SP470216R00060002.pdf PDF
WSHP_15_Technical_Data_Sheet.pdf PDF
HZ2A_N_0411.pdf PDF
HZ2A_N_0301.pdf PDF
HZ2A_N_0302.pdf PDF
HZ2M_N_0301.pdf PDF
HZ2A_N_0104.pdf PDF
SP470216R00060001.pdf PDF
Atch___2_Scope_of_Work.pdf PDF
Atch___1_16R0006_SECTION_L_ _M.pdf PDF
Atch___4_DOL_Wage_Rate_Determination.pdf PDF
SP470216R0006.pdf PDF
Atch___3_CSC-15750_FINAL_DRAWING_SET_revised.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

CONSTRUCTION COST ESTIMATE

PROJECT NO. CSC-15750 DRAWING NO. 7-713 DATE:

PROJECT TITLE: UPS ADDITIONS TO BLDG 58

ARCHITECT/ENGINEER: ESTIMATOR:

PRELIMINARY DESIGN FINAL DESIGN X OTHER

ITEMQUANTITYMATERIALLABOREQUIP COSTTOTAL COST
NO. OF UNITSUNIT OF MEASUREPER UNITTOTALUNIT MANHOURTOTAL MANHOURSRATE PER HOURTOTALUNIT RATETOTAL
ELECTRICAL COST
120/208V, 3P, 4W, 150A MCB, 42 CKT PANELBOARDEA
30A, 2P CIRCUIT BREAKEREA
30A, 1P CIRCUIT BREAKEREA
20A, 1P CIRCUIT BREAKEREA
40kW STANDBY UPS SYSTEMEA
UPS SYSTEM ADDITIONAL 1YR WARRANTYEA
SIEMENS 175A CIRCUIT BREAKEREA
#2/0 THHN WIRECLF
#1/0 THHN WIRECLF
#10 THHN WIRECLF
#12 THHN WIRECLF
#6 GROUND WIRECLF
#12 MC CABLECLF
2" EMT CONDUIT (INCLUDES ALL BENDS, COUPLINGS, TERMINATIONS, ETC…)LF
1" EMT CONDUIT (INCLUDES ALL BENDS, COUPLINGS, TERMINATIONS, ETC…)LF
3/4" EMT CONDUIT (INCLUDES ALL BENDS, COUPLINGS, TERMINATIONS, ETC…)LF
20A DUPLEX OUTLET (INCLUDES BOX & COVER PLATE)EA
20A QUADRAPLEX OUTLET (INCLUDES BOX & COVER PLATE)EA
4" SQUARE JUNCTION BOXEA
ADDITIONAL GENERAL ELECTRICIAL LABOR
MECHANICAL COST
RE-INSTALLATION OF SUSPENDED CEILINGSF
RE-INSTALLATION OF CEILING TILESSF
WATER SOURCE HEAT PUMP DEMOLITIONEA
DUCTWORK DEMOLITIONLBS
DIFFUSER/GRILL DEMOLITIONEA
PIPE DEMOLITIONLF
WATER SOURCE HEAT PUMP BALANCINGEA
DIFFUSER/GRILL BALANCINGEA
WATER SOURCE HEAT PUMPEA
10" DIA. DUCTLF
12" DIA. DUCTLF
14" DIA. DUCTLF
RECTANGULAR DUCTLBS
10" FLEX DUCTLF
12" FLEX DUCTLF
DUCT INSULATIONSF
DUCT LINERSF
DIFFUSERSEA
RETURN GRILLEA
VOLUME DAMPEREA
SMOKE DAMPEREA
1" PIPE, SCH 40LF
PIPE INSULATIONLF
CONTROL VALVEEA
BALL VALVEEA
CONTROL WORKLS
THERMOMETERSEA
SUBTOTAL
OH
PROFIT
BOND
TOTAL
Attachment # 5Source Selection Infromation See FAR 2.101 and 3.104