11.2Manhole frames and covers 2.11.3Handhole frames and covers

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

File details come from the government source that posted it. Updated .