RFP SP470214R0004 ATTACHMENT 3 Cost Estimate Bid Form
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P0003AT1.docx | DOCX document | |
| P0003.pdf | ||
| P0003AT2.pdf | ||
| P0002AT1.pdf | ||
| SF_30.pdf | ||
| P0001AT2.pdf | ||
| P0001AT1.pdf | ||
| P0001.pdf | ||
| 14R0004.pdf | ||
| Attach_2-drawings_bldg_20_repair.pdf | ||
| Attach_4-AS_form_3000.pdf | ||
| Attach_1-OH140002_2_14_14_WD.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY13-FCIE-Means
| BID SHEET | |||||
| PROJECT NO. CSC-14711 | DRAWING NO. 3-1591 | SHEET | 1 | OF | 1 |
PROJECT TITLE: Repair Drainage East Side Building 20
| ARCHITECT/ENGINEER: Barbour | |||||||||
| ITEM DESCRIPTION | QUANTITY | MATERIAL | LABOR | EQUIPMENT | TOTAL COST | ||||
| NO. OF UNITS | UNIT OF MEASURE | COST PER UNIT | TOTAL | RATE PER Unit | TOTAL | RATE PER Unit | TOTAL |
| demo | remove railings to be reused | Ea. |
| demo | remove granite to be reused | Ea. |
| demo | demo sidewalk/floor slab 6"wwf+200%sm./cngstd | SF |
| demo | remove metal decking (may require torching) | SF |
| torch cutting 1"th.plate | LF | |
| demo | rmv beams,struct.mbrs,rmv whl/cut to500lbs | Ea. |
| demo | remove stairs | SF |
| demo | rmv.soil undr.strs/ramp cmmn earth,hydr.bckh.1/2bkt | BCY |
| demo | remove staircase walls 10"+20%heavy reinf. | SF |
| demo | staircase/ramp footings 1.5'Tx3'W+20% heavy reinf. | LF |
| demo | demo overlook wall 8"+20%heavy reinf. | SF |
| demo | remove ramp wall 8"+20%heavy reinf. | SF |
| demo | demo exterior stucco 1"thick over mesh | SF |
| load/haul 12 CY truck | ||
| demo related | support WT sections/sprinkler system | LS |
| scaffolding | CSF | |
| micropile | micropile equipment mobilization | LS |
| micropile | CIP,thin wall shell pipe,not incl.reinf.8"dia.16ga. | VLF |
| mircropile | for reinf.steel add | LB. |
| staircase | cmpct top 6"rllr.cmpct.opr.wlkng | ECY |
| staircase | staircase foundation mat under 10CY (3ksi) | CY |
| staircase | staircase wall(3ksi)10"thick8'tall | CY |
| staircase | cmpct bkfl.6"rllr.cmpct.opr.wlkng | ECY |
| staircase | stairs(3.5ksi)not incl.sfty treads,cast on ground | SF |
| staircase | re-install stair railing | |
| forms elevated slabs plywood job built | SF | |
| footing plywood forms | SF | |
| wall plywood forms | SF | |
| stair forms | SF | |
| slab on grade forms | LF | |
| ramp | cmpct top 6"rllr.cmpct.opr.wlkng | ECY |
| ramp | ramp footers 24"x12"reinforced (3ksi) | CY |
| ramp | ramp wall(3ksi)8"th.various heights | CY |
| ramp | cmpct bkfl.6"rllr.cmpct.opr.wlkng | ECY |
| welded wire fabric | 6x6 W2.1xW2.1 (8x8) 30 lb. per C.S.F. | C.S.F. |
| ramp | slab on grade(3ksi)incl.finish,not incl.frms/reinf. | SF |
| elevated slab | elev. Slab (4000 psi), not incl. forms/reinf. 4" th. | S.F. |
| ramp | steel decking 3"deep 20ga. | SF |
| beams | W12x16 < 2tons add 100% | LF |
| overlook | cmpct top 6"rllr.cmpct.opr.wlkng | ECY |
| overlook | overlook wall footer 18"x12"reinforced (3ksi) | CY |
| overlook | overlook wall(3ksi)8"thick 3'high | CY |
| reinstall granite | LS | |
| overlook | overlook joint sealant | CLF |
| overlook | overlook railing | LS |
| overlook | overlook curbing w/granite | LS |
| PVC,ribbed,3/8"thick,6"wide | LF | |
| overhang | overhang curb | LF |
| overhang | overhang railing | LS |
| overhang | ext.stucco ceilings | SY |
| fireproofing | fireproof spryd cmnt.fltd dck per1"thick | SF |
| landscaping | hydroseeding w/wood&fiber mulch added | SY |
| sidewalk | CIP concrete sidewalk, 5"thick,4"gravel base,4'wide | LF |
TOTAL $0.00
| OH | $0.00 |
| Profit | $0.00 |
| Bond | $0.00 |
| new TOTAL | $0.00 |