Statement_of_Work_-_Striping_and_Sealing.pdf

PDF 1 MB Posted

Attached to
Striping and Sealing
Solicitation number
140P6425Q0048
Issued by

About this file

This is a Statement of Work (SOW) for a parking lot pavement seal and stripe project at the Lincoln Home National Historic Site in Springfield, Illinois. The project involves seal coating approximately 28,800 square feet in the Visitor Parking lot (restriping 71 parking spaces, including 7 directional arrows and 3 handicap spaces) and approximately 14,350 square feet in the Bus Parking Lot (restriping 9 bus parking spaces and 6 directional arrows). The work requires specific materials including asphalt rubber crack sealant, emulsified asphalt pavement sealant, and waterborne traffic paint, with detailed application methods such as crack cleaning, routing, and two-coat sealant application. The project has a 90-calendar day performance period, with work to be conducted primarily during normal business hours, and requires maintaining public access to a minimum of 40 parking spaces throughout the project.

The SOW specifies strict technical requirements for surface preparation, sealant application, and striping, including temperature restrictions, surface cleaning protocols, and paint color specifications (white for parking stripes, crosswalks, and road edge lines; blue and white for handicap symbols). The contractor must provide photo documentation, comply with environmental and safety regulations, and submit a traffic control plan. The project includes a one-year workmanship warranty, and the contractor must provide manufacturer warranty information and operation manuals for installed products. The work is part of the National Park Service's efforts to preserve the historic site's neighborhood and enhance visitor experience.

View the file

Other files

File Type Posted
Striping_and_Sealing_Q_A_0001.pdf PDF
Sol_140P6425Q0048_Amd_0001.pdf PDF
Sol_140P6425Q0048.pdf PDF
DOL_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Service Contract Requirements V. 2021-10-18 Page | 1

LINCOLN HOME NATIONAL HISTORIC SITE

SPRINGFIELD, ILLINOIS

PARKING LOT PAVEMENT SEAL AND STRIPE

PMIS 318282

PROJECT STATEMENT OF WORK

NATIONAL PARK SERVICE

8 APRIL 2025

Page | 2

TABLE OF CONTENTS

Service General Requirements

Service General Requirements

DRAWINGS

-Drawings

-Site Map with Project Location

SERVICE GENERAL REQUIREMENTS

Page | 3

PART 1 – GENERAL

ITEM 1 – LOCATION AND DESCRIPTION OF WORK

1.1 Background: Lincoln Home National Historic Site preserves fourteen historic houses and associated outbuildings, within its four-square city blocks, 12.24 acre boundary, that date from the Lincoln-era, including the Lincoln Home. Through neighborhood preservation and interpretive activities, the National Park Service seeks to recreate a vivid sense of the relationship of the Lincoln family to their neighbors and the broader Springfield community, enriching the experience of visitors at Lincoln Home National Historic Site.

1.2 Work Covered by the Contract Documents:

A. Project Location: 413 South 8th Street, Springfield, Illinois 62701 B. Work consists of: Project includes seal coating approximately 28,800 square feet in the Visitor

Parking lot and restriping 71 parking spaces with numbers, 7 directional arrows and 3 handicap spaces. Seal coating approximately 14,350 square feet in the Bus Parking Lot and restriping 9 bus parking spaces and 6 directional arrows. All spaces and numbering assignments are included on the attached maps/drawings. Work shall specifically include the following:

1. Materials:

A. Crack Sealant. Asphalt rubber or rubberized asphalt (ASTM D 3405) or Low-modulus rubberized asphalt (state-modified ASTM D 3405) suitable for the local temperatures.

B. Pavement Sealant. Emulsified asphalt. Use of coal tar emulsion is not allowed.

1. Emulsified asphalt shall be either grade SS1h or AE-NT. Clay stabilized emulsion with a ph not greater than 7.0, and a solids content of not less than 45 percent by mass may be used. Water shall be potable and of such quality that the water will not separate from the emulsion before the material is placed in the work. Mineral aggregate components shall be 100% passing the #16 mesh sieve. These components shall be natural or manufactured material consisting of clean, hard, durable, uncoated particles that are clean and free from decomposed materials, organic materials and other deleterious substances.

2. Oilseal. Oilseal shall be a quick drying latex emulsion with suitable admixtures manufactured specifically for the purpose of isolating asphalt sealcoat from any residual oils, petroleum grease, and gasoline stained pavement. The properties of the oilseal shall be compatible with the pavement sealant.

3. Tack coat. The tack coat shall consist of one part SS1h with 4 parts water or 2 parts asphalt sealcoat with one part water.

C. Waterborne Traffic Paint. Furnish an acrylic water based ready-mixed paint for use on asphalt and hydraulic cement. Paint shall be composed of resin solids of 100 percent acrylic polymer with the exact formulation determined by the manufacturer. It shall meet the specifications of the local state DOT. The paint shall dry to no pickup in 15 minutes maximum.

2. Construction Methods.

Page | 4

A. Crack Sealant (all cracks ¼-inch & wider) All cracks ¼-inch to 1-inch wide shall be cleaned, routed and sealed before sealcoating. Cracks wider than one inch shall be filled with a fine aggregate, hot, dense-graded asphalt concrete, conforming to a State DOT 3/8-inch maximum asphalt concrete.

1. Cleaning/weed removal. Cracks shall be cleaned of all weeds and debris prior to cracksealing. Cracks shall be cleaned by high pressure air blasting or any other method that leaves a clean dry surface.

2. Routing. Recommended width ½ - 1 inch. Depth ½ -3/4 inch, 1-inch maximum.

3. Filling. Flush fill (1st choice) or overband (do not use overbanding in parking lots or other areas with foot traffic) Cracks shall be treated with a heat lance, or hot air lance, before sealant installation. Sealant should never set higher than 1/8 inch above the pavement.

B. Pavement Sealant

1. Prior to application, all areas shall be power swept, vacuumed, and cleared of all loose material. All adjacent concrete structures (driveways, walks, gutters, garages, etc.) shall be cleaned of all dirt dust, and debris prior to applying any materials to the areas designated for sealcoating. Any standing or puddle water shall be spread over the surface and dried before any sealer is applied.

2. Oil spots shall be manually scraped and cleaned with a mild detergent in order to promote adhesion of the sealcoat. After cleaning the areas described above, the areas shall be sealed with an oil seal

3. On excessively weathered surfaces, pavement surfaces previously sealed with coal tar-based sealants, or areas such that cleaning operations leave a film of dust, a tack coat shall be applied at a rate of 0.05 to 0.10 gallon/square yard. The tack coat must be dry prior to application of the asphalt sealcoat. Area affected is about approximately 10%.

4. All manholes, adjacent concrete structures shall be protected from overspray.

5. Emulsion sealcoat shall be applied only if ambient air temperature is 55°F or higher or if minimum surface temperature is 60°F or higher. Application of the sealcoat in ambient temperatures in excess of 80°F shall require pretreatment of the asphalt surface with a water mist. The surface must be damp without standing water.

6. Sealcoat shall not be applied within 24 hours prior to forecasted rain, during rain, or when the surface contains standing water.

7. Application of the asphalt sealcoat shall be by mechanical means using rubber-faced squeegees, brooms, distributor bar/wand, or a combination of these. Use of hand squeegee or brush application shall be restricted to areas not accessible to the mechanized equipment or to accommodate trim work adjacent to curbs or sidewalks, etc.

8. Asphalt sealcoat shall be applied in two coats. The first application of sealcoat must be thoroughly dry prior to application of the second coat. Asphalt sealcoat shall be applied uniformly over the prescribed area in continuous parallel lines in a manner so that no ridges or uncoated areas shall exist. Application rates based on two coats undiluted material shall be a minimum of 25 gallons per 1,000 square feet (SF).

9. The addition of #30 mesh sand with additional binder is required for the first coat.

The addition of sand shall be 2 to 3 pounds per gallon. Additional binder shall consist of 0.10 gallon of SS1h or 1-3% liquid latex binder per gallon undiluted asphalt sealcoat. The properties of the liquid latex shall be compatible with the asphalt sealcoat.

10. Traffic shall not be allowed on the asphalt sealcoat until the sealcoat is thoroughly cured, approximately 24 hours.

C. Striping. Sealcoat shall dry for minimum of 24 hours before striping is applied. Apply paint when the pavement and air temperatures are above 50°F. Apply two coats.

Page | 5

**********Apply each coat at a rate of 110 square feet per gallon. ********** rate could be as high as 210 SF/gal for each coat******

1. Road and parking marking colors shall be:

1. Parking stripes; white.

2. Crosswalks, handicap van-accessible parking space marking, stop limit lines; white.

3. Handicap symbols; blue and white.

4. Road edge lines; white.

D. Traffic Control:

1. All traffic control shall be accordance with the Manual of Uniform Traffic Control

Devices (MUTCD). The contractor shall submit a Traffic Control Plan to the CO a minimum of 21 days prior to the anticipated start date. No on site work will be authorized until the plan is approved.

C. All work will be performed under a single contract.

Period of performance: Work shall be completed within 90 calendar days. The period of performance is inclusive of 06 weather days.

ITEM 2 - EXISTING UTILITIES

2.1 N/A

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. Laws & Policies - Lincoln Home National Historic Site (U.S. National Park Service) (nps.gov)

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the site or within the park unless approved by the Contracting Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

D. The Government will occupy the main parking lot for duration of the project. The contractor shall coordinate construction operations with the COR to minimize conflicts and facilitate Government usage of the site.

E. The contractor shall maintain access to the Visitor Center parking area at all times. A minimum of 40 parking spaces shall be available to the public at all times during the project.

F. The Bus lot drive can be closed to the public for construction operations.

Page | 6

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day Inauguration Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday;

holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area. Do not disturb areas beyond the pavement. The contractor shall confine construction staging operations and material storage as directed by the Contracting Officer’s Representative (COR). Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Limits: The Visitor parking lot will be open during construction. Contractor is always to keep one lane for entry/exit of the parking lot unobstructed. Bus Lot can be closed for work.

C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

D. Do Not disturb site. The contractor shall protect from damage (including overspray) all curbing, wheel stops, signage, vegetation, traffic counters, inlets, and sidewalks..

E. Utilities

a. General: Cost or use charges for temporary facilities shall be included in the Contract

Sum as required.

Page | 7

b. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for operations without any additional permit costs. Use resources wisely and minimize waste of water.

c. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for operations without any additional permit costs. Power may or may not meet your power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

d. Toilets: Public restrooms are available at the Visitors Center.

F. Security and Protection facilities:

1 Environmental Protection: Provide protection, operate temporary facilities, and conduct work in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2 Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all service equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Disassembly of equipment components or specialized inspection tools are not required.

3 Tree and Plant Protection: N/A

3.4 Storage - Staging Areas:

A. Confine Storage of materials and equipment to the project staging area within the allowed use of the parking lot. Specific storage units shall be provided by the contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR.

Security of the materials and equipment on site is the Contractor’s responsibility.

3.5 Preservation of Natural Features: N/A

3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

a. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

b. Address Recycling: Government goal is to salvage and recycle as much nonhazardous waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Photo Documentation:

Page | 8

Contractor must provide existing condition, progress and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email within 7 days from time of taken or as approved by COR.

3.9 Fire and Life Safety:

4 Comply with the requirements of NFPA.

5 Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov).

Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

i. Immediately report all spills of hazardous materials to the CO, COR and park.

ii. Maintain a spill emergency response kit.

iii. Train employees how to respond to a spill and use an emergency response kit.

3.10 Noise and Acoustics Management: N/A

ITEM 4 - EXAMINATION OF THE SITE

4.1 All interested contractors are urged to visit the job site and examine existing conditions before submitting quotes. Contractors will be expected to complete the work as quoted.

ITEM 5 – SUBMITTALS

5.1 General Submittal Procedures:

A. General: Prepare and submit submittals for approved equipment as specified

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting Officer.

2. All bidders are urged to visit the job site and examine existing conditions before submitting bids. Contractors will be accountable for understanding existing conditions.

No cost changes for items visible during site visit will be allowed.

5.2 Shop Drawings, Product Data, and Samples: N/A

ITEM 6 – TEMPORARY SERVICES

6.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.

ITEM 7 - PROJECT CLOSEOUT

Page | 9

7.1 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for intended use.

7.2 Completion: Contractor shall request a final inspection to the Contracting Officer and COR.

7.3 Warranties

A. Workmanship Warranty will be based on project acceptance and will remain in effect for 1 year following acceptance. The contractor will also support manufacturer warrantied items and repair work during this period.

B. Provide all manufacturer warranty information of products installed. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

END OF SECTION

Page | 10