SOW - Replace Bldg 65 Air Compressors.pdf
PDF 155 KB Posted
- Solicitation number
- Not on record
- Issued by
-
Department of Defense
About this file
This is a Statement of Work (SOW) for the Air Force Research Laboratory (AFRL/RAVZ) to replace the aging air compressor system in Building 65, dated 20 May 2026.
The contractor must provide a complete turnkey replacement of the air compressor system, including removal and disposal of two existing Ingersoll Rand Nirvanna compressors (Model IRN100H-CC), one Ingersoll Rand dryer (Model TS11A), one Zeks dryer (Model 800HSFA400), one coalescing filter, existing prefilters, and an Ingersoll Rand mist eliminator. The new system shall consist of two oil-free, air-cooled rotary screw compressors with a minimum capacity of 400 CFM at 125 psig each, and two air-cooled dryers sized for minimum 490 CFM capacity each. The contractor must install all associated piping, valves, electrical connections, and control systems to integrate the new equipment with the existing plant air distribution system. The piping configuration must allow independent isolation of each compressor and dryer for maintenance while maintaining operational redundancy, with capability for either or both trains to operate simultaneously. All electrical work must comply with the National Electrical Code (NEC) and local standards. A master control system with automated lead/lag functionality and Modbus protocol communication capability is required, with manufacturer-built-in controls acceptable if available.
Installation must follow a phased approach to maintain continuous facility operations without exceeding four-hour system shutdowns, requiring approval from the Government project manager. The contractor shall perform manufacturer-recommended startup and commissioning procedures and provide comprehensive training to up to three Government employees for up to four hours on operation and routine maintenance. All deliverables include the fully operational system, Operations and Maintenance manuals for all equipment, and completion of the training session, with training costs included in the total project price.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Replace Building 65 Air Compressors
20 May 2026
1.0 Background
The Air Force Research Laboratory (AFRL/RAVZ) has identified a critical need to replace the existing air compressor system located in Building 65. The current system, consisting of two
Ingersoll Rand Nirvanna air compressors and associated dryers, is approaching its end of service life. The equipment has experienced multiple failures, leading to costly repairs and significant disruptions to facility operations. Furthermore, with only one currently operational dryer, the system lacks full redundancy. This compressed air system is essential, serving critical operational and research-specific equipment within the facility. This project will mitigate operational risks by replacing the aging equipment with a new, fully redundant, and reliable system.
2.0 Scope of Work
The contractor shall provide all necessary labor, materials, tools, and equipment to complete the turnkey replacement of the Building 65 air compressor system. The scope of this project includes the disconnection, removal, and disposal of two existing air compressors and two dryers; the provision and installation of two new oil-free rotary screw air compressors and two new air dryers; and the installation of all associated piping, electrical connections, and control systems required for full operational capability. The contractor shall ensure that at least one compressor remains operational throughout the project execution, minimizing downtime as specified herein.
3.0 Requirements
The contractor shall perform the following tasks:
3.1 Equipment Removal and Disposal
The contractor shall:
• Carefully disconnect all electrical, piping, and ancillary connections from the existing equipment to facilitate removal.
• Remove and dispose of the following government-owned equipment in accordance with all applicable federal, state, and local regulations:
o Two (2) Ingersoll Rand Nirvana air compressors (Model: IRN100H-CC).
o One (1) Ingersoll Rand air dryer (Model: TS11A).
o One (1) Zeks air dryer (Model: 800HSFA400).
o One (1) associated coalescing filter and existing prefilters.
• Remove and dispose of the existing Ingersoll Rand mist eliminator located downstream of the dryers. This unit shall not be replaced.
3.2 Equipment Specifications
The contractor shall furnish and install new equipment meeting the following minimum specifications:
• Air Compressors:
o Quantity: Two (2) o Type: Oil-free, rotary screw o Cooling: Air-cooled o Capacity: Each unit shall provide a minimum of 400 CFM at 125 psig.
• Air Dryers:
o Quantity: Two (2) o Type: Air-cooled o Capacity: Each unit shall be sized for the new compressors with a minimum capacity of 490 CFM.
• Ancillary Components:
o Furnish and install a new prefilter system compatible with the new compressors.
3.3 Installation
The contractor shall:
• Modify existing concrete equipment pads as necessary to accommodate the footprint of the new equipment.
• Install the new compressors in the same location as the removed units. The new dryers shall be installed in the location of the removed Ingersoll Rand dryer.
• Install all new piping, valves, and supports required to connect the new compressors and dryers to the existing plant air distribution system.
o The piping and valve configuration shall allow for the independent isolation of each compressor and dryer for maintenance purposes while the other unit remains in service.
o The system shall be configurable to allow either or both compressor/dryer trains to be operational simultaneously.
• Modify and extend existing electrical services as required to safely and effectively power the new equipment. All electrical work shall comply with the National Electrical Code
(NEC) and local standards.
• Perform manufacturer-recommended startup, testing, and commissioning procedures for all new equipment.
3.4 Control System
The contractor shall:
• Provide and install a master control system capable of managing both compressors and dryers. If the compressor and/or dryers have this capability built in, that shall be a sufficient solution for control.
• The control system must support automated lead/lag functionality and have the capability to alternate the lead unit based on accumulated run hours to ensure even wear.
• The compressors shall be equipped with external communication outputs that can be monitored via the Modbus protocol.
3.5 Phased Installation and Operational Continuity
To ensure continuous facility operations, the contractor shall adhere to the following phased installation sequence:
1. One existing Ingersoll Rand compressor and the Zeks dryer shall remain operational.
2. The contractor shall remove the second Ingersoll Rand compressor and the Ingersoll
Rand dryer.
3. The contractor shall then install the two new dryers and one new compressor. This new train shall be commissioned and brought online.
4. Once the new train is fully operational, the second existing compressor and dryer shall be decommissioned, removed, and disposed of.
5. The contractor shall then install the second new compressor.
• Continuous plant air must be maintained at all times. Any required shutdowns of the air system must be scheduled and approved by the Government project manager in advance and shall not exceed four (4) hours in duration.
3.6 Training
The contractor shall provide a comprehensive training session on the operation and routine maintenance of the new compressor system.
• Duration: Up to four (4) hours.
• Audience: Up to three (3) designated Government employees.
• The cost of this training shall be included in the total project price.
4.0 Deliverables
• Fully installed, commissioned, and operational air compressor system meeting all requirements specified herein.
• Operations and Maintenance (O&M) manuals for all new equipment.
• Completion of the training session as specified in Section 3.6.