Statement of Work.pdf
PDF 228 KB Posted
- Attached to
- Methyl Methacrylate (MMA) Floor Coating Repair
- Solicitation number
- 12505B24R0017
About this file
This document is a Statement of Work (SOW) for a project to repair the Methyl Methacrylate (MMA) floor coating in Building 5, Room 19 at the National Centers for Animal Health (NCAH) in Ames, Iowa, which is owned by the United States Department of Agriculture (USDA).
The SOW requires the contractor to prepare the existing floor surface and apply a new MMA floor coating with a 6mm flint traction coat and 46 mesh white aluminum oxide in designated areas, totaling 430 square feet. The contractor is responsible for all labor, materials, disposal, and equipment. The period of performance is 180 days, with the actual work to be completed within 14 days once the room is available. The contractor must submit product data, a project schedule, a safety policy, and warranty documentation. The work must be performed during normal business hours and comply with site security and access requirements. The existing USDA utilities can be used at no cost to the contractor. This is a Total Small Business Set-Aside with a NAICS code of 238338 (Flooring Contractors) and a size standard of $19.0 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFIs.pdf | ||
| Site Visit Sign-In May 08.pdf | ||
| Site Visit Sign-In May 07.pdf | ||
| SF30 - Amendment 01.pdf | ||
| Wage Determination.pdf | ||
| ARS-371.pdf | ||
| Past Performance Questionnaire.pdf | ||
| Drawings and Photos.pdf | ||
| ARS-372.pdf | ||
| SF-1442.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) Project: Building 5 Room 19 Animal Entry-Holding Methyl
Methacrylate (MMA) Floor Coating Repair
GENERAL INFORMATION
1.0 Scope of Work: The United States Department of Agriculture (USDA), National
Centers for Animal Health (NCAH) Building 5 located at 1920 Dayton Avenue, Ames, IA has an existing eight-year-old MMA floor coating that has a worn surface that needs a more aggressive traction coating for large animal traffic and caretakers.
We need the floor surface prepared to accept a new MMA coating with a 6 mm flint traction coat and a 46 mesh white aluminum oxide traction coating areas designated on the attached drawing. The total area is 430 square feet. Integral base does not have to be recoated, but the finished coating must adhere correctly to the existing integral base for a watertight seal in the corners with no gaps or voids.
Additional grinding will be required under the interior door that swings into Room 19 so the door does not interfere with the new floor coating (presently 1/8” or less clearance). The door cannot be modified.
2.0 Background: The existing Building 5 MMA floor coating was installed during a resurfacing project in 2015 using BASF MasterTop 1855 SRS CP product. The goal is to install a new MMA floor coating in the Room 19 Animal Entry-Holding to increase traction for large animals to reduce the chance of slipping or falling and endangering the animal or care takers. Attached is drawing A-101 with the Building 5 Room 19 location, construction route and room details.
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks: The contractor is responsible for all labor, material, disposal, and equipment to complete the work. The work required to install the new MMA coating includes:
1. The length of the contract will be 180 days after award of contract and the work must be completed within 14 days once the room is available.
2. Submit MMA product and Safety Data Sheets for BASF MasterTop 1855 SRS CP MMA Flooring System, or equivalent – Clear with a 6 mm flint brown/tan traction coat and the 46 mesh white aluminum oxide in dark gray base coat with two clear topcoats.
3. Provide schedule for the work no later than 10 days after the award of the Contract.
4. Submit contractor safety policy for review by COR at least 10 business days prior to starting work on site.
5. The work must be completed during normal business hours 7am to 5 pm excluding Government Holidays.
6. Contractor is responsible for removing and reinstalling gates, head chute or any items that are removed to complete the work and reinstall without damaging the new floor coatings.
7. Contractor is responsible for the restoration or repair of any damages to structures, finishes, site grounds or surroundings. Damages to be restored to the same condition or better at no additional cost to Government.
8. Contractor is responsible for completing a bond test that is witnessed by the COR or other authorized representative using the product to verify mix and adhesion to the existing floor prior to proceeding with the final installation.
9. Prepare surfaces in accordance with manufacturer instructions. Any work necessary to use mechanical means (self-contained grinding and /or shotblasting) must have a HEPA vacuum system to collect dust.
10. Prefill surface irregularities holes and cracks if necessary.
11. Apply activator for the MasterTop SRS, or equivalent, product per manufacturer instructions.
12. Apply adhesion coat for the MasterTop SRS, or equivalent, clear colored product per manufacturer instructions.
13. Broadcast to rejection 6 mm flint traction coat and 46 mesh aluminum oxide in areas shown on the attached drawing A-101. Let the adhesion coat cure and vacuum to remove loose material.
12. Apply first clear topcoat of the MasterTop, or equivalent, clear sealer and let cure.
13. Apply second clear topcoat of the MasterTop, or equivalent, clear sealer and let cure.
14. All work to be performed per Manufacturer’s specifications and details.
15. Remove all trash or debris accumulated from completing the work from the site and dispose of in a responsible manner.
16. Provide documentation for a minimum of a three year material and labor warranty that starts after completion of the work.
3.0A Product Specifications
• The recommended product to use for the floor coating is MasterTop 1855 SRS CP Methyl Methacrylate (MMA) floor coating system with a clear color. An equivalent will be considered. Submit product specifications with proposal.
Traction material shall be 6m flint brown/tan in color and 46 mesh white aluminum oxide in a dark gray base coat in the areas shown on the attached drawing A-101 with two clear topcoats over the traction material.
3.0B Warranty/Closeout
Provide a minimum of a three year warranty for labor to repair of faulty workmanship and material. The warranty shall start at the completion of the project. The contractor shall provide technical specifications and product information along with the cost proposal. An award will not be completed until the product has been determined to be acceptable.
3.1 Work Restrictions & Conditions
A. Site Security Access
a. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/subcontractor employees shall sign-in and out at the main entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of each work day. A current government-issued identification with a picture ID is required for entry.
b. This project construction site is located in the limited access zone.
c. Construction vehicles and a construction trailer will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.
d. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.
e. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.
f. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.
g. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.
h. No pets or animals are allowed inside the Security Gate, even if left in vehicle.
i. No firearms or weapons are allowed on site.
B. Work Hours: Regular work hours for the site are 7:00am to 5:00pm, Monday through Friday, excluding Government holidays.
C. Work Outside Regular Work Hours: Will not be allowed.
3.2 Temporary Facilities
A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any temporary utility connections.
B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.
C. Construction Trailer: Will be allowed for the Project with location to be coordinated with COR.
D. Toilet Facilities: The Contractor shall provide a portable toilet and services to maintain the toilet facilities, placement and removal after the work has been completed. The location is to be coordinated with the COR.
3.3 Warranty Documentation
1. Warranty List: Provide a 3 year warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic PDF file to the COR.
2. Warranty Copies in Binder: Provide the COR one signed & dated copy of all warranties for products and equipment installed on the project. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.
4.0 Government Furnished: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The room has one 20 Amp. 120V single phase power circuit. The Contractor shall be responsible for making and removing any temporary utility connections. The Contractor may use larger floor preparation equipment with appropriate HEPA vacuum capture system, but they will need to provide their own portable generator, fuel and power cables to operate the equipment outside Building 5. Construction trailer may be used for the project with the location coordinated with COR. The COR or Location Coordinator will direct Contractor to parking available near the Building 5 Room 19 Exterior Entry and available parking spaces on concrete as directed.
5.0 Deliverables / Schedule
Item No.
Deliverable
Objective
Due
1 Project Schedule Defining the responsibilities, timeline, risks, and milestones of contract objectives. Ref. Subtask 3.0.3
No later than five
(10) business days after contract award
2 Contractor Safety Policy.
For review and approval by COR.
Ref. Sub Task 3.0.4
Ten business days before starting work on site.
3 Material Submittal Defining the characteristics of the materials used to complete the project.
Ref. Subtask 3.0.2
No later than five
(10) business days after contract award
4 Warranty For review and approval by COR.
Ref. Sub Task 3.0.16, 3.0B & 3.3.1 & 2
At completion of project.
6.0 Place of Performance:
USDA, National Centers for Animal Health, 1920 Dayton Avenue, Ames, IA 50010
7.0 Technical Point of Contact:
TBA
| 3.1 Work Restrictions & Conditions |
| A. Site Security Access |
| a. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/subcontractor employees shall sign-in and out at the main entrance gate and wear a contractor/visitor identification... |
| b. This project construction site is located in the limited access zone. |
| c. Construction vehicles and a construction trailer will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots. |
| d. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative. |
| e. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons... |
| f. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs. |
| g. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals. |
| 3.2 Temporary Facilities |
| A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any temporary utility connections. |
| B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project. |
| C. Construction Trailer: Will be allowed for the Project with location to be coordinated with COR. |
| D. Toilet Facilities: The Contractor shall provide a portable toilet and services to maintain the toilet facilities, placement and removal after the work has been completed. The location is to be coordinated with the COR. |
| 3.3 Warranty Documentation |
| 1. Warranty List: Provide a 3 year warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic PDF file to the COR. |
| 2. Warranty Copies in Binder: Provide the COR one signed & dated copy of all warranties for products and equipment installed on the project. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-ou... |