SOW B2 Switchgear H7 Freq Converter (004).pdf
PDF 821 KB Posted
- Attached to
- Bldg. 2 and Hangar 7 Electrical Upgrades Federal contract opportunity
- Solicitation number
- W50S8J-20-R-0007
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W508SJ20R0007 P001.pdf | ||
| W50S8J-20-R-0007.pdf | ||
| B2 SWITCHGEAR Q and A updated 13 May 2020.pdf | ||
| B2 SWITCHGEAR Site Visit Q and A.pdf | ||
| Site visit sign in sheet.pdf | ||
| SFS_FORM_31 V8 BADGING FORM.pdf | ||
| SOW Attachment 1- UFGS 26 35 43.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
Building 2 and Hangar 7 Electrical Upgrades
Project Number VBDZ202102
BASE BID – BUILDING 2 SWITCH GEAR
DESCRIPTION:
The Contractor shall provide all construction services and materials to replace the existing 120/208 volt 3 phase; 4 wire 800 amp electrical switch gear equipped with an 800 main breaker, located in Building 2.
Switch gear that is currently in place is manufactured by Federal Pacific. The switch gear powers the main hangar (Hangar 1), along with all of Building 2 and Building 12.
New switch gear must be equivalent or superior in performance and capacity to the current configuration, and must be approved by the Contracting Officer Representative (COR) prior to purchase and installation.
A. Demo:
1. Remove existing switch gear
a. All material and debris will be discarded appropriately by the contractor.
b. Receipts and weigh slips of all recycled materials are to be submitted to the Civil
Engineer Squadron (CES) for inclusion in the project completion report
2. See attached base map to show location
3. See photos below for base map, electrical room entrance, and equipment details
B. Construction
1. New switch gear shall be configured as follows:
a. 2- 400 amp fused buckets
b. 1- 600 amp fused buckets
c. 1- 200 amp fused buckets
d. 2- 30 amp fused buckets
e. 6- 100 amp fused buckets
2. New switch gear is to have surrounding items reattached, once it is installed. Items include an existing side breaker panel, an existing E-MON D’MON sub meter mounted on it, and an existing trough. All items should function properly once reconnected.
3. New switch gear shop drawings and layout are to be submitted for approval by COR, prior to execution
C. QA/ QC
1. Reconnect to all loads with phase rotation remaining as existing setup. Confirmation testing with base electrician personnel present is required.
D. SPECIAL NOTE
1. Scheduling of the project is to be coordinated with CES. This switchgear is the main electrical supply feed for multiple maintenance work and office areas, as well as the main aircraft hangar.
Work is to begin on an Alternate Workday Schedule (AWS) Friday, and to be completed by the
Sunday evening of the same weekend, which is a total of 3 calendar days.
2. Empty conduits that are attached to the topside of the switch gear will not require reinstallation.
These conduits will be identified during the site walk through.
Photo 1. Location Map
Photo 2. Switch Gear Access at Bldg 2
Photo 3. Existing Switch Gear with Side Trough
Side Trough
Photo 4. Existing Switch Gear with Panel and Meter
Side Breaker Panel
Sub Meter
Photo 5. Existing Switch Gear Plate Information
Photo 6. Existing Switch Gear Plate Information
BID OPTION #1 – HANGAR 7 FREQUENCY CONVERTER
DESCRIPTION:
In addition to the base bid, Contractor shall provide all construction services and materials to replace the existing precision frequency converter in Hangar 7. Existing frequency converter is 90 kVA, 400 Hz equipment manufactured by FCX Systems, Model #PFC072-V-40-FM.
New frequency converter must be equivalent, or superior in performance and capacity compared to the existing converter. Converter manufacturer, design and model number must be approved by the COR prior to purchase and installation.
A. Demo:
1. Remove existing precision frequency converter
a. See site plan below for location of converter
b. See photographs below of existing unit and plate
c. All material and debris are to be discarded by the contractor.
d. Contractor to provide receipts for all materials that are recycled. Receipts must be included in project completion report
B. Construction
1. New frequency converter shall be a 90 kva, 400 hertz converter.
2. New frequency converter drawings and layout are to be submitted for approval by COR, prior to execution
3. Requirements:
a. OUTPUT POWER RATING: 400 Hz – 90 kva
b. INPUT VOLTAGE: 480V/3ph/60Hz
c. INPUT CONNECTION: 3 Pole Thermal Mag. Trip Circuit Breaker, operable form the front of unit.
d. OUTPUT VOLTAGE 400 Hz: 200/115V/3ph/400 Hz (wye configuration)
e. OUTPUT CONNECTION 400 Hz: 3 Pole Contactor rated for 45kva with
Enable/Disable control and Aircraft Interlock Circuit
f. UNIT ENCLOSURE ENVIRONMENTAL RATING: Outdoor (NEMA 4 equivalent)
4. Installation timing and testing must be coordinated with hangar usage and base personnel availability.
C. Field Testing – QA/QC
1. Field testing and training is to occur in the presence of base electrician and shop personnel.
Training is to cover operation, maintenance and servicing of the equipment.
2. Load bank rental is to be included to test the converter once installed at unity power factor.
3. Project to include all associated freight and personnel travel charges.
D. Codes and Standards
1. Purchase and installation of the frequency converter must be compliant with the following codes
a. UFGS 26 35 43
b. MIL-STD-704F
c. NFPA 70
E. SPECIAL NOTE
1. Scheduling of the project will have to be coordinated with civil engineer (CE) and maintenance
(MXG) squadrons.
Photo 1: Location Map
Photo 2: Frequency Converter Plate Information
Photo 3: Frequency Converter Plate Information – continued
The Contractor shall provide all personnel and necessary equipment to establish an adequate and safe work zone
CONTRACTOR REQUIREMENTS
1. The Contractor will submit all warrantee information against defects in material and workmanship upon completion of installation.
2. The Contractor will notify DigSafe and have a signed form from CES prior to any excavation.
3. The Contractor is responsible for accuracy of all measurements and the implementation of appropriate building codes. The Contractor must get approval from Civil Engineering
Production Control (344-2441) and/or Engineering (344-2445) before starting work and before any utility shutdowns.
4. The Contractor is responsible for site cleanliness.
5. The Contractor will assist in the filling out of the Air Force Form DD1354 to signify the acceptance of the project by ANG and authorize the capitalization of the asset. Once completed the contractor will be required to sign, at which time they will receive the 5% being retained until signature on DD1354 has been completed.
6. The Contractor shall provide product submittals for materials prior to beginning work. The
109th Civil Engineering Squadron will review product submittals and return them to the
Contractor. Only materials approved by the 109th Civil Engineering Squadron will be used for this project.
7. All contractor employees, to include subcontractor employees, requiring access to Government
Installations, Facilities and Controlled Access areas shall complete locally generated AT training equivalent to AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable.
8. In accordance with AFI 10-701, Operations Security, OPSEC
PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 90 days of employees’ initial assignment to the contract and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial OPSEC training is locally generated and will be provided during badge issue.
9. The use and possession of controlled substances to include marijuana (medical or recreational use) on the installation is in violation of Title 10 US Code 912a. Art 112a. Contractors are notified this policy is strictly enforced and violators will be denied entry. Personnel caught on the installation can be prosecuted.
10. Contract manpower reporting is required.
PROPOSED PROJECT SCHEDULE
The project will begin 14 days following the Notice to Proceed. The project shall be completed within 6 months following the notice to proceed. This schedule includes lead time required for equipment ordering.