STATEMENT OF WORK
Replace HVAC System for TXANG at NAS JRB Fort Worth
Buildings 1670 and 1671 May 5, 2021
1. Background: The existing HVAC systems provide conditioned air to buildings 1670 and 1671 at NAS JRB Fort Worth, which support administrative and training functions, a variety of open and enclosed office spaces, and multi-use conference spaces. The two (2) existing Trane 40 Ton Model number: CGAEC404AEA1HJRTW (BOTH), Serial numbers:
J97G82364 (Bldg 1671) and J97G82365 (Bldg 1670) HVAC/chiller systems are deteriorating and require constant maintenance to keep running.
2. The contractor shall furnish all labor, parts, tools, plant, equipment, appliances, transportation and materials necessary. The contractor shall procure and install properly sized air-to-air chiller units for the required conditioned air spaces. Work shall include a power phase monitor on the new chillers to prevent damage to the unit in the event of improperly phased power. All work shall be performed in accordance with this Statement of Work (SOW) and associated specifications and drawings. All work shall also be performed in accordance with international, federal, state, local building codes, and Unified Facilities Criteria (UFC). (See Section 7. References).
3. Objectives: It is the government’s intent for the contractor to provide a turnkey HVAC replacement solution by providing two (2) 40 Ton Air Cooled Chiller systems that will maintain environmental conditions by a LON Network Controls (LNC) Network 8000 controller.
3.1. Contractor is highly encouraged to conduct a site visit prior to submitting a proposal for the work to better understand the requirements, site conditions, and work environment. The 136th Civil Engineer Squadron (CES) will obtain gate passes for all contractors and required personnel.
3.2. All government provided drawings or As-builts are for reference only. Contractor shall field verify all existing conditions and dimensions.
3.3. Contractor shall observe all applicable Occupational Safety and Health Administration (OSHA) and State safety precautions pertaining to the contract.
4. Tasks: The contractor shall perform the following, but not limited to:
4.1. The 40 Ton Carrier Air Cooled Chiller systems must include, but not limited to, the following:
• Chillers must utilize R-410a Refrigerant
• Must be compatible with 208/230V
• BACnet and LON Translator Control
• Crank Case Heater on all Compressors
• Heat Trace on Chilled Water Piping
• Security Grilles/Hail Guards
• Ships with bottom skid, top crate, and bag
• Power phase monitor with shutdown feature
• One (1) Carrier Navigator Display module per chiller
4.2. Reclaim refrigerant from existing chillers to be removed per approved EPA guidelines. Refrigerant will be left on site for TXANG to properly dispose of.
4.3. Remove existing chillers, chilled water (CHW) piping and other debris caused from construction. All materials to be reviewed by 136 CES personnel prior to disposal. TXANG reserves the right to repurpose parts/components of removed chillers to be used on other existing chiller systems elsewhere.
4.4. Contractor to furnish all required crane, rigging, transportation, hoisting, and securing for all equipment required for this project.
4.5. Rework existing new chiller housekeeper pads to allow for new equipment installation where applicable. All modifications must be made to match existing means and methods.
4.6. Provide labor and materials to install new chillers in place of existing chillers being removed.
4.7. Connect to all existing refrigerant relief piping and valves. Replace as required.
4.8. Furnish and install electrical as required to connect to the chiller systems. All electrical and instrumentation wiring shall comply with manufacturer’s requirements. Disconnect and reconnect electrical to include the following;
4.8.1. Lockout/Tag out the existing chiller disconnects in buildings
4.8.2. Disconnect conduit and wiring feeding the existing chillers
4.8.3. Provide and install new fusible disconnects
4.8.4. Provide and install wiring and conduit from new disconnects to new chiller panels
4.8.5. Check voltages and rotation
4.8.6. Label disconnects
4.9. Flush existing refrigerant piping and replace all refrigerant dryers throughout the system. Contractor will install suction line dryers on both circuits.
4.10. Two weeks after installation, contractor will remove suction line dryers and replace all liquid line dryers.
4.11. Contractor will perform bleed down test utilizing vacuum pump for 24 hours on both circuits prior to connecting new chillers to existing refrigerant lines.
4.12. Furnish and install new insulation on existing and newly installed pipe, valves, and fittings.
4.13. Perform factory start up inspection on new chiller systems.
4.14. Set expansion valves for each circuit.
4.15. Log machine pressures, temperatures, flow, amperage and voltage.
4.16. Install proper LNC Network 8000 controls system. Coordinate with existing Controls Company (Schneider Electric) to ensure proper connection to building automation system.
4.17. Test and Balance system for optimal operation.
4.18. Provide 4 hours of owner operational training.
4.19. Coordinate inspections as required by the contracting officer’s representative (COR). The completion of a government inspection does not relieve the contractor of its responsibility to comply with required project documents, code, or the need to provide quality materials and workmanship.
4.19.1. Clean job site daily. Site shall be cleaned and restored to initial cleanliness prior to final acceptance.
4.19.2. Request a pre-final inspection from the government for the purpose of identifying and resolving common project deficiencies. Request a final acceptance inspection from the government for the purpose of identifying and resolving minor less-common deficiencies prior to project closeout.
4.20. The contractor shall immediately notify the COR upon discovery of any unforeseen site conditions or discrepancies between the government’s project documents and manufacturer’s guidance.
5. Delivery: The contractor shall perform the following:
5.1. Provide proof of insurance.
5.2. Provide bonding or alternative forms of bonding in accordance with FAR
28.102 (contracts exceeding $35,000).
5.3. Provide a progress schedule and bi-weekly progress reports on a government approved format after the issuance of an NTP for all projects exceeding ninety days, or otherwise indicated by the contracting officer.
5.4. Provide submittals in advance to the government prior to purchase. Government COR will review and approve all submittals prior to purchase.
5.5. Provide a release of claims after completion of project.
5.6. Provide a letter of guarantee after completion of project.
5.7. Minimum one (1) year on all workmanship and standard manufacturer’s warranty on products.
5.8. Provide 1 year construction installation warranty on entire project.
5.9. Provide 5 year warranty on all parts and equipment for project.
6. Government Furnished Property: The government shall furnish access to electrical power and water.
7. References:
7.1. UFC 3-410-01: Heating, Ventilating, and Air Conditioning Systems, 1/7/2013
7.2. UFC 3-410-02: Direct Digital Control for HVAC and Other Building Control Systems, 7/18/2018
7.3. ANG ETL 1-01-01, Air National Guard Design Policy, 1/1/2004
7.4. NFPA 11, 16
7.5. ASHRAE 90.1, AHRI Certified
7.6. UL Listed to US safety standard
8. Security: The government may prohibit installation access to anyone categorized as a security concern. These concerns may include, but are not limited to: record of criminal conduct (active arrest warrant), felony conviction, illegal drug involvement, personal conduct, registration on any sexual offender registry, record of convictions/charges stemming from disrespect for law, and non-us citizen without proper documentation. It is the contractor’s responsibility to contact the Government Point of Contact (POC) to determine eligibility and any associated cost with obtaining installation access.
9. Period of Performance:
9.1. Contractor shall coordinate material ordering and delivery schedule so that all demolition, repairs and construction are completed in ninety (90) calendar days after the issuance of a notice to proceed (NTP).
9.2. The normal business hours for the government are 6:30AM to 5:15PM, Tuesday through Friday with the exception of Holidays, unless arrangements have been made in advance.
10. All work will be performed at NAS JRB Fort Worth. Physical Address: Buildings 1670 and 1671.
11. Government Points of Contact:
11.1. Base Civil Engineer: Lieutenant Colonel Matthew Joseph, 136th Civil Engineer Squadron, Office: 817-852-3320, Email: matthew.joseph.5@us.af.mil
11.2. Contracting Officer’s Representative / Base Civil Engineer: Major Justin Schultz, 136th Civil Engineer Squadron, Office: 817-852-3327, Email:
justin.schultz.10@us.af.mil
11.3. Civil Engineer Operations Manager: TSgt Troy Sumner, 136 Civil Engineer Squadron, Office: 817-852-3336, Email: troy.sumner@us.af.mil
11.4. Civil Engineer Operations Manager: TSgt David Shamburger, 136 Civil Engineer Squadron, Office: 817-852-3334, Email: david.shamburger.2@us.af.mil
11.5. Contracting Officer: SMSgt Fletcher Weems, 136th Mission Support Contracting, Office: 817-852-3310, Email: fletcher.weems.2@us.af.mil
END OF SECTION