Specifications (16).pdf

PDF 6 MB Posted

Attached to
2026 Task Order Contract Multimodal Transportation System
Solicitation number
46-00020
Issued by
Bexar County, Texas

About this file

This is a specification document for the City of San Antonio's 2026-2027 Transportation Construction Contract Package 3, a task order contract designed to implement multimodal transportation system improvements across the city. The project is managed by the City Manager and Director of Transportation and encompasses non-site-specific construction activities including concrete curbs, sidewalks, driveways, retaining walls, curb ramps, asphalt replacement, tree removal and planting, sign relocation, pavement markings, and bicycle facility construction. The contract has a three-year term (1,095 calendar days) with projects issued as individual task orders that can range from $2,000 and above. Multiple project sites will be assigned throughout the city by the City Engineer or Project Manager, with contractors potentially managing multiple concurrent task orders. Project locations, plan details, and specific quantities will be incorporated via task orders over the contract life. The contractor must submit a detailed Quality Control Plan at least two weeks prior to the pre-construction meeting for each task order, and must provide project delivery and baseline schedules within 14 calendar days of the pre-construction meeting or risk suspension of future task orders and payment holds.

The contract establishes unit prices for various construction activities that remain valid throughout the contract duration, with payment contingent on satisfactory completion verified by City inspection. No direct payment is provided for mobilization, insurance, barricades, traffic handling, temporary erosion control, or excavation incidental to curb and sidewalk construction; these costs must be incorporated into other bid items. The contractor is responsible for producing and implementing traffic control layouts, which may be based on approved City and TxDOT standards or engineered plans developed by a licensed Texas professional engineer at the contractor's expense with no additional City cost. Additional traffic control measures may be required by the City at no additional expense to the contractor. Liquidated damages for construction delays are assessed on a per-site basis, and no additional compensation is provided for reduced working hours or night and weekend work. Final payment for each task order is released upon City approval of final completion, at which point all balances are considered paid in full.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF SAN ANTONIO

TRANSPORTATION AND CAPITAL IMPROVEMENTS

SPECIFICATIONS

FOR

2026 – 2027 Transportation Construction Contract Package 3

CITY MANAGER

ERIK WALSH

DIRECTOR OF TRANSPORTATION

CATHERINE HERNANDEZ

Prepared By:

Firm ID No. F-928

10101 REUNION PL, STE. 400

SAN ANTONIO, TEXAS 78216

JUNE 2026

6/17/2026

City of San Antonio Specification for Construction 2026 – 2027 Transportation Construction Contract Package 3

TABLE OF CONTENTS

SPECIFICATIONS: PAGE REFERENCE

Project Description PD-1 - PD-3

Governing Specifications, Special Specifications, Special Provisions, GSSP-1 – GSSP-6 And Supplemental Specifications

Special Provision to Item 101 – Preparing Right-of-Way 1 PAGE

Special Provision to Item 103 – Remove Concrete 1 PAGE

Special Provision to Item 205 – Hot Mix Asphaltic Concrete Pavement 1 PAGE

Special Provision to Item 209 – Concrete Pavement 1 PAGE

Special Provision to Item 500 – Concrete Curb, Gutter, and Concrete Curb 1 PAGE and Gutter

Special Provision to Item 502 – Concrete Sidewalks 3 PAGES

Special Provision to Item 504 – Concrete Medians and Islands 1 PAGE

Special Provision to Item 531 – Signs 3 PAGES

Special Provision to Item 533 – Cleaning and Removal of Pavement Markings 1 PAGE and Markers

Special Provision to Item 535 – Hot Applied Thermoplastic Pavement 1 PAGE Markings

Special Provision to Item 536 – Preformed Pavement Markings 1 PAGE

Special Provision to Item 556 – Cast in Place Detectable Warning Surface Tiles 1 PAGE

Special Provision to Item 804 – New Tree & Shrug Planting and Maintenance 1 PAGE

Supplemental Specification 1 – Railroad Insurance and Permit 1 PAGE

Supplemental Specification 2 – Railroad Flagger 1 PAGE

Supplemental Specification 3 – Sidewalk Drain Box 3 PAGES

Supplemental Specification 4 – Public Works Project Sign 1 PAGE

Supplemental Specification 5 – Police Officer 1 PAGE

Supplemental Specification 6 – Portable Changeable Message Sign 1 PAGE (Electronic Message Board)

Supplemental Specification 7 – Exploratory Excavation of Existing Utilities 2 PAGES

Supplemental Specification 8 – Woven or Nonwoven Geotextile 1 PAGE

Supplemental Specification 9 – Driver Feedback Speed Sign Assemblies 5 PAGES

Supplemental Specification 10 – Bike Lane Delineators 2 PAGES

Supplemental Specification 11 – Permanent Concrete Barrier – Bike Lane 1 PAGE

Public Works Project Sign Detail 1 PAGE

SAWS – DD-852-03 Manhole Ring Encasement Detail 2 PAGES

Concrete Bus Pad Detail 1 PAGE

Miscellaneous Construction Standards 2 PAGES

Concrete Bike Lane Barriers 1 PAGE

PD-1

Project Description Project Duration The start date of this task order construction contract shall be the date of issuance of the first task order. The contract shall be terminated one thousand and ninety-five (1095) calendar days from the start of the contract. The construction time (in calendar days) for each individual site will be negotiated between the City Engineer or Project Manager and the Contractor. The Contractor may also be limited to the amount of individual project sites open at any given time based on performance or available resources. Liquidated damages for construction time will be assessed on a per site basis should the Contractor fail to complete the construction in the specified calendar days as negotiated by the City Engineer or Project Manager. The Contractor shall refer to section 4.2.6 of the general conditions for claims for additional contract time due to inclement weather.

Project Scope Project construction may include but is not limited to: removal and replacement or installation of concrete curbs, sidewalks, driveways, concrete retaining walls-combination type, and curb ramps, minor asphalt replacement, topsoil, sodding, tree pruning, removal and/or replacement, sign relocation, pavement markings, bicycle facility construction or retrofit, construction activities within railroad right-of-way and any other items required due to the site conditions to accomplish the project scope.

This is a non-site specific contract, and task orders issued can be as small as $2,000.00.

Project locations and plan details will be incorporated into this contract by task order over the life of the contract. The quantities included in this contract are only to be used in the determination of the low qualified bidder. They are not to be used in determining the quantity of materials to be ordered for work under this contract. The contractor shall accept all task orders assigned, regardless of size.

Quantities included in this contract, as well as the entire bid amount are not guaranteed. Unit prices established shall remain valid throughout the duration of the contract.

Project Location The sites shall be assigned by the City Engineer or Project Manager and shall be located throughout the City. Each project site will be issued as a separate task order and quantities will be provided to the Contractor. Subsequent task orders will be issued for other work assignments that are to be accomplished during the life of this contract. The contractor should expect to enter more than one task order at one time.

It is anticipated that some project sites may require working time restrictions or night and weekend work. No additional compensation will be paid or given to the contractor for reduced working times or night and weekend work.

Important Notes

PD-2

Important Notes

· For each Task Order, a pre-construction meeting shall be held to kick off the construction phase. The Contractor shall provide a project delivery and baseline schedule within fourteen calendar days of pre-construction meeting. If a project delivery and baseline schedule is not provided by the Contractor within 14 calendar days of pre-construction meeting, the City reserves the right to not issue any future task orders and hold payment if necessary to the Contractor until a project delivery and baseline schedule has been received.

§ Change orders will not increase contract time duration unless authorized by the City Project Manager.

§ No direct payment shall be made for the following specification items. Contractor shall include cost of these items in various other bid items:

100.1 Mobilization

100.2A Insurance

530.1 Barricades, Signs, and Traffic Handling

540 Temporary Erosion, Sedimentation and Water Pollution Prevention and Control

Other Detour signage, flaggers, temporary traffic control devices, and all other traffic control measures or methods required to maintain vehicular, bicycle, and pedestrian traffic during construction

§ Excavation due to construction of curb, sidewalk, retaining walls, driveways, and parkway grading (edge of pavement/curb to property line) shall not be paid for directly but shall be included in various other bid items of which it forms a component part.

§ It is the Contractor’s responsibility to produce and implement the traffic control layout for each project location. The Contractor may utilize approved City and TxDOT traffic control standards as an approved traffic control plan, but first must receive approval from the City or their representatives on the proposed concept.

Should the Contractor choose to deviate from approved traffic control standards, he shall produce an engineered traffic control plan developed and signed by a professional engineer licensed to practice in the state of Texas. Payment for developing a signed and sealed traffic control plan shall be subsidiary to this contract and at no additional cost to the City. The City has the right to direct the Contractor to add additional traffic control measures should there be a concern of safety for the general public, at no additional expense to the City.

Quality Control Plan Contractor shall submit a detailed Quality Control Plan (QCP) in accordance with the requirements as set forth in these plans and specifications. The QCP shall be submitted

PD-3

to City a minimum of two (2) weeks prior to the pre-construction meeting. The City will review the QCP, provide comments, and ultimately approve the final QCP prior to Contractor beginning construction operations. The Contractor QCP must be approved by the City prior to the pre-construction meeting, or for task order contracts prior to issuance of the first task order. The QCP will become a component of the contract and the Contractor will be required to adhere to it. Obtain approval for changes to the QCP made during the project.

The City may suspend operations if the Contractor fails to comply with the QCP. Failure to adhere to the approved QCP may result in delayed processing or rejection of payment requests.

Final Payment and Task Order Closeout When all work on an issued Task Order is complete in full, and the Contractor has received from the City both a Notice of Substantial Completion and Final Completion of Work, Contractor shall submit the final payment request and notate that the applicable payment request is Final. The Task Order will then be closed out by City and Contractor.

Upon completion of payment request cycle and receipt of final payment by Contractor, Contractor agrees that all balances associated with Task Order have been paid in full.

Final payment by the City shall constitute Final Completion of Work.

All City of San Antonio Specifications & Construction Detail sheets are available on the City’s Website at:

https://www.sanantonio.gov/PublicWorks/Current-Vendor-Resources/Standard- Specifications-and-Details

All Construction and Material Specifications for SAWS bid items are available at:

https://apps.saws.org/business_center/specs/constspecs/ https://apps.saws.org/business_center/specs/matspecs/

All Standards and Specifications for CPS bid items are available at:

https://secure.cpsenergy.com/CorporateApps/StandardsAndSpecs.jsp

The Specific Contract Documents for this project are available on the City’s Website at:

https://www.sa.gov/Directory/Departments/Finance/About/Divisions/Procurement/Biddin g-Contracting/Opportunities Click on the following link “2026 – 2027 Transportation Construction Contract Package 3”

GSSP - 1

CITY OF SAN ANTONIO, TEXAS

GOVERNING SPECIFICATIONS, SPECIAL SPECIFICATIONS, SPECIAL

PROVISIONS, AND SUPPLEMENTAL SPECIFICATIONS

FOR

2026 – 2027 Transportation Construction Contract

All Standard Specifications and Special Specifications applicable to this project are identified as follows:

CITY OF SAN ANTONIO STANDARD SPECIFICATIONS FOR CONSTRUCTION

JUNE, 2008 AND SPECIAL PROVISIONS DATED MAY 2009, FEBRUARY 2010,

JUNE 2010 and NOVEMBER 2013

ITEM DESCRIPTION

101 - PREPARING RIGHT-OF-WAY

103 - REMOVE CONCRETE

104 - STREET EXCAVATION

105 - CHANNEL EXCAVATION

107 - EMBANKMENT

108 - LIME TREATED SUBGRADE

109 - CEMENT TREATED SUBGRADE

200 - FLEXIBLE BASE

202 - PRIME COAT

203 - TACK COAT

204 - SURFACE TREATMENTS

205 - HOT MIX ASPHALTIC CONCRETE PAVEMENT

208 - SALVAGING, HAULING AND STOCKPILING RECLAIMABLE

ASPHALTIC PAVEMENT

209 - CONCRETE PAVEMENT

GSSP - 2

237 - POTHOLE REPAIR

500 - CONCRETE CURB, GUTTER, AND CONCRETE CURB AND GUTTER

502 - CONCRETE SIDEWALKS

503 - ASPHALTIC CONCRETE, PORTLAND CEMENT CONCRETE, AND

GRAVEL DRIVEWAYS

504 - CONCRETE MEDIANS AND ISLANDS

505 - CONCRETE RIPRAP

506 - CONCRETE RETAINING WALLS – COMBINATION TYPE

507 - CHAIN LINK WIRE FENCE

512 - ADJUSTING EXISTING MANHOLES AND VALVE BOXES

513 - REMOVING AND RELOCATING MAILBOXES

515 - TOPSOIL

516 - SODDING

520 - HYDROMULCHING

531 - SIGNS

533 - CLEANING AND REMOVAL OF PAVEMENT MARKINGS AND

MARKERS

535 - HOT APPLIED THERMOPLASTIC PAVEMENT MARKINGS

536 - PREFORMED PAVEMENT MARKINGS

537 - RAISED PAVEMENT MARKERS

556 - CAST IN PLACE DETECTABLE WARNING SURFACE TILES

801 - TREE AND LANDSCAPE PROTECTION

804 - NEW TREE & SHRUB PLANTING AND MAINTENANCE

GSSP - 3

TEXAS DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS FOR

CONSTRUCTION – SEPTEMBER 1, 2024

ITEM DESCRIPTION

192 - LANDSCAPE PLANTING

194 - ROADSIDE AMENITY

250 - GEOGRID BASE REINFORCEMENT

432 - RIPRAP

450 - RAILING

459 - GABIONS AND GABION MATTRESSES

465 - JUNCTION BOXES, MANHOLES, AND INLETS

514 - PERMANENT CONCRETE TRAFFIC BARRIER

528 - LANDSCAPE PAVERS

533 - MILLED RUMBLE STRIPS

540 - METAL BEAM GUARD FENCE

545 - CRASH CUSHIOIN ATTENUATORS

556 - PIPE UNDERDRAINS

658 - DELINEATOR AND OBJECT MARKER ASSEMBLIES

662 - WORK ZONE PAVEMENT MARKINGS

690 - MAINTENANCE OF TRAFFIC SIGNALS AND ILLUMINATION

1005 - LOOSE AGGREGATE FOR GROUNDCOVER

1006 - LANDSCAPE SOIL AMENDMENT

5005 - BOLLARDS

GSSP - 4

CITY OF SAN ANTONIO

SPECIAL PROVISIONS FOR CONSTRUCTION

ITEM DESCRIPTION

101 - PREPARING RIGHT-OF-WAY

103 - REMOVE CONCRETE

205 - HOT MIX ASPHALTIC CONCRETE PAVEMENT

209 - CONCRETE PAVEMENT

500 - CONCRETE CURB, GUTTER, AND CONCRETE CURB AND GUTTER

502 - CONCRETE SIDEWALKS

504 - CONCRETE MEDIANS AND ISLANDS

531 - SIGNS

533 - CLEANING AND REMOVAL OF PAVEMENT MARKINGS AND

MARKERS

535 - HOT APPLIED THERMOPLASTIC PAVEMENT MARKINGS

536 - PREFORMED PAVEMENT MARKINGS

556 - CAST IN PLACE DETECTABLE WARNING SURFACE TILES

804 - NEW TREE & SHRUB PLANTING AND MAINTENANCE

SUPPLEMENTAL SPECIFICATIONS FOR CONSTRUCTION

SUP 01 - RAILROAD INSURANCE AND PERMIT

SUP 02 - RAILROAD FLAGGER

SUP 03 - SIDEWALK DRAIN BOX

SUP 04 - PUBLIC WORKS DEPARTMENT PROJECT SIGN

SUP 05 - POLICE OFFICER

GSSP - 5

SUP 06 - PORTABLE DYNAMIC SIGN (INSTALLATION, PROGRAMMING,

REMOVAL)

SUP 07 - EXPLORATORY EXCAVATION OF EXISTING UTILITIES

SUP 08 - WOVEN GEOTEXTILE

SUP 09 - DRIVER FEEDBACK SPEED SIGN ASSEMBLY

SUP 10 - BIKE LANE DELINEATORS

SUP 11 - PERMANENT CONCRETE BARRIER – BIKE LANE

DETAILS FOR CONSTRUCTION

PUBLIC WORKS PROJECT SIGN DETAIL

CONCRETE BUS STOP PAD

MISCELLANEOUS CONSTRUCTION STANDARDS I & II

CONCRETE BIKE LANE BARRIERS

SPECIAL PROVISION

Item 101 Preparing Right-of-Way

Delete:

Section 101.5 Measurement in its entirety Section 101.6 Payment in its entirety

Add:

101.5 Measurement:

“Preparing right-of-Way” for new construction and retrofit type construction shall be limited to removal of trees and other vertical type plant species. Miscellaneous vertical type plant species shall be considered trees within this specification and applicable bid items. Measurement of removal shall be based upon the number of satisfactorily removed trees and upon diameter of removed trees. Tree diameter to be determined from onsite topographic survey or tree specific survey. If no such surveys are conducted contractor shall measure, photographically record, and submit summary of trees designated for removal to the City of San Antonio Project Manager and the Engineer.

101.6 Payment:

The accepted quantities shall be paid at the contract unit price for the tree diameter applicable in the bid list which shall be full compensation for furnishing of all materials, labor, tools, equipment and supplies to conduct satisfactory removal of trees as shown on the plans or as approved by the City of San Antonio Project Manager and the Engineer. Additional trees removed, not approved by City of San Antonio Project Manager and the Engineer, shall be replaced with approved tree species, approval required from City of San Antonio Project Manager and the Engineer, so that the sum of the diameters of new trees installed is equal to or greater than the diameters of unapproved trees removed, at contractor’s expense.

101.7 Bid Item:

101.2 – Tree Removal (8”-16” Diameter) – per each (EA)

101.3 – Tree Removal (17”-24” Diameter) – per each (EA)

101.4 – Tree Removal (25” – 36” Diameter) – per each (EA)

SPECIAL PROVISION

Item 103 Remove Concrete

Delete:

Section 103.5 Measurement, Section D Section 103.6 Payment in its entirety Section 103.7 Bid Item 103.4

Add:

103.5 Measurement, Section D:

Miscellaneous Concrete and Small Structures. Miscellaneous Concrete and Small Structures will be measured by the cubic foot in its original position regardless of the thickness of the concrete, reinforcing steel encountered, height of structure or depth of foundation, if applicable.

103.6 Payment:

This item will be paid for at the contract unit price bid for “Remove Concrete Curb”, “Remove Concrete Traffic Barrier”, “Remove Concrete Sidewalks and Driveways,” or “Remove Miscellaneous Concrete and Small Structures” which price shall be full compensation for all work herein specified, including the furnishing of all materials, equipment, tools, labor, and incidentals necessary to complete the work.

103.7 Bid Item:

103.5 – Remove Miscellaneous Concrete and Small Structures – per cubic foot (CF)

SPECIAL PROVISION

Item 205 Hot Mix Asphaltic Concrete Pavement

Add:

205.2 Materials, After Section B:

B1. Reclaimed Asphalt Shingles (RAS). RAS is defined as processed asphalt shingle material from manufacturing of asphalt roofing shingles or from re-roofing residential structures. Post-manufactured RAS is processed manufacturer’s shingle scrap by-product. Post-consumer RAS is processed shingle scrap removed from residential structures. Comply with all regulatory requirements stipulated for RAS by the TCEQ. RAS shall not be used within asphaltic surface or wearing courses.

SPECIAL PROVISION

Item 209 Concrete Pavement

Add:

209.5 Measurement, Section C:

Reinforced Concrete Bus Pad. Concrete pavement will be measured by the square yard of surface area in place. The surface area includes concrete toe-in, in cases where existing or proposed roadway surface is HMAC. Monolithic concrete curbing is to be installed adjacent to concrete bus pads and is to be considered subsidiary to the unit price bid for “Reinforced Concrete Bus Pad”, thus area measurements are to extend to the back of curb.

209.6 Payment, Section D:

Reinforced Concrete Bus Pad. Work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the adjusted unit price bid for “Reinforced Concrete Bus Pad” of the type and depth specified on plans and as adjusted in accordance with Section 209.6.B, “Deficient Thickness Adjustment” and 209.4.M, “Ride Quality”.

209.7 Bid Item:

209.2 – Reinforced Concrete Bus Pad – per square yard (SY)

209.3 – HES Concrete Pavement (13”) With Integral Color – per square yard (SY)

209.4 – HES Concrete Pavement (6”-13” Var. Thickness, 9.5” Average) – per square yard (SY)

SPECIAL PROVISION

Item 500 Concrete Curb, Gutter, and Concrete Curb and Gutter

Delete:

Section 500.6 Payment in its entirety

Add:

500.5 Measurement, Section B

Sawtooth Curb. Accepted work for the item “Concrete Sawtooth Curb” shall be measured by the linear foot of constructed curbing, to include lowered areas of curbing.

500.6 Payment:

The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid for “Concrete Curb”, “Concrete Curb (Mono)”, “Concrete Gutter”, “Concrete Curb and Gutter”, “Concrete Mountable Curb”, “Concrete Sawtooth Curb”, or “Concrete Full Depth Header Curb” of the type specified.

This price is full compensation for surface preparation of base, equipment, labor, materials, tools, and incidentals. Topsoil to be paid under Item 515, “Topsoil.”

500.7 Bid Item:

500.5 – Concrete Mountable Curb – per linear foot (LF)

500.6 – Concrete Sawtooth Curb – per linear foot (LF)

500.7 – Concrete Full Depth Deep Header Curb – per linear foot (LF)

SPECIAL PROVISION

Item 502 Concrete Sidewalks

Delete:

Section 502.4 Construction, Section D, Paragraph 1 Section 502.4 Construction, Section F, Paragraph 1 Section 502.4 Construction, Section G in its entirety Section 502.5 Measurement in its entirety Section 502.6 Payment in its entirety

Add:

502.4 Construction, Section D, Paragraph 1

A cushion, 4 inch minimum thickness, or crusher screenings, gravel, crushed rock or flexible base material shall be spread, wetted thoroughly, tamped and leveled. The cushion shall be moist at the time the concrete is placed. Where the subgrade is rock or gravel, 70% of which is rock, the 4 inch cushion need not be used. The Engineer will determine if the subgrade meets the above requirement.

502.4 Construction, Section E, After Last Paragraph

6” X 6” W/D 2.9 X W/D 2.9 welded wire flat sheets (Item 303) will NOT be allowed to be used as reinforcement for sidewalks. Contractor shall use No. 3 bars (minimum) @ 18 inches O.C. each way or 6” X 6” W/D 5 X W/D 5 welded wire flat sheets (Item 303) centered in slab as reinforcement for sidewalks.

All curb ramps, as noted in Section 502.4G below, shall be constructed at commercial grade, with No. 4 bars (minimum) at 12 inches O.C. each way centered in slab, at 6 inches thick. Sub-base placement identified in Section 502.4.D of this provision applies to curb ramps. Wire mesh of any size will NOT be allowed for Curb Ramps.

502.4 Construction, Section F, Paragraph 1

Unless otherwise specified on the plans or as agreed to by the Engineer, tooled joints with rounded edges will be placed at intervals equal to the sidewalk width and will be opened with one-half inch (1/2”) radius by one and one-half inch (1 ½”) depth and closed by one-half inch (1/2”) radius by one inch (1”) depth.

502.5 Measurement

A. Concrete Sidewalk. Sidewalks shall be measured by the square yard of plan surface area at the depth specified by plan, regardless of installation method.

B. Concrete Curb Ramp. Curb ramps shall be measured by the number of satisfactorily constructed unit curb ramp. A unit curb ramp shall consist of the curb ramp, landing, adjacent flares or siding curb, and detectable warning surface as shown in the plans.

C. VIA Shelter Pad. Concrete pad for VIA shelter structure shall be measured by the number of satisfactorily constructed concrete pads. A unit shelter pad shall include the concrete pad and any required mounting hardware that shall be cast into the concrete.

D. VIA Bench Pad. Concrete pad for VIA benches shall be measured by the number of satisfactorily constructed concrete pads. A unit bench pad shall include the concrete pad and any mounting hardware that shall be cast into the concrete.

502.6 Payment:

A. Concrete Sidewalk. The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid per square yard for “Concrete Sidewalks – 4” Thickness” or “Concrete Sidewalks – 6” Thickness”.

B. Concrete Curb Ramp. The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid per each satisfactorily installed curb ramp for items 502.03 through 502.12 “Concrete Curb Ramp (TXDOT Type XX Curb Ramp)”.

C. VIA Shelter Pad. The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid per each for “VIA Shelter Pad”.

D. VIA Bench Pad. The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid per each for “VIA Bench Pad”.

E. The unit price of items included within Specification 502 is full compensation for surface preparation of base; materials; drilling and doweling into existing concrete curb, sidewalk, and pavement; repair of adjacent street or pavement structure damaged by these operations; and equipment, labor, materials, tools, and incidentals.

F. Sidewalks that cross and connect to concrete driveways will be measured and paid for in accordance with Item 503, “Asphaltic Concrete, Portland Cement Concrete, and Gravel Driveways”.

502.7 Bid Item:

502.03 – Concrete Sidewalk (4” Thickness) – per square yard (SY)

502.04 – Concrete Sidewalk (6” Thickness) – per square yard (SY)

502.05 – Concrete Curb Ramp (TXDOT Type 1 Curb Ramp) – per each (EA)

502.06 – Concrete Curb Ramp (TXDOT Type 2 Curb Ramp) – per each (EA)

502.07 – Concrete Curb Ramp (TXDOT Type 3 Curb Ramp) – per each (EA)

502.08 – Concrete Curb Ramp (TXDOT Type 5 Curb Ramp) – per each (EA)

502.09 – Concrete Curb Ramp (TXDOT Type 7 Curb Ramp) – per each (EA)

502.10 – Concrete Curb Ramp (TXDOT Type 10 Curb Ramp) – per each (EA)

502.11 – Concrete Curb Ramp (TXDOT Type 20 Curb Ramp) – per each (EA)

502.12 – Concrete Curb Ramp (TXDOT Type 21 Curb Ramp) – per each (EA)

502.13 – Concrete Curb Ramp (TXDOT Type 22 Curb Ramp) – per each (EA)

502.14 – VIA Shelter Pad – per each (EA)

502.15 – VIA Bench Pad – per each (EA)

SPECIAL PROVISION

Item 504 Concrete Medians and Islands

Delete:

Section 504.5 Measurement in its entirety Section 504.6 Payment in its entirety

Add:

504.2 Materials

E. Adhesive Grout and Concrete Paint. Provide coatings in accordance with TXDOT’s DMS 8110, “Coatings for Concrete”. Match color of coating with Aerospace Material Specification – Standard 595A color 23655, yellow, unless otherwise shown on the plans.

504.4 Construction

B. Monolithic Concrete Median Nose. Monolithic concrete median nose shall be formed and reinforced in accordance with Item 504 “Concrete Medians and Islands” or as directed by plan. As directed by plan apply concrete paint, color yellow, to surface and curb of median nose area using method specified in Item 311 “Concrete Surface Finish”.

504.5 Measurement

A. Concrete Median. Concrete medians shall be measured by the square yard to the face of the curb.

B. Concrete Directional Island. Concrete directional islands shall be measured by the square yard to the face of curb.

C. Monolithic Concrete Median Nose. Monolithic concrete median nose shall be measured by the number of satisfactorily installed monolithic concrete median noses. A unit monolithic concrete median nose shall be considered to be inclusive of the curbing, concrete median, and painting of the median nose.

D. Median Paint – Yellow. Median paint shall be measured by the linear foot, at face of curb, of satisfactorily painted curb.

504.6 Payment:

A. The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid for “Concrete Median”, “Concrete Directional Island”, “Monolithic Concrete Median Nose”, or “Median Paint – Yellow”.

This price is full compensation for preparing foundation surfaces; furnishing and operating equipment; curbs and gutters used as part of the concrete median or directional island; concrete finishings and painting; and labor, materials, tools, and incidentals.

504.7 Bid Item:

504.3 – Monolithic Concrete Median Nose – per each (EA)

504.4 – Median Paint – Yellow – per linear foot (LF)

SPECIAL PROVISION

Item 531 Signs

Delete:

Section 531.5 Measurement in its entirety Section 531.6 Payment in its entirety

Add:

531.4 Construction

Section C, Subsection b. Signpost and Foundation Removal.

1. Sign located within grass areas. Where designated by plan Contractor is to remove both signpost and foundation in its entirety. Unless requested by City of San Antonio Project Manager signpost and foundation are to become property of Contractor and are to be disposed of by the Contractor in accordance with federal, state, and local regulations.

Removed signposts shall not be reinstalled for new signage unless approved by City of San Antonio Project Manager. Contractor to backfill hole from removed foundation with embankment in accordance with Item 107 “Embankment”, backfill shall be densified to match surrounding conditions. Apply seed, according to TXDOT Item 164 “Seeding for Erosion Control” or install sod, in accordance with CoSA Item 516 “Sodding” over embankment area.

a. If sign is located within landscaped or similar areas Contractor shall replace surface with material to match surrounding area, as approved by City of San Antonio Project Manager.

2. Sign located within sidewalk, median or other concreted areas. Where designated by plan Contractor is to cut sign post flush with surface of surrounding concrete. Contractor shall cut signpost in such a manner that any protrusion does not exceed ¼” in height and shall remove any sharp edges left behind by cutting or grinding methods. Unless requested by City of San Antonio Project Manager signpost and foundation are to become property of Contractor and are to be disposed of by the Contractor in accordance with federal, state, and local regulations. Removed signposts shall not be reinstalled for new signage unless approved by City of San Antonio Project Manager.

3. For sign locations outside of listed Contractor shall notify City of San Antonio Project Manager and Engineer prior to commencing removal of signposts and foundations in question.

Section D, Relocation of existing signs

1. Existing sign panels. Where designated by plan Contractor shall unbolt and remove all existing sign panels from existing signpost and retain sign panels for reuse on new signpost at the new location as designated by plan. Sign panels to be reused shall be inspected by City of San Antonio Inspector prior to reinstallation. Any sign panels deemed unfit for reuse shall be returned to the Traffic Operations Section and replacement sign panels shall be furnished by Contractor.

2. Existing signpost. Existing signposts designated by plan for relocation shall be removed in accordance with Specification 531, 531.4 Construction, Section C, Subsection b.

3. Install new signpost and relocated sign panel(s) per plan and in accordance with Specification 531.

531.5 Measurement

A. Install Ground Mount Sign. Measurement shall be based upon the number of satisfactorily installed signs by specified size. A unit install ground mounted sign shall be considered to be inclusive of furnishing applicable sign panel, by plan; signpost; and foundation.

B. Install Sign Panel. Measurement shall be based upon the number of satisfactorily installed sign panels on existing signposts, by specified size. A unit sign panel shall be considered to be inclusive of furnishing applicable sign panel, by plan.

C. Remove Sign and Post. Measurement shall be based upon the number of satisfactorily removed signs, posts, and foundations. A unit removed sign and post shall be considered to be inclusive of removing sign panel; removing signpost; cutting signpost; removing foundation;

backfill; seeding, sodding, or other materials required to match surrounding conditions; delivery of removed materials to City of San Antonio, as required; and disposal of removed materials.

D. Remove Sign Panel. Measurement shall be based upon the number of satisfactorily removed sign panels, regardless of size.

E. Relocate Existing Sign. Measurement shall be based upon the number of satisfactorily relocated signs. A unit relocated sign shall be considered to be inclusive of removing sign panels;

removing signpost; removing foundation; backfill; seeding, sodding, or other materials required to match surrounding condition; and furnishing of signpost and foundation.

531.6 Payment:

A. Install Ground Mount Sign. The accepted quantity shall be paid at the contract unit price for each satisfactorily installed ground mounted at the specified size, which shall be full compensation for furnishing of all materials, labor, tools, equipment, supplies, and incidentals.

B. Install Sign Panel. The accepted quantity shall be paid at the contract unit price for each satisfactorily install sign panel, at the specified size, which shall be full compensation for furnishing of all materials, labor, tools, equipment, supplies, and incidentals.

C. Remove Sign and Post. The accepted quantity shall be paid at the contract unit price for each satisfactorily removed sign and post, which shall be full compensation for furnishing of all materials, labor, tools, equipment, supplies, and incidentals.

D. Remove Sign Panel. The accepted quantity shall be paid at the contract unit price for each satisfactory removed sign panel, regardless of size, which shall be full compensation for furnishing of all materials, labor, tools, equipment, supplies, and incidentals.

E. Relocate Existing Sign. The accepted quantity shall be paid at the contract unit price for each satisfactorily relocated sign and post, which shall be full compensation for furnishing of all materials, labor, tools, equipment, supplies, and incidentals.

531.7 Bid Item:

531.86 – Install Ground Mount Sign up to 36”X36” – per each (EA)

531.87 – Install Ground Mount Sign greater than 36”x36” – per each (EA)

531.88 – Install Sign Panel up to 36”X36” – per each (EA)

531.89 – Install Sign Panel greater than 36”X36” – per each (EA)

531.90 – Remove Sign and Post – per each (EA)

531.91 – Remove Sign Panel – per each (EA)

531.92 – Relocate Existing Sign – per each (EA)

531.93 – Install Temporary “Business is Open” sign

SPECIAL PROVISION

Item 533 Cleaning and Removal of Pavement Markings and Markers

Delete:

Section 533.5 Measurement and Payment in its entirety Section 533.6 Bid Item in its entirety

Add:

533.5 Measurement

A. This Item shall be measured by each word, symbol, or shape eliminated; by the foot of marking eliminated; or by any other unit shown on the plans and shall be paid at the contract unit price.

B. Eliminate Existing Railroad Crossing Symbol. Removal of existing railroad crossing symbol shall be paid at the contract unit price. A unit removed railroad crossing symbol shall be considered to be inclusive of three (3) lane width 24” white bars, one (1) 16” white crossing, two

(2) white “R” markings, and any pertinent raised pavement markings. In the event multiple travel lanes are present each lane shall require a separate measurement unit. This Item shall also include railroad markings found within bike lanes or other bike facilities and shall be measured by the same manner.

533.6 Payment:

A. The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid Item 533. This price is full compensation for the elimination method used and materials, equipment, tools, labor, and incidentals. Removal of raised pavement markers shall not be paid for directly but will be subsidiary to the pertinent bid items.

533.7 Bid Item:

533.1 – Eliminate Existing Pavement Markings and Raised Markers (4”) – per linear foot (LF)

533.2 – Eliminate Existing Pavement Markings and Raised Markers (8”) – per linear foot (LF)

533.3 – Eliminate Existing Pavement Markings and Raised Markers (12”) – per linear foot (LF)

533.4 – Eliminate Existing Pavement Markings and Raised Markers (24”) – per linear foot (LF)

533.5 – Eliminate Existing Pavement Markings and Raised Markers (Arrow) – per each (EA)

433.6 – Eliminate Existing Pavement Markings and Raised Markers (DBL Arrow) – per each (EA)

533.7 – Eliminate Existing Pavement Markings and Raised Markers (Word) – per each (EA)

533.8 – Eliminate Existing Pavement Markings and Raised Markers (RR-Xing) – per each (EA)

533.9 – Eliminate Existing Pavement Markings and Raised Markers (Raised Marker) – per each (EA)

533.10 – Eliminate Existing Pavement Markings and Raised Markers (Med Nose) – per each (EA)

533.11 – Eliminate Existing Pavement Markings and Raised Markers (Bike Symbol) – per each (EA)

SPECIAL PROVISION

Item 535 Hot Applied Thermoplastic Pavement Markings

Add:

535.7 Bid Item:

535.22 – 4 Inch Wide Yellow Line (Skip) – per linear foot (LF)

535.23 – 4 Inch Wide White Line (Skip) – per linear foot (LF)

535.24 – 4 Inch Wide Black Line (Contrast) – per linear foot (LF)

535.25 – 6 Inch Wide Yellow Line (Solid) – per linear foot (LF)

535.26 – 6 Inch Wide Yellow Line (Skip) – per linear foot (LF)

535.27 – 6 Inch Wide White Line (Solid) – per linear foot (LF)

535.28 – 6 Inch Wide White Line (Skip) – per linear foot (LF)

535.29 – 6 Inch Wide Black Line (Contrast) – per linear foot (LF)

535.30 – 8 Inch Wide White Line (Broken) – per linear foot (LF)

535.31 – 8 Inch Wide White Line (Dot) – per linear foot (LF)

535.32 – Bus Lane Striping (Red) – per square foot (SF)

535.33 – Median Nose Yellow – per each (EA)

535.34 – Bike Green Paint – per square foot (SF)

SPECIAL PROVISION

Item 536 Preformed Pavement Markings

Add:

536.7 Bid Item:

536.21 – 12 Inch Wide Black Line (High Contrast) – per linear foot (LF)

536.22 – 18 Inch Wide Yellow Line – per linear foot (LF)

536.23 – 24 Inch Wide Yellow Line – per linear foot (LF)

536.24 – Bike Box and Colored Lanes (Green) – per square foot (SF)

536.25 – Bike Sharrow Marking – per each (EA)

536.26 – Merge White Arrow – per each (EA)

536.27 – 16”X24” Preformed White Triangle with 2” Black Contrast – per each (EA)

536.28 – Left Turn White Arrow Bicycle Facility – per each (EA)

536.29 – Right Turn white Arrow Bicycle Facility – per each (EA)

536.30 – Bicycle Rider Symbol – per each (EA)

SPECIAL PROVISION

Item 556 Cast in Place Detectable Warning Surface Tiles

Delete:

Section 556.5 Measurement in its entirety Section 556.6 Payment in its entirety Section 556.7 Bid Item

Add:

556.5 Measurement

A. Cast in Place Detectable Warning Surfaces. Cast in Place Detectable Warning Surfaces shall be measured by the square foot of satisfactorily installed warning surfaces and paid at the contract unit price.

B. Detectable Warning Surfaces for Curb Ramps. Cast in Place Detectable Warning Surfaces utilized in curb ramp construction shall not be measured for payment and shall be considered subsidiary to the applicable curb ramp bid item.

556.6 Payment:

A. The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid for “Cast in Place Detectable Warning Surface”. This price is full compensation for preparing foundation surfaces, furnishing and operating equipment, labor, materials, tools, and incidentals.

556.7 Bid Item:

556.1 – Cast in Place Detectable Warning Surface – per square foot (SF)

SPECIAL PROVISION

Item 804 New Tree & Shrub Planting and Maintenance

Add:

804.13 Bid Item:

804.2 – New Tree & Shrub Planting and Maintenance – Ornamental (0”-2” DIA) – per each (EA)

804.3 – New Tree & Shrub Planting and Maintenance – Ornamental (2”-6” DIA) – per each (EA)

804.4 – New Tree & Shrub Planting and Maintenance – Large Canopy (0”-2” DIA) – per each (EA)

804.5 – New Tree & Shrub Planting and Maintenance – Large Canopy (2”-6” DIA) – per each (EA)

2026 – 2027 Transportation Task Order Contract Package 3

SUPPLEMENTAL SPECIFICATION 1

Railroad Insurance and Permit

SUP 1.1 DESCRIPTION: Contractor to secure all required railroad insurance and permits per each project task order. All fees associated with such permits shall be included in this item.

SUP 1.2 MATERIALS: N/A.

SUP 1.3 CONSTRUCTION: N/A.

SUP 1.4 MEASUREMENT: Railroad Insurance and Permit to be measured per each project;

necessary per each task order assignment.

SUP 1.5 PAYMENT: Railroad Insurance and Permit shall be paid at the contract unit price per each task order project.

BID ITEM:

SUP 1 – Railroad Insurance and Permit – per each (EA)

SUPPLEMENTAL SPECIFICATION 2

Railroad Flagger

SUP 2.1 DESCRIPTION: Coordination of Railroad Flagger is required for all activities that encroach onto Railroad Property. Flaggers must be qualified to perform duties and follow procedure within railroad right of way. Specifically, where workers or equipment have potential to foul tracks, 25 feet but could be a greater distance; or as established by governing entities and railroad owners or owners. This also applies to the area above Railroad tracks such as on roadway overpass grade separations or overhead utility work.

SUP 2.2 MATERIALS: N/A.

SUP 2.3 CONSTRUCTION: N/A.

SUP 2.4 MEASUREMENT: Measurement for this Item will be per flagger per hour. Contactor must submit invoices to City for verification of working hours that each flagger was present on site.

SUP 2.5 PAYMENT: The work performed and materials furnished with this item and measured as provided under “Measurement”, will be paid for by submitted invoice. This price is full compensation for furnishing all labor, materials, supplies, equipment, fees, and incidentals necessary to complete the work as directed.

SUP 2 – Railroad Flagmen – per hour (HR)

SUPPLEMENTAL SPECIFICATION 3

Sidewalk Drain Box (1/2 inch thick)

SUP 3.1 DESCRIPTION: Construct sidewalk drain box in accordance with the design plans.

SUP 3.2 MATERIALS: Furnish materials conforming to the following:

A. Hydraulic Cement Concrete: Item 300, “Concrete.” Use Class “A” concrete or other concrete as specified. Use Grade 8 course aggregate for extruded Class A concrete. Use other grades if approved by the Engineer.

B. Reinforcing Steel: Item 301, “Reinforcing Steel.”

C. Membrane Curing Compound: Item 305, “Membrane Curing.”

D. Concrete Structures: Item 307, “Concrete Structures.”

E. ½” Thick Galvanized Steel Checkered Plate

SUP 3.3 EQUIPMENT: Furnish equipment as required and/or in accordance with the pertinent Items.

SUP 3.4 CONSTRUCTION: Location of sidewalk drain box shall be indicated by plans or as directed by the Engineer.

A. Removal of Existing Sidewalk. If an existing sidewalk is present at the location of the proposed sidewalk drain box, remove existing sidewalk to the depths and limits shown on the plans or identified by the Engineer. All concrete sidewalks to be repaired shall be cut with a concrete saw or other equipment approved by the Engineer from existing sidewalks, driveways, or other concrete structures. If necessary, remove adjacent soil and vegetation to prevent contamination of the sidewalk area, and place it in a windrow or stockpile. Do not damage adjacent sidewalk or other structures during removal and reconstruction operations. Remove and dispose of existing concrete and other materials from the work area.

B. Subgrade Preparation. Shape and compact subgrade to the line, grade, and cross-section shown on the plans. Mechanically tamp and sprinkle foundation when placement is directly on subgrade.

C. Sub-base Placement. A cushion, 2 inch minimum thickness, of crusher screenings, gravel, crushed rock or flexible base material shall be spread, wetted thoroughly, tamped and leveled. The cushion shall be moist at the time the concrete is placed.

Where the subgrade is rock or gravel, 70% of which is rock, the 4 inch cushion need not be used. The Engineer will determine if the subgrade meets the above requirements.

The foundation shall be level and uniformly compacted to prevent future settlement.

D. Reinforcement. Concrete sidewalks shall be reinforced as shown in the plans. Concrete reinforcement for the concrete foundation of the sidewalk drain box can be found on the detail sheet titled, “Miscellaneous Construction Standards 1.”

E. Joints. Unless otherwise specified on plans or as agreed to by Engineer, tooled joints with rounded edges will be placed every six feet (6’) and will be opened with one-half inch (½”) radius by one and one-half inch (1 ½”) depth and closed by one-half inch (½”) radius by one-inch (1”) depth.

1. Expansion Joints. Provide sidewalk sections separated by pre-molded or board joint

½ inch thick or as shown on the plans, on each side of the sidewalk drain unless otherwise directed. The expansion joint material shall be placed vertically and shall extend the full depth and width of the concrete.

F. Concrete Placement. Forms shall be of metal or wood and shall extend for the full depth of the concrete. All forms shall be free from warp and of sufficient strength to resist the pressure of the concrete without displacement. Bracing and staking of forms shall be such that the forms remain in both horizontal and vertical alignment until their removal. All forms shall be cleaned and coated with an approved form release agent or form oil before concrete is placed. Divider plates shall be of metal. Forms shall conform to the specified radius when placed on curves.

G. Finish and Curing. Provide finished work with a well-compacted mass, a surface free from voids and honeycomb, and the required true-to-line shape and grade. After finishing each portion of the sidewalk, the surface shall be textured with heavy broom finish. Within twenty minutes of broom finish, a curing compound shall be used to protect the sidewalk. The curing compound shall be of a high solid content, greater than thirty percent (+30%) and clear in nature. Colored curing compounds will not be allowed. All edges shall be tooled to have slight radius. Surface water retention is not acceptable. Concrete must be cured and protected from freezing temperatures for at least three (3) days.

H. Backfilling. Once concrete has cured, sidewalk will need to be backfilled to a height determined by the Engineer with material approved by the Engineer. The top 4 inches of fill shall be tamped and sloped using clean topsoil. Heavy equipment must remain off sidewalk drain box and surrounding sidewalk at all times.

All necessary excavation for the sidewalk drain box will be considered incidental work pertaining to this item, and will not be paid for directly. The adjacent excavation and grading of the slopes shall be done in a manner acceptable to the Engineer.

SUP 3.5 MEASUREMENT: Sidewalk Drain Box will be measured by linear foot at the width specified on the plans or by the Engineer. The concrete structure that serves as the foundation for the sidewalk drain box shall not be measured for payment but shall be included in the cost of Sidewalk Drain Box.

SUP 3.6 PAYMENT: The work performed and materials furnished with this item and detail and measured as provided under “Measurement” will be paid for at the contract unit price bid per each for “Sidewalk Drain Box” which price shall be full compensation for surface preparation of base; materials; reinforcement; excavation, hauling and disposal of excavated material; steel plate; drilling and doweling into existing concrete curb, sidewalk and pavement; repair of adjacent street or pavement structure damaged by these operations; and equipment, labor, materials, tools and incidentals necessary to complete the work.

BID ITEM:

SUP 06 – Sidewalk Drain Box (12” Wide) – per linear foot (LF) SUP 07 – Sidewalk Drain Box (18” Wide) – per linear foot (LF) SUP 08 – Sidewalk Drain Box (24” Wide) – per linear foot (LF)

SUPPLEMENTAL SPECIFICATION 4

Public Works Project Sign

SUP 4.1 DESCRIPTION: Purchase project sign for the Public Works Department (PWD) for length of construction of individual project.

SUP 4.2 MATERIALS: Contractor to furnish materials necessary to display the project sign.

SUP 4.3 EQUIPMENT: Provide equipment necessary to conduct the work specified herein or as directed by the Engineer.

SUP 4.4 CONSTRUCTION: Contractor to furnish sufficient signs for the duration of this contract in accordance with this supplemental specification and the detail included within these contract documents. At a minimum, Contractor shall furnish two (2) signs per street, to be placed at each end of the project. The City or their representative holds the authority to require Contractor to install additional Public Works project signs at no additional costs. Contractor shall install signs a minimum of 72 hours in advance of mobilizing construction crews.

SUP 4.5 MEASUREMENT: PWD Project Sign, as prescribed above, will be measured by the unit of each project sign. The storage and transfer of sign from project to project, as well as the equipment & material required to mount the sign, will not be measured for payment.

SUP 4.6 PAYMENT: The work performed as prescribed by this item will be paid for at the contract unit price bid per Each for PWD Project Sign which price shall be full compensation for sign purchase, equipment & materials required to mount each sign, storage and transfer of each sign from project to project; for furnishing and placing all materials and for all labor, tools, equipment and incidentals necessary to complete the work.

SUP 09 – Public Works Department Project Sign – per Each (EA).

SUPPLEMENTAL SPECIFICATION 5

Police Officer

SUP 5.1 DESCRIPTION: Provide uniformed off-duty police officer(s) as directed by the City of San Antonio Project Manager and Traffic Engineer where two-way traffic is to be maintained at major intersections.

SUP 5.2 MATERIALS: N/A

SUP 5.3 CONSTRUCTION: Coordinate with City of San Antonio Construction Inspector to determine the duration and locations where off-duty police officers will be deployed. At project sites that require police officers, contractor will not be allowed to start any form of work until police officer is on-site and directing traffic.

SUP 5.4 MEASUREMENT: Police Officer services will be measured by the hour per officer.

Contractor must provide official time statements showing documentation of hours worked per officer.

SUP 5.5 PAYMENT: The accepted quantity of man-hours shall be paid at the contract unit price for each hour. Contractor will not receive payment for the police officer hours until official time statements have been provided to and approved by the City.

SUP 5.6 BID ITEM:

SUP 10 – Police Officer – per Hour (HR)

SUPPLEMENTAL SPECIFICATION 6

Portable Changeable Message Sign (PCMS)

(Electronic Message Board)

SUP 6.1 DESCRIPTION: Provide portable changeable message signs to notify the general public of construction activities for upcoming and ongoing projects.

SUP 6.2 MATERIALS: N/A.

SUP 6.3 EQUIPMENT: Provide equipment necessary to conduct the work specified herein or as directed by the Engineer.

SUP 6.4 CONSTRUCTION: Perform all work in conformance with this section unless otherwise shown on the plans. Provide portable changeable message signs as directed by Project Manager or Engineer. Text for message boards will be provided by Project Manager or Engineer. Project locations will be determined by the Engineer or Project Manager. Contractor must be able to provide portable changeable message signs for the duration of specified projects throughout the duration of the contract. Contractor must also have one (1) portable changeable message sign on standby in the event one of the message boards in use breaks down.

SUP 6.5 MEASUREMENT: Portable Changeable Message Signs, as prescribed above, will be measured per each on a daily basis. The equipment required to store, relocate and transport the message boards will not be measured for payment. Adjusting messages will also not be measured for payment. The standby portable changeable message sign will not be measured for payment.

SUP 6.6 PAYMENT: The work performed as prescribed by this item will be paid for at the contract unit price bid per each per day for “Portable Changeable Message Signs” which price shall be full compensation for all storage, transportation, set up and maintenance; for furnishing and placing all materials and for all labor, tools, equipment, and incidentals necessary to complete the work.

SUP 6.7 BID ITEM:

SUP 11 – Portable…

This is the start of the file's text. The full file is on GovTribe.