STATEMENT OF NEED
Commercial Wi-Fi 28 October 2022
1. PROJECT DESCRIPTION:
Provide commercial Wi-Fi to COANG facilities
2. OBJECTIVE:
The objective of this project is to provide Wi-Fi conforming to the specifications listed below to the buildings/rooms identified in the Statement of Need (SON). Multiple shops on Buckley SFB need fast, reliable Wi-Fi to be able to update devices not allowed on the NIPR Network. These devices need to be updated daily to comply with regulation.
3. GENERAL REQUIREMENTS:
Vendor shall provide commercial internet circuits to the following locations:
Building 701 – Two Wireless Access Points to cover entire second floor; minimum 1G download speed: 80 devices at once
Building 801 South, Room 233 – One Wireless Access Point, minimum 500mbps download speed: 20 devices at once
Building 911 Coverage for entire building, 3 common areas, 3 offices, 12 bedrooms; Minimum 500 mbps download speed: 25 devices at once
4. SCOPE:
Vendor is responsible to design/provide and install all equipment necessary to meet this SON. The Government will provide rack space in the main communication building and will route the circuits to each building listed above. The vendor will be responsible to distribute the internet service to the wireless access points.
5. SERVICE PERFORMANCE PERIOD.
The Period of Performance shall be One (1) Base Year (12 months) and four (4) Option Years (12 months each). The vendor is required to complete the installation and begin service within 30 days of contract award.
END OF STATEMENT OF NEED