Statement of Need - Wi-Fi.pdf

PDF 82 KB Posted

Attached to
140th Wing Commercial WiFi - Amendment 1
Solicitation number
W50S6V23Q0002
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF NEED

Commercial Wi-Fi 28 October 2022

1. PROJECT DESCRIPTION:

Provide commercial Wi-Fi to COANG facilities

2. OBJECTIVE:

The objective of this project is to provide Wi-Fi conforming to the specifications listed below to the buildings/rooms identified in the Statement of Need (SON). Multiple shops on Buckley SFB need fast, reliable Wi-Fi to be able to update devices not allowed on the NIPR Network. These devices need to be updated daily to comply with regulation.

3. GENERAL REQUIREMENTS:

Vendor shall provide commercial internet circuits to the following locations:

Building 701 – Two Wireless Access Points to cover entire second floor; minimum 1G download speed: 80 devices at once

Building 801 South, Room 233 – One Wireless Access Point, minimum 500mbps download speed: 20 devices at once

Building 911 Coverage for entire building, 3 common areas, 3 offices, 12 bedrooms; Minimum 500 mbps download speed: 25 devices at once

4. SCOPE:

Vendor is responsible to design/provide and install all equipment necessary to meet this SON. The Government will provide rack space in the main communication building and will route the circuits to each building listed above. The vendor will be responsible to distribute the internet service to the wireless access points.

5. SERVICE PERFORMANCE PERIOD.

The Period of Performance shall be One (1) Base Year (12 months) and four (4) Option Years (12 months each). The vendor is required to complete the installation and begin service within 30 days of contract award.

END OF STATEMENT OF NEED

File details come from the government source that posted it. Updated .