SOW.ElectronicsComponents Rev 1.pdf

PDF 218 KB Posted

Attached to
Twinax Cables for Data Transmission in Cryogenic Temperatures of DUNE
Solicitation number
SS_455376
Issued by

About this file

This document is a Statement of Work (SOW) for the procurement of twinax cables for data transmission in cryogenic temperatures associated with the Deep Underground Neutrino Experiment (DUNE) project. Brookhaven National Labs (BNL) requires the purchase and delivery of 1,750 pieces of 22 meter cables and 2,200 pieces of 27 meter cables. The cables must use THV (Tetrafluoroethylene, Hexafluoropropylene, Vinylidene Flouride) material for cable extrusion due to the cryogenic temperature requirements of 77K. The delivery schedule calls for the 27 meter cables to be delivered in 4 batches by February 28, 2026, and the 22 meter cables to be delivered in 5 batches by April 30, 2027. This SOW is related to a pre-solicitation for the Twinax Cables for Data Transmission in Cryogenic Temperatures of DUNE, issued by the Department of Energy Office of Science, which is currently only requesting information from interested vendors on their capabilities to meet the SOW requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P.O. Box 5000 Upton, NY 11973-5000 managed by Brookhaven Science Associates for the U.S. Department of Energy

Subject: Statement of Work for Twinax Cables for Data Transmission in Cryogenic Temperatures of DUNE

Background:

Brookhaven National Labs (BNL) requires the purchase and delivery of twinax cables for data transmission in cryogenic temperatures associated with the DUNE (Deep Underground Neutrino Experiment) project. These cables are required to utilize THV (Tetrafluoroethylene, Hexafluoropropylene, Vinylidene Flouride) material for cable extrusion in the construction of these cables. Extensive tests carried out by BNL have shown that only this type of material is acceptable given the cryogenic temperature utilized (77K).

Schedule:

Two types of cables will be procured in this order:

1) 1,750 pieces of 22 m cables with part number of HDR-223199-02-ECDP

a) Delivery of the first batch on or before April 30, 2026

b) Delivery of full order on or before April 30, 2027, in 5 batches

2) 2,200 pieces of 27 m cables with part number of HDR-227794-03-ECDP.

a) Delivery of the first batch on or before June 30, 2025

b) Delivery of full order on or before February 28, 2026, in 4 batches.

The delivery of cables will start with 27 m cables first, followed by 22 m cables.

Signature: ___ ___Hucheng Chen___________ Of Requestor

File details come from the government source that posted it. Updated .