N2 Modernization Phase 4

Statement of Work (SoW) FEU Project #23006

USDA – NCAH

1920 Dayton Avenue

Ames, Iowa 50010

GENERAL INFORMATION:

1.0 Scope of Work:

The scope of this project is to replace the soon to be discontinued Johnson Controls (JCI) Building Automation supervisory and N2 hardware and communication wiring to the most currently available components to meet BACnet Standards. Program system to operate in the new Metasys User Interface (MUI).

2.0 Background:

The location, apart from Building 20 CLF, has had the HVAC, lighting, laboratory room controls, and other automated control functions controlled by Johnson Controls Building Automation System: PMI and Metasys. PMI software and network components were phased out and replaced with the new Metasys web-based components at the end of the 20th century. The PMI Network Control Modules were replaced with the Network Automated Engines. The field controllers, to this point, communicated via an 18-gauge 3 conductor cable: Johnson Controls N2/RS-485 with 9,600 Baud Rate. In 2016, all the DX-9100 digital controllers were replaced with new advanced field equipment BACnet controllers. This change occurred because the controllers had reached their end-of-life and were discontinued by JCI. The new controllers are communicating via the JCI N2 protocol. N2 is a slower communicating protocol than BACnet/MSTP: 22-gauge 4 conductor cable @ 38,400 Baud Rate. There are still several old N2 controllers that are obsolete and need updating to the new CGM series of BACnet controllers. The Network Automated Engines will be replaced with the Smart Network Engines, which have more memory and processing capability, a smaller physical footprint, and no battery to maintain. System shall be converted to the new Metasys User Interface (MUI). This enhancement will provide more ease of operations for the user/operators, as well as other system operating and troubleshooting capabilities.

The result of installing the new hardware components and communication wiring will make the Building Automation System more robust, highly improving the control and acquisition of data and data transfers to storage, graphical and control logic speed, and reliability of processes, and giving us a system that is at the industry current standards to meet the needs and demands that the current system will not be able to achieve with discontinued hardware.

All equipment, network engines/controllers and BACnet devices, listed in the Statement of Work is located on the isolated NCAH Building Automation Network and DOES NOT communicate to the USDA Enterprise Network.

CONTRACTOR REQUIREMENTS

3.0 Technical Requirements/Tasks:

Contractor shall provide labor, material, and equipment to perform the tasks stated below. Any parts/material directly related to the controls and controllers found defective during the work tasks shall be brought to the attention of the contracting officer’s representative for handling determination. Moving existing controllers and reconfiguring to new BACnet trunks shall be done a single panel at a time to limit “down time” of panel to the system. Contractor shall provide owner trainer on new Metasys User Interface (MUI).

A. Building 7:

a. Supply and install (1) SNE22000-0 Smart Network Engines to replace

NAE12.

b. Remove existing N2 communication trunk cables and install new BACnet MS/TP cables for SNE12.

c. Remove the (13) AS-UNT DEVICES.

d. Supply, install, and program (1) CGM09090-0 to replace the (1) AS-UNT devices. Repeaters installed as necessary.

e. Move existing N2 FAC and IOM to new BACnet trunk and switch the controllers from N2 to BACnet software configuration.

f. Program controllers to new Metasys User Interface (MUI).

g. Map points to Metasys System: All Items, logics, user views, graphics, trends, trend studies, alarms, and schedules.

B. Building 9:

a. Supply and install (1) SNE22000-0 Smart Network Engines to replace NAE04. No Tek-Air devices on this NAE.

b. Remove existing N2 communication trunk cables and install new BACnet MS/TP cables for NAE20 and NCE15.

c. Supply, install, and program (3) CGM09090-0 to replace the (3) AS-UNT devices. Repeaters installed as necessary.

d. Move existing N2 FAC and IOM to new BACnet trunk and switch the controllers from N2 to BACnet software configuration.

e. Program controllers to new Metasys User Interface (MUI).

f. Map points to Metasys System: All Items, logics, user views, graphics, trends, trend studies, alarms, and schedules.

g. Checkout and verify proper operation of all controllers and logics.

GENERAL REQUIREMENTS

4.0 Work Restrictions & Conditions

A. Site Security Access:

a. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor and subcontractor employees shall always sign-in and out at the main site entrance gate and wear a contractor/visitor identification badge while on the site. The ID badges will be turned in at the end of the workday. A current government-issued identification with a picture ID is required for entry.

b. Access to each individual site shall be arranged by the Contracting Officer's Representative according to the schedule submitted by the contractor and approved by the Contracting Officer’s Representative. The contractor shall coordinate and schedule his/her work under this contract to cause the least interference with the normal flow of visitor and employee traffic.

c. Construction vehicles will be allowed access to the contracted buildings.;

contractor employee’s personal vehicles shall be parked in the facility parking lots designated by the Contracting Officer’s Representative.

d. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.

e. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but not limited to, disease control and health requirements.

f. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided by the Contracting Officer’s Representative if the situation occurs.

g. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.

h. Work Hours: Regular work hours for the site are 7:00AM to 4:30PM, Monday through Friday, excluding Government holidays. Requests for exceptions to this schedule shall be made in writing forty-eight (48) hours in advance and approved by the Contracting Officer's Representative.

i. Construct Work in stages to accommodate Owner’s use of premises during construction period. Coordinate construction schedule and operations with Contracting Office’s Representative.

j. Coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment.

k. Assume full responsibility for protection and safekeeping of items under this Agreement, stored on site.

l. Move any stored items, under Contractor’s control, which interfere with operations of Owner or separate contractor.

m. Obtain and pay for use of additional storage or Work areas needed for operations.

n. Owner will occupy premises during entire period of construction for conduct of its normal operations. Coordinate with Owner’s Representative/COR in all construction operations to minimize conflict, and to facilitate Owner usage. Contractor shall always conduct its operations as to ensure least inconvenience to Owner.

4.1 Work Restrictions & Conditions

B. Use of Premises:

a. Limit use of premises to work areas. Do not disturb portions of site beyond areas in which the work is approved.

b. Keep driveways, entrances, walkways, and doorways serving premises clear and available to the Government, employees, visitors, and emergency vehicles always. Do not use these areas for parking or storage of materials.

c. Limited parking may be available on the site away from each facility.

d. The contractor shall provide a list of all staff employees that will be working on the project to the Contracting Officer’s Representative (COR) a minimum of three days in advance. The contractors that will be onsite will be required to provide a valid driver’s license and be a valid United States Citizen to be able to access campus.

e. Once onsite, contractors will be escorted by a USDA employee to the location of the work and will always be escorted while onsite.

C. Adherence to Security Policies and Procedures:

a. The Contractor shall adhere to ALL Site, ARS, APHIS and USDA security policies and procedures including Code of Federal Regulations Requirements, Standard Operating Procedures, Security Directives, Security Procedures, General Orders, Post Orders and any applicable Government Policies and Procedures.

b. Failure to adhere to or violation of any above listed requirements, procedures, directives, orders and/or policies may result in criminal prosecution or contractor representative or contractor employee (violator) removal.

4.2 Regulatory Requirements

A. The equipment materials, installation, workmanship, and operation shall conform to the most stringent applicable requirements of the most recent editions of the associated publications, in the below section and in the attached specifications unless otherwise noted:

a. National Fire Protection Association (NFPA)

(a) NFPA 101 – Safety to Life from Fire in Buildings and Structures.

(b) NFPA 1 – Uniform Fire Code

(c) NFPA 5000 – Building Construction and Safety Code

b. Underwriters Laboratories, Inc. (UL)

(a) Appropriate UL Standards

c. State and Local Building Codes as adopted by the Authority Having Jurisdiction (AHJ).

d. The Uniform Federal Accessibility Standards (UFAS)

e. Occupational Safety and Health Administration (OSHA)

f. Architectural Barriers Act (ABA)

g. Equipment Manufacturer Printed Instructions

4.3 Coordination

A. The contractor shall coordinate all work with the Contracting Officer's Representative.

B. The contractor shall submit an installation schedule for review and approval by the Contracting Officer's Representative within ten (10) days of task order award.

C. The contractor shall be solely responsible for coordinating work with all subcontractors and ensuring that all items of joint use in conjunction with installations are completed.

4.4 Special Provisions

A. Finished surfaces of existing facilities that are affected, marred, scratched, or damaged by the contractor shall be refinished to match original condition.

a. Patching material shall be of the same type, style, and thickness, and shall be finished to match existing adjacent surface construction in color and texture.

b. Patching material, paint color, paint material and paint application methods shall be approved in advance by the Contracting Officer’s Representative.

B. No building structural members shall be cut or altered without prior approval of the Contracting Officer's Representative.

C. Any damage resulting from contractor's operation shall be brought to the attention of the Contracting Officer's Representative immediately.

D. The contractor shall take all necessary and reasonable measures to keep the work site clean of trash and debris. Work areas shall be cleaned immediately as work in that area is completed, and before moving to a new work site. Place all trash and debris in OSHA approved containers, remove, and dispose of trash off site daily.

E. The contractor shall move all materials, and equipment, including ladders and scaffolding from the site at the completion of each day's operation unless otherwise approved by the Contracting Officer's Representative.

F. The contractor shall provide proper safety equipment to workmen and always ensure a safe environment for employees and the public. The contractor shall work to ensure free, unobstructed, and safe access to and about the work area.

4.5 Temporary Facilities

A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any utility connections.

B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.

C. Toilet Facilities: The existing USDA toilet facilities may be used by the Contractor for completion of the contract work at no cost to the Contractor.

Locations of the facilities determined by the Contracting Officer’s Representative.

D. Dumpster/Roll-off: The Contractor may use USDA receptacles determined by the Contracting Officer’s Representative.

4.6 Lockout/Tagout

A. The Contractor and/or subcontractor employees who will be working on the job will apply a lockout/tagout (LOTO) process to control dangerous energy sources.

The Contractor/subcontractor shall have a LOTO program established and use Contractor LOTO locks, tags, and procedures.

B. The Contractor/subcontractor shall review their LOTO program with NCAH FEU personnel to coordinate LOTO programs before implementing LOTO.

4.7 Closeout Submittals

A. Warranty Documentation:

a. Warranty Copies in Binder: Provide one signed & dated copy of all warranties for cabling and controls installed on the project. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.

b. A (1) one-year warranty shall be provided for faulty workmanship and material. This includes software, programming, point mapping, and graphic issues. The warranty shall start at the completion of the project and approval of the Final Pay Application.

c. Contractor shall provide Check-out sheets to reflect the check-out and verifications done in Section 3.0 Technical Requirements/Tasks in the above Statement of Work.

B. Operation & Maintenance Manuals:

a. Contractor shall provide an electronic copy, in PDF format, of all Operation & Maintenance documentation provided with the controls systems installed in the project via email to the COR.

C. Record Drawings:

a. As-Built Drawings: Final As-Built drawings shall be provided to the COR.

Drawings to be emailed or hand delivered to the COR.

END OF SECTION