SOW BVGM252001.pdf

PDF 236 KB Posted

Attached to
Building 1 HVAC Repair Federal contract opportunity
Solicitation number
W50S8Q-25-Q-A003
Issued by
Department of the Army National Guard

About this file

This document is a Statement of Work (SOW) for a Building 1 HVAC Repair project at the Blue Ash Air National Guard Station in Ohio. The project scope involves removing and replacing the existing 30-ton Roof Top Unit (RTU), installing new HVAC controls and components, replacing the Direct Digital Controls (DDC) controller and headend computer, and configuring new DDC software. The contractor will also replace the existing roof access ladder and hatch handrail to meet OSHA standards.

The project has a maximum duration of 90 calendar days from the Notice to Proceed, with work limited to 7:00 am - 4:30 pm Monday through Friday. The contractor is responsible for obtaining all necessary permits, following environmental and safety regulations, and providing a one-year warranty on all materials and labor. The project requires adherence to various federal, state, and local building codes, including OSHA standards, National Electrical Code, and specific Air Force facility criteria. The estimated project value is not explicitly stated, but the solicitation indicates it falls between $100,000 and $250,000 and is set aside for small businesses.

View the file

Other files for this federal contract opportunity

Other files attached to Building 1 HVAC Repair, newest first.
File Type Posted
RFI Answers_BLDG1 HVAC.pdf PDF
Binder_Controller Photos.pdf PDF
SiteVisit Sign in Sheet_BLDG 1 HVAC_7-24-25.pdf PDF
RFI Answers_BLDG1 HVAC.pdf PDF
Solicitation - W50S8Q25QA003.pdf PDF
Springfield Base Facility Standards - FINAL - March 2025 Signed.pdf PDF
Binder_BLDG 1 HVAC Drawings.pdf PDF
RFI Template.docx DOCX document
Material Submittals BVGM252001.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

DEPARTMENT OF THE AIR FORCE

178th WING

CIVIL ENGINEER SQUADRON

STATEMENT OF WORK

Bldg 1 Repair HVAC (Blue Ash Air National Guard Station)

PROJECT NO.

BVGM252001

DEPARTMENT OF THE AIR FORCE

178th CIVIL ENGINEER SQUADRON

REV: 10 June 2025

Page | 2

1. GENERAL INFORMATION

1.1. DEFINITION OF TERMS

1.1.1. GOVERNMENT refers to the United States GOVERNMENT and the United States Air Force as represented by the United States CONTRACTING OFFICER or their designated representative, the CONTRACTING OFFICER’s REPRESENTATIVE (COR) from the 178th Civil Engineer Squadron.

1.1.2. CONTRACTOR refers to the CONTRACTOR, the SUBCONTRACTOR for the CONTRACTOR, any and all CONTRACTOR and SUBCONTRACTOR employees or personnel, the CONTRACTOR’s tools, and the CONTRACTOR’s vehicles and equipment.

1.1.3. NOTICE TO PROCEED (NTP) provides written notification that the CONTRACTOR has provided adequate design submittals and approved by the CONTRACTING OFFICER. This shall allow the CONTRACTOR to begin ordering construction materials.

1.1.4. PERIOD OF PERFORMANCE (PoP) begins with the NOTICE TO

PROCEED and ends after the final acceptance of the construction.

1.2. ABBREVIATIONS / ACRONYMS

KO: CONTRACTING OFFICER

COR: CONTRACTING OFFICER’s REPRESENTATIVE PoP: Period of Performance OTHERS: Workmen under the employ of Other CONTRACTORS or the

GOVERNMENT.

GFE: GOVERNMENT Furnished Equipment NTP: Notice To Proceed provided by the CONTRACTING OFFICER SOW: Statement of Work ECPs Entry Control Points OSHA: Occupational Safety and Health Administration ASTM: American Society for Testing and Materials UFC: Unified Facilities Criteria (Design Manual) UFGS: Unified Facilities Guide Specifications QA/QC: Quality Assurance / Quality Control EM: Environmental Manager MSDS: Material Safety Data Sheet VECP: Value Engineering Contract Proposal DDC: Direct Digital Controls HHW: Heating Hot Water

Page | 3

1.3. INSTALLATION STANDARDS

1.3.1. The job site location for this project is at Building 1 on Blue Ash Air National Guard Station, 10649 McKinley Rd, Blue Ash, OH 45242.

1.3.2. CONTACTOR shall provide all labor, material, tools, equipment, supervision, and all items to complete the work in accordance with all portions of the SOW and Drawings, unless otherwise noted under the Government Furnished Equipment/Property section (Para. 2.2).

1.3.3. Repairs, replacements, new installations and re-installations shall conform to the current version of all applicable Federal, State, and Local building codes, laws, and regulations for building constructions, renovations, and maintenance activities as specified by the installation standards referenced below. The workmanship shall meet the requirements of these standards.

The CONTRACTING OFFICER or COR must approve the workmanship upon completion and prior to closeout of the contract.

1.3.4. Adhere to all Unified Facilities Criteria (UFC) and Unified Facilities Guide Specifications (UFGS). The US National Electric Code (NEC), Plumbing Codes, International Building Code (IBC), and the Ohio Building Code (OBC) shall be the minimum construction standard allowed, however the UFC shall take precedence should conflict arise.

1.3.5. Follow standards for worker safety found in Occupational Safety and Health Administration (OSHA) requirements, EM385-1-1, National Electric Safety Code, and other similar Standards.

1.3.6. For any electrical work, provide a licensed electrician knowledgeable of and conforming to the requirements of the National Electrical Code (NEC).

The licensed electrician must hold and be able to provide a current and valid certification prior to the start of any electrical work. Follow all standards for electrical installations pertaining to fire protection and personnel safety found in the most current US National Electric Code

(NEC).

1.3.6 Any work completed to add new, repair or modify existing fire alarm and detection systems must be installed in accordance with current NFPA requirements. The components or system installed shall operate with existing building components and be compatible with existing fire alarm panel, able to communicate with headend units at the primary and alternate BDOC locations. The Springfield Ohio Air National Guard Base Fire Department requires a Monaco Fire Alarm panel system.

1.3.7 Exterior walls, interior bearing walls (and/or columns) and roof assembly shall meet minimum blast and ballistic mitigation criteria as set forth by

UFC 4-020-02FA.

Page | 4

1.3.8 All concrete design shall be in accordance with ACI 318 Code

Requirements for Structural Concrete.

1.3.9 Dispose of all solid waste to include non-hazardous and hazardous waste in compliance with all Federal, State, and Local environmental laws and regulations in coordination with the Base Environmental Management Office (EMO). Track and report the volume of solid waste (Construction & Demolition) disposal and recycling costs incurred, or funds received, disposal sites, and weight tickets to the COR using Post-Project Waste Diversion Report (attached) within 30 days from project completion using the submittal process.

1.3.10 Perform site preparation in accordance with drawings and specifications included within or attached to this Statement of Work (SOW). Questions pertaining to the depth and extent of the site preparation shall be directed to the COR. Alteration of existing surfaces or facilities, not identified by the GOVERNMENT, shall not occur. CONTRACTOR shall be responsible for any damage to any surfaces, structures, facilities, and equipment not identified by the GOVERNMENT for alteration and shall be repaired to the COR’s approval at the CONTRACTOR’s expense.

1.3.11 Field-verify all conditions and measurements provided in this statement of work. The CONTRACTOR assumes full monetary responsibility for any and all additional work, materials, or equipment required to complete the project that was not included in the statement of work that a reasonable site inspection would have revealed. The CONTRACTOR shall not be responsible for conditions that a reasonable site inspection would not have revealed (unforeseen site conditions).

1.3.12 It is highly encouraged to develop, prepare, and submit Value Engineering Change Proposals (VECP’s) voluntarily. The CONTRACTOR shall share in any net acquisition savings realized from accepted VECPs, in accordance with the incentive sharing rates in paragraph (f) of 52.248-1 in the FAR. If a VECP is accepted, the CONTRACTOR shall share in net acquisition savings of between 50 - 75 percent or as negotiated by KO and as described in the FAR.

1.3.13 Complete a DD1354 break-out form for the work performed on project within 30 days of project completion using the submittal process. The form must be completed satisfactorily and in a timely manner before the final invoice is processed for payment. Any questions regarding completion of the form should be referred to the Real Property Manager for assistance.

Real Property Manager: Mr. Jordan Deady Email:

jordan.deady.2@us.af.mil phone: (937) 525-2586.

Page | 5

1.4. STANDARD PRODUCTS

1.4.1 Materials such as sealants, adhesives, waterproofing, or fireproofing must comply with standards set forth by UL, ASTM, and IEC and listed for the specific use intended.

1.4.2 In the event of conflict among the Specifications, Drawings, and/or Technical Instructions, the CONTRACTOR shall bring such conflict to the attention of the CONTRACTING OFFICER or COR for resolution before proceeding with the work involved. Submit through the RFI process for documentation of conflict and agreed upon resolution utilizing the provided RFI Template.

1.5. SUBMITTALS

1.5.1. The CONTRACTING OFFICER or COR must approve all material submittals prior to procurement. Materials substitution after submittal approvals shall not be allowed without approval by KO.

1.5.2. Provide documentation for each submittal in accordance with Material Submittal list. Include a catalog sheet of the specific product containing the product technical information, data, or specifications. Highlight selected options if technical information contains more than one option. When requested by COR, a sample of the product/equipment or material must accompany the submission (typically for approval of finish color, if not already specified in the attached Base Facility Standards).

1.5.3. Material submittals are required unless approval from the COR or CONTRACTING OFFICER has been granted otherwise. All Material Submittals, Design Drawings, and Specifications are to be submitted to the COR and CONTRACTING OFFICER with a fillable/signable PDF version of the Air Force Form 3000 (attached) for approval prior to installation of the material submitted. Submittals, Drawings, and Specifications shall be reviewed by the KO and approved prior to installing the approved material.

Copy the following individuals on all submittals:

Technical Inspector: Mr. Nick Owens – nicholas.owens.2@us.af.mil Technical Inspector: Mr. Shane Ober – shane.ober.1@us.af.mil Technical Inspector: Mr. Mike Howard – michael.howard.53@us.af.mil COR: Mr. Blake Melling – blake.melling.1@us.af.mil Contract Specialist: TSgt Seth Taylor – seth.taylor.8@us.af.mil KO: MSgt Samantha McKinney - Samantha.mckinney.1@us.af.mil mailto:michael.howard.53@us.af.mil

Page | 6

1.5.4. Provide a detailed Project Schedule identifying milestone dates to COR prior to issuance of NTP. A detailed Design and Construction Schedule in a CPM – Gantt style format shall be submitted for approval using Air Force Form 3064 (attached) using the submittal process. If a change in the schedule is required, resubmit the Progress Schedule for approval in electronic format to the COR within 7 days. AF Form 3064 will be used to evaluate project completion, ensure updates are submitted.

1.5.5. Provide Progress Reports weekly to the COR and KO using Air Force Form 3065 (attached). Progress Reports shall track the CONTRACTOR’s progress in relation to the approved Progress Schedule as well as assist in computing partial payments.

1.5.6. Provide a list of names of all contracted personnel performing work on base to the COR using the Base Pass Information Required for Contractors template (attached) at least 72 hours prior to base access requirement. Coordinate with Contracting or Base Engineering Personnel for required documentation. Be prepared to submit copies of Driver’s License for all personnel requiring access in addition to DBIDS requests.

1.5.7. Submit SDS (Safety Data Sheet) for all chemical materials to be used for this SOW, to be included with the AF 3000 form for material submittals.

Upon approval from the COR, store materials in accordance with Occupational Safety and Health Administration (OSHA) requirements.

Provide the Organization Hazardous Material Identification (attached) within 10 days of issuance of the Notice to Proceed (NTP) and updated prior to any new materials being brought onto the installation. At the completion of the project, all unused hazardous materials must be removed from the installation by the CONTRACTOR. Submit the total amount of materials used for the project to the COR using the Transient Organization Hazardous Material Inventory Form.

1.5.8. Abide by the Federal acquisition program for Green Procurement as outlined in USEPA Comprehensive Procurement Guideline website.

Provide a list of all recovered materials to the COR using Recovered Materials Determination Form & Recovered Materials Procurement Determination (attached) with the material submittals as outlined in 1.4.1 within 30 days of project completion.

1.6. PERMITS / CERTIFICATION

1.6.1. CONTRACTOR is responsible for obtaining all required base passes, dig permits, utility locates, and all other permits required to complete the work described in this SOW.

Page | 7

1.6.2. CONTRACTOR must submit and obtain an approved dig permit from Ohio Utilities Protection Service (OUPS) prior to start of any site work.

Permit requests must be made 48 hours in advance by calling OUPS office at 1-800-362-2764. CONTRACTOR may request utility drawings from Base Engineering and Base Communications through the COR, to assist CONTRACTOR in locating underground utilities. COR must approve all dig permits, site excavation plan, and markings prior to start of any digging. If damage or injury occurs from digging without a dig permit the CONTRACTOR shall be responsible for all repairs at no additional cost to the government. CONTRACTOR shall keep copies of all approved dig permits on site at all times.

1.6.3. Submit a Storm Water Pollution Prevention Plan (SWPPP) for approval by Clark County Engineer (30-day review process) for greater than 1 acre of disturbed surface area. If SWPPP plan is submitted, also submit a Notice of Intent (NOI) to the Ohio Environmental Protection Agency (OEPA) 21 days prior to start of construction and receive the Director’s Authorization before construction begins. Provide a copy of the NOI, Director’s Authorization, SWPPP, and SWPPP inspections to Environmental Management Office (EMO).

1.6.4. Pull all required state boiler permits and arrange a State of Ohio boiler inspection at time of completion prior to Pre-Final Inspection. Include any work required to obtain approval from the state boiler inspector in the cost of this proposal.

1.6.5. Obtain any required Air Quality (EPA) permit from the Regional Air Pollution Control Agency (RAPCA) for Dayton, OH.

1.7. QUALITY ASSURANCE / QUALITY CONTROL

1.7.1. Supply appropriate supervision and QA/QC for each task of the project to ensure the workmanship and product reflect the SOW and drawings. This project is commercial grade and only commercial type equipment, and fixtures will be accepted. The KO or COR may periodically perform QA checks as deemed necessary at any time during the PoP. These checks do not relieve the CONTRACTOR of the obligations under this section to provide a complete and working product.

1.8. PERSONNEL

1.8.1. A full-time Superintendent must be appointed and present at all times during work specified in this SOW and Drawings. The superintendent will be responsible for all onsite activities. Submit name(s) of Superintendent, and any identified alternates, to COR prior to issuance of NTP.

Page | 8

1.8.2. CONTRACTOR IS NOT required to report this contract in the Contract Manpower Reporting Application.

1.8.3. The GOVERNMENT is not liable for any injury incurred by CONTRACTOR, CONTRACTOR personnel, or other persons while they are on site. CONTRACTOR shall take full responsibility for the safety of all personnel within the project site, to include base personnel.

1.8.4. CONTACTOR shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. CONTRACTOR shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services, or local Security Office. CONTRACTOR shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF, and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.8.5. CONTRACTOR and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation /facility access and local security policies and procedures (provided by government representative).

1.8.6. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities, and Controlled Access areas shall complete AT Level I awareness training within 30 calendar days after contract start date. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT Level I Awareness Training is available at the following website: http://jko.jten.mil.

1.8.7. Violations of these policies may result in termination of the contract.

Compliance with security requirements shall not be a basis for failing to complete work in the required period of performance.

1.8.8. CONTRACTOR shall recover base passes upon job completion and return to Government within five (5) days of Final Inspection, if physical passes provided.

1.9. ENVIROMENTAL AND SAFETY

Page | 9

1.9.1. CONTRACTOR is responsible for all costs incurred for clean-up, sampling analyses, and disposal of spill debris as a result of CONTRACTOR’s actions. CONTRACTOR shall report all spills to the Environmental Management Office (EMO) immediately. If appropriate, cost incurred for clean-up by the 178 WG for CONTRACTOR’S actions will be reimbursed to the 178 WG from CONTRACTOR.

1.9.2. CONTRACTOR shall ensure that all personnel receive Environmental Management System (EMS) Awareness training and a copy of the Base Environmental Policy. A copy of the training can be obtained from the 178th Base EMO.

1.9.3. CONTRACTOR shall abide by the Asbestos Notification Requirements as outlined on the OH EPA website. This includes notification of the OH EPA upon the disturbance of more than 260 LF of piping, 160 SF on other facility components, or 35 CF of contaminated material.

1.9.4. CONTRACTOR shall abide by the OH EPA Green Procurement Program as outlined on the USEPA website.

1.9.5. CONTRACTOR shall stop work immediately and contact the 178th Base Environmental Management Office upon unearthing any historical or cultural artifacts during construction.

1.9.6. CONTRACTOR shall obtain all required permits and adhere to and abide by environmental requirements as stipulated by 178th Base EMO. This shall include but is not limited to the following forms:

1. Transient Organization Hazardous Material Inventory

2. Post-Project Waste Diversion Report

3. Recovered Materials Procurement Determination Form

4. Recovered Materials Determination Form

1.9.7. CONTRACTOR shall perform a jobsite cleanup each day and remove all debris and refuse from the site to the satisfaction of the COR. Unoccupied areas to be broom swept daily. Occupied areas shall be kept free of dust and debris at all times.

1.9.8. CONTRACTOR shall ensure that employees are supplied and use proper safety equipment (i.e. gloves, safety boots) described in OSHA, EM 385 & EM 304 and follow safe work procedures, which protect CONTRACTOR employees and personnel in the vicinity of the job site in accordance with all current OSHA requirements. CONTRACTOR shall assume any liability for any injury incurred by CONTRACTOR personnel while working on site.

1.9.9. CONTRACTOR shall maintain awareness to all NATIONAL DISASTER RESPONSES including Lightning Watch / Lightning Warning / Hazmat

Page | 10

Release / Severe Thunderstorm / Tornado Watch / Tornado Warning and shall:

1. Follow all Giant Voice Announcements as directed

2. Discontinue outside / inside work and seek shelter in designated shelter or building as directed

3. Follow directions from Shelter Manager or Senior Military

Official

1.9.10. In case of base emergency, CONTRACTOR shall dial 911 then alert Base Security (BDOC) at 937-327-2221.

Page | 11

2. CONTRACT REQUIREMENTS

2.1. GENERAL WORK DESCRIPTION (SYNOPSIS)

2.1.1. Remove and dispose of the existing 30-ton RTU. Provide and install a new RTU; install new curbing only if required to fit the new unit. Remove the existing DDC controller and install new. Install new controls onto all HVAC components that are currently on the DDC. Provide and configure a new computer and workstation for the DDC. Remove the existing roof access ladder and hatch handrail and install new.

Project Intent:

To repair the HVAC, associated controls, and replace the existing access roof hatch and ladder.

2.2. GOVERNMENT FURNISHED EQUIPMENT / PROPERTY

2.2.1. The GOVERNMENT shall provide basic/minimal documents describing the work required in this SOW. Drawings provided are to clearly identify know issues needing addressed. The CONTRACTOR shall be responsible to assess the job.

2.2.2. The GOVERNMENT shall provide the CONTRACTOR access to the site to include all areas of work described in this SOW.

2.2.3. The GOVERNMENT shall provide no other equipment, services, or property.

2.3. PERIOD OF PERFORMANCE

2.3.1. CONTRACTOR shall have a maximum of 90 calendar days from the initial Notice to Proceed (NTP) to complete the project including any design and construction. Any changes or extensions to this time period need prior approval from the CONTRACTING OFFICER.

2.3.2. CONTRACTOR shall have access to the site from 7:00 am - 4:30 pm Monday - Friday. CONTRACTOR will not have access to the site on Weekends and Government Holidays unless approved by COR prior.

2.4. COMPLETION

2.4.1. The COR shall certify performance and final completion of this contract utilizing the Contract Pre-Final/Final Inspection and Acceptance Report.

Page | 12

2.4.2. The CONTRACTOR shall restore any disturbed areas at the direction of the KO and the COR to include grading and reseeding to prior site condition.

2.4.3. The CONTRACTOR shall schedule a Pre-Final Inspection with KO and COR 10 days prior to end of Period of performance. Any Punch List items will be identified and recorded at this time.

2.4.4. CONTRACTOR shall schedule a Final Inspection with KO and COR upon completion of Punch List and within the final 10 Days, following the Pre- Final Inspection. This inspection will confirm that all Punch List items have been corrected. Upon completion of the Final Inspection the GOVERNMENT shall take over ownership of the project.

2.5. REQUIRED WARRANTIES

2.5.1. The CONTRACTOR shall provide a 1-year warranty on all material, labor, installed equipment, and work performed in this SOW in addition to any manufacturer’s warranties. Warranties shall be submitted using the submittal process within 30 days of project completion.

Page | 13

3. DETAILED DESCRIPTION OF WORK

3.1. Construction and Safety Practice

3.1.1. The CONTRACTOR will be required to photograph/document the existing site conditions prior to beginning work for record. Existing condition photos must be submitted through the submittal process.

3.1.2. The CONTRACTOR will be required to photograph/document progress throughout construction, Daily/Weekly depending on project duration.

Progress photos must be submitted through the submittal process Weekly.

3.1.3. CONTRACTOR shall ensure that safe construction practices are used in accordance with current OSHA standards, EPA (RAPCA) requirements and base requirements. The Contractor shall submit a site safety plan prior to start of project. The Contractor shall maintain a clean job site at all times with daily clean-up.

3.1.4. CONTRACTOR shall field verify all measurements prior to execution.

3.1.5. CONTRACTOR shall provide all labor, material, and equipment to complete job as indicated in this Statement of work and Drawings.

4.1. RTU Demolition

4.1.1. The CONTRACTOR shall completely disconnect the RTU before removal.

4.1.2. The CONTRACTOR shall recover the existing refrigerant for disposal per EPA guidelines.

4.1.3. The CONTRACTOR shall provide a crane plan to remove the existing RTU.

4.1.4. The CONTRACTOR shall disconnect and remove the existing 30-ton RTU.

4.1.5. The CONTRACTOR shall demolish the existing RTU curb adapter if needed to fit the new unit.

4.1.6. The CONTRACTOR shall remove all construction waste from the property, to include the RTU.

4.2. HVAC Installation

4.2.1. The CONTRACTOR shall provide a crane plan for the installation of the new

RTU.

Page | 14

4.2.2. The CONTRACTOR shall provide and install a new RTU that is right-sized for the facility.

4.2.3. The CONTRACTOR shall disconnect the existing HVAC equipment from the 2 existing DDC controllers.

4.2.4. The CONTRACTOR shall remove the 2 existing DDC controllers and install one DDC controller in their place. Multiple controllers may be installed if required to connect all HVAC equipment.

4.2.5. The CONTRACTOR shall install new controls to all components of the system that are currently connected to the DDC, to include the RTU, boiler system, 17 VAV boxes, temperature sensors, and thermostat.

4.2.6. The CONTRACTOR shall demo the existing wall-mounted thermostats and install new thermostats with digital display, local setpoint adjustment, and occupancy override.

4.2.7. The CONTRACTOR shall provide and set up a new DDC headend unit for the system in Building 2, next to the existing headend unit.

4.2.8. The CONTRACTOR shall install new DDC software onto the headend unit. All components of the HVAC system that were on the previous system shall be configured onto the new computer. The DDC must be functional with the capability to adjust and override each part of the HVAC system.

4.3. Access Ladder Installation

4.3.1. The CONTRACTOR shall demo and remove the existing roof access ladder and roof hatch handrail.

4.3.2. The CONTRACTOR shall install a new aluminum handrail where the existing fiberglass handrail was.

4.3.3. The CONTACTOR shall install a new roof access ladder. The new ladder shall correct the maximum vertical step distance of 14” IAW OSHA standards. The step-off distance between the top ladder rung and roof must be between 7” and 12” inches perpendicularly.

5. Base Facility Standards

5.1. All finishes should follow the Base Facility Standards, if applicable. All finishes, and/or equivalents, will be approved through the material submittal process with COR approval. See attachments for Base Facility Standards.

Page | 15

6. BID STRUCTURE

Item Number Description Quantity Unit Amount 0001 BVGM252001 Bldg 1 Repair HVAC 1 Lump Sum $_______

7. POINTS OF CONTACT

7.1. Technical Inspector: Mr. Nick Owens -- (937) 525-2589

7.2. Technical Inspector: Mr. Shane Ober -- (937) 327-2163

7.3. Technical Inspector: Mr. Mike Howard -- (937) 327-2277

7.4. COR: Mr. Blake Melling – (937) 327-2352

7.5. Contracting Specialist: SSgt Seth Taylor (937) 327-2208

7.6. Contracting Specialist: TSgt Samantha McKinney (937) 327-2575

7.7. KO: MSgt Daniel Nuttall -- (937) 327-2379

7.8. Environmental Manager: Mr. Dylan Bunch -- (937) 327-2277

7.9. Real Property Manager: Mr. Jordan Deady -- (937) 525-2586

7.10. Dig Permit: OUPS Reporting -- 1-800-362-2764

8. ATTATCHMENTS

8.1. AF FORM 3000

8.2. AF FORM 3064

8.3. AF FORM 3065

8.4. Base Pass Information Required for Contractors

8.5. Transient Organization Hazardous Material Inventory

8.6. Construction & Demolition Debris Waste Diversion Worksheet

8.7. Recovered Materials Determination Form

8.8. Base Facility Standards

Page | 16

QUALITY ASSURANCE SURVEILLANCE PLAN

For: BVGM252001 Repair Bldg 1 HVAC Contract Number: NA Contract Description: The scope of this project is to replace the RTU on Bldg 1, install new controls on all components of the HVAC system, install a new HVAC controller, install a new DDC headend computer, and configure the new DDC software.

Contractor’s name: NA

1. PURPOSE

This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP does not detail how the contractor accomplishes the work.

2. GOVERNMENT ROLES AND RESPONSIBILITIES

The following personnel shall oversee and coordinate surveillance activities.

a. Contracting Officer (KO) & Contract Specialist (KS) - The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract.

The KO is ultimately responsible for the final determination of the adequacy of the contractor’s performance. The KS acts as an acquisition consultant and serves as liaison between the contractor and the requesting agency.

Assigned KO: MSgt Samantha McKinney Assigned KS: TSgt Seth Taylor Organization: 178 MSG Organization: 178 MSG Telephone: 937.327.2379 Telephone: 937.327.2208 Email: samantha.mckinney.1@us.af.mil Email: seth.taylor.8@us.af.mil

b. Contracting Officer’s Representative (COR) & Construction Specialist - The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.

The contractor shall refer any changes they deem may affect contract price, terms, or conditions to the KO for action. The Construction Specialist assists the COR with daily monitoring of the construction project.

Assigned COR: Mr. Blake Melling Assigned Construction Specialist: Mr. Nick Owens Organization: 178 CES Organization: 178 CES Telephone: 937.327.2352 Telephone: 937.327.2589 Email: blake.melling.1@us.af.mil Email: nicholas.owens.2@us.af.mil mailto:samantha.mckinney.1@us.af.mil mailto:seth.taylor.8@us.af.mil mailto:blake.melling.1@us.af.mil

Page | 17

3. CONTRACTOR REPRESENTATIVES

The following employees of the contractor serve as the contractor’s Program Manager and Quality Control for this contract.

Program Manager/Contractor Quality Control – Name Telephone: (937)000-0000 Email: Contractor01@Example.com

4. PERFORMANCE STANDARDS

The completeness, timeliness, and satisfaction of the work performed will be evaluated based on the project requirements, period of performance, and quality of the work. Completeness of project requirements means all items specified in the Statement of Work (SOW) are done.

Timeliness is evaluated based on the work performed according to the schedule submitted.

Quality of work is judged based on appearance and functionality.

5. RATINGS.

A rating scale shall be used to determine a positive, neutral, or negative outcome.

COMPLETENESS

Yes Performance met contract requirements.

No Performance did not meet contract requirements.

TIMELINESS

Blue Ahead of schedule Green On time Red Behind schedule

QUALITY

Blue Exceptional quality; above and beyond expectations Green Acceptable quality Red Unacceptable quality

6. DOCUMENTING PERFORMANCE.

Performance will be documented on the Quality Assurance Chart attached.

a. ACCEPTABLE PERFORMANCE.

The Government shall document positive performance on the Quality Assurance Chart.

b. UNACCEPTABLE PERFORMANCE.

When unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the COR shall document the discussion and place it in the COR file. The contractor will propose a

Page | 18 corrective action/plan for the COR’s approval. Once approved by the COR and the KO authorizes the work, the contractor will complete the corrective action.