USAG BENELUX

ENGINEERING DIVISION

HANGAR # 6 - CHIEVRES AIR BASE

HAINAUT - BELGIUM

SPECIFICATIONS FOR

PROJECT R-CH # O2D-19199-9J

LOCATION Chievres Air Base

TITLE Replace water piping at the CAC

DATE March 2020

PERFORMANCE PERIOD 150 calendar days (the notice to proceed period included)

INDEX

CHAPTER I : GENERAL

CHAPTER II : TECHNICAL PROVISIONS

SECTION 1 : PRELIMINARY WORK AND DISMOUNTING/DEMOLITION

SECTION 2 : MISCELLANEOUS OPENINGS, CHASES, ROUTES AND

RESSERRAGE

SECTION 3 : WATER DISTRIBUTION SYSTEM

SECTION 4 : ELECTRICAL INSTALLATION AND BMS

SECTION 5 : SANITRY DEVICES AND FITTINGS

SECTION 6 : WALL AND CEILING

SECTION 7 : INSPECTIONS, TESTS AND COMMISSIONING OPERATIONS

CHAPTER III : BID SCHEDULE

CHAPTER I

GENERAL

G-01 : SCOPE OF WORK

A) General work description

The purpose of this project is to replace the galvenized steel pipes used for the cold and hot water distribution.

The site of work is located: Chievres Air Base

Bldg 20004 7950 Chievres

B) Principal features

Principal items to be performed to accomplish the work consist of the following:

1) See various sections on previous page.

The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawing.

G-02 : DRAWINGS AND STANDARDS

A) Drawings

All work under this contract shall be carried out in strict conformity with the following drawing, which forms a part of these specifications.

DRAWINGS TITLE DATE

R-CH-O2D-19199-9J-1 Building 20004-Exisiting situation Mar 20 R-CH-O2D-19199-9J-2 Building 20004-New situation Mar 20 R-CH-O2D-19199-9J-3 Building 20004-False ceiling and wall tiles Mar 20 R-CH-O2D-19199-9J-4 Building 20004-Plumbing diagram Mar 20

B) Specific applicable standards

All Belgian norms and regulations (NBN (Bureau de Normalisation), EN (European Norm), etc.) in force concerning the performance of this project shall be applicable.

All regulations in matter of environmental, safety and health will be applicable

- General Regulations for Work Protection (RGPT) and Code on the welfare of workers on the work place

- 2010 ADA Standards for Accessible Design

- The technical information memos published by the CSTC (Belgian Building Research Institute).

- Standard tender specification 105/90 of the “Régie des Bâtiments” (Buildings Agency).

- Water distribution company regulations.

- Ministerial and Royal Orders.

- Fire prevention service recommendations.

- BELGAQUA technical provisions and EN1717.

- NFPA code

- Data sheets developed by the US Army.

- NBN EN 671-1 and NBN S21-019.

- Pipe-marking principles according to NBN69 (NEN 3050)

- UFC 1-200-02 High Performance and Sustainable Building Requirements

- ASHRAE 189.1 Section 6.3.2 – Secton 6.4.2 – Section 6.4.3 Building Water Use Reduction

- UFC 3-420-01 Plumbing

Not limited to those above.

G-03 : GUARANTEE, WORKMANSHIP AND MATERIALS

A) Workmanship and materials

All work done by the contractor will be in strict conformance with the best practices of the trades involved.

The contractor will employ workmen who are skilled in their particular trades.

In particular, all works with potential risk of refrigerants release to the atmosphere should be conducted under the direct supervision or by a person with a category I certificate as specified in the EU regulation (EC) 303/2008 and valid for the Walloon Region area.

For safety purposes, during the execution of the work, the contractor’s workers will have to speak French or English.

All materials will be brand new.

The contractor will in no way use asbestos containing materials for the performance of his work.

The paints will be lead free.

All hazardous products brought on site by the contractor must be documented on an inventory list with safety data sheet.

Equipment and materials shall be new, maintainable and repairable with spare or replacement parts easily available in the host nation.

B) Guarantee

The contractor will guarantee his workmanship and materials for a minimum period of 1 year after the date of final acceptance or for the period as specified by pertinent Belgian laws for the workmanship or materials in question, whichever is longer.

G-04 : SCHEDULING OF WORK

Prior to starting any work, the contractor will furnish the contracting officer, for approval, a detailed schedule showing the successive phases of the work. All interruptions or disturbance in normal functioning of US Government organizations will also be indicated (road closure, water or utility cuts).

The planning of the work must be set up, discussed and approved by the contractor, the building manager and the Government Point of Contact COR before the start of the work. A close coordination with the management and authorities of the base, i.e. Fire Department, is mandatory.

G-05 : AS-BUILT DRAWINGS

The contractor will submit detailed as-built drawings after completion of the project and before submitting the final bill. As-built drawings will be precise and accurate. They will be drawn on BENTLEY MICROSTATION v8 system or any other 100% compatible system. The CD-Rom of the basic project will be given to the contractor for correction at his request.

G-06 : DIGGING PERMIT, UNDERGROUND PIPES AND CABLES

Before starting the earthwork, the contractor will submit a written Digging Permit Request to the COR. He will provide minimum 15 days before starting the earthwork the situation drawings with the earthwork that will be performed, when the work will be performed, and all utilities near the earthwork site. Drawings must be of sufficient scale to clearly show the proposed work. The drawing of existing utilities will be provided to the contractor during contract award. No digging shall occur until written approval is provided by Chief Engineering, Plans and Services Division (CEPSD), Technical Director of Public Works (TDPW) or Director of Public Works (DPW).

Additional information (drawings, etc...) about underground pipes and cables can be obtained at the Engineer Division - Hangar 6 - Chievres Air Base.

However, this information is only given as an indication and does not in any way commit the responsibility of the U.S. Government. The contractor will thus be responsible for carrying out the required soundings to verify their exactitude.

The contractor will ensure that no underground pipes or cables of any kind and their accessories will be damaged during the performance of the work. Any repair is done at the contractor’s expense and to the same standard as before the damage.

G-07 : HOT WORK PERMIT

All security measures as stated in the General Work Safety Regulations (“Règlement Général sur la Protection du Travail” “RGPT”) will be complied with. Prior to starting the work, the contractor will ask a Hot Work Permit (for welding, cutting work, etc...) to the COR. This permit will be delivered by the U.S. Army Fire Officer.

In addition, no open fires or burning of trash will be allowed within the confines of the USAG Benelux (NSSG) Community.

Contractors, concessionaires or vendors performing work or conducting business on or in facilities under the jurisdiction of the USAG Benelux Military Community Commander Area of Responsibility will conform to this regulation. The COR will ensure that a copy of the French or Dutch translation of this regulation is handed to contractors at pre-construction conferences and that all requirements therein are adhered to. Specific requirements and limitations are as follows:

1. Smoking will be prohibited in the vicinity of hazardous operations and locations.

2. Waste material and rubbish will not be stored or allowed to accumulate within the building or in the immediate vicinity, but will be removed from the site at least daily.

Rubbish will not be burned on the site.

3. Contractor materials and equipment will not be stored in a location or manner which will create a fire exposure to facilities adjacent to the project site.

4. The contractor will provide fire extinguishers at all locations where work is carried out.

5. In every building operation where a shed, storage, or other shanty is placed, or room or space is used for storage or workshop, the contractor will provide at least one approved portable fire extinguisher in an accessible location.

6. Flammable liquids and other hazardous materials such as paints, paint thinner, gasoline, asphalt, and tar will be stored in small detached structure or out in the open and not inside main buildings. Low flash point liquid used within buildings will be handled only in approved safety cans.

7. Adequate ventilation will be provided for paint spraying and operations involving the application of materials using adhesives containing flammable solvents. Such operations will be conducted remote from any potential source of ignition.

8. Asphalt and tar kettles will be located in a safe place outside of the building. Such kettles will not be placed on roofs or porches. Continuous supervision will be maintained while kettles are in operation. Metal covers will be provided for all kettles to smother flames in case of fire.

9. Electrical wiring and equipment for lighting, heating, and power purposes will be installed in compliance with current US and Host Nation Electrical Regulation requirements.

10. Cutting and welding will not be permitted unless:

a. A valid Hot Work Permit (welding permit) is available.

b. Combustibles have been safely covered or moved away.

c. A fire guard with a serviceable fire extinguisher is posted for the duration of the work and 30 minutes thereafter to assure that sparks or drops of hot material do not start fires.

11. Fire hydrants will only be used for fire fighting and training of the local fire and

Emergency Services. Water can only be taken from hydrants with the permission of the Community Fire and Emergency Services Office. Parking within 2.5 m (8 feet) of a hydrant is not permitted.

12. Vehicles and other equipment with fuel driven motors, with mounted and filled fuel tanks will be equipped with 2,5 kg or larger carbon dioxide or dry chemical fire extinguishers.

13. Gasoline, oil and grease shall not be disposed into drainage systems or public water systems. Oil contaminated areas will be covered with an absorbent material and removed in accordance with the Spill Contingency plan. Any POL spillage will be reported immediately to the DES Fire and Emergency Services Office, DSN 597- 5214/5211 or Civ 068/25 5214, 068/25 5211 .

14. Construction offices, huts, construction vehicles, trailers and supplies will be located at least 10 m from all adjacent buildings.

15. Access for fire fighting vehicles will be provided to the immediate job site at the start of construction and maintained until all construction is completed. Vehicle parking control measures will be established.

16. Free access from the street to fire hydrants and to outside connections for standpipes or other firefighting equipment, whether permanent or temporary, will be provided and maintained at all times. No materials or constructions will be placed within 10 feet of such hydrants or connections, or between fire hydrants and the center line of the street.

17. Scaffolding materials or equipment will not block fire escape routes or access routes during performance of projects in occupied buildings.

18. In all buildings over 30 feet in height at least one stairway will be provided in a usable condition at all times.

19. Notification and actions to be taken in case of a fire:

a. Persons who discover a fire shall immediately alarm all personnel in the area, and shall report the fire to the Community Military Police using the nearest telephone. Military telephone dial 117.

b. The fire shall be reported using the building number. If the fire is outside of a building, the nearest building number shall be given. Stay on the phone until the operator on duty has completely understood and does not have any further questions. After the notification you should immediately ensure all windows and doors are closed and that all personnel have left the area. The responding fire department must be informed if any special dangers exists; example: If gas and pressurized containers, or paint and other flammable material are within the range of the fire. Not only acute fires, but also fires which have been extinguished and did not cause any damage must be reported.

c. To ensure smooth notification and fire fighting procedures, it is essential to show all employees the location of the nearest telephone, make sure they are familiar with the building number in which they are employed, and inform them of the locations of the fire extinguishers.

Also, for fire safety reasons, hot work permit will not be issued to perform cutting or welding operations before or after USAG BENELUX AOR regular duty hours.

G-08 : ENVIRONMENTAL STEWARDSHIP

All measures shall be taken to prevent occurrence of spills during works. When a leak is detected (i.e. fuel leak on field works vehicles or company vans), the contractor shall proceed to the immediate clean-up of the spill. Should the spill characteristics exceed the contractors response capacities, the contractor shall immediately contact:

1) The COR

2) The Chievres Air Base Fire Department (068/ 25 5214).

3) The USAG Benelux Environmental Division (068 27 5704)

4) The Spill Response Coordinator (068 27 5906)

The contractor must comply with all European, Belgian and regional environmental laws and regulations as well as regulations specified within the Belgian Final Governing Standards (BFGS). The BFGS is available on request through the Government Point of Contact COR).

BFGS requirements that should be followed include, but are not limited to, the following:

BFGS Requirements

Air:

Any work that may potentially result in the release/recovery/recycling of a refrigerant requires the supervision of a trained refrigerant technician. (C.2.3.6.1.)

The use of the following Ozone Depleting Substances is prohibited: CFC’s, other fully halogenated chlorofluorocarbons, Halons, Carbon tetrachloride, 1.1.1.trichloro-ethane, Carbon tetrachloride, Hydrobromoflurorocarbones, bromochloromethane. (C.2.3.6.5.1) The following use of Hydrochlorofluorocarbons (HCFC)s is prohibited: aerosol, solvents, and refrigerants. (C2.3.6.5.2)

Drinking Water:

Only lead-free pipe, solder, flus and fittings can be used to repair water systems and plumbing systems for drinking water. (C.3.3.1.11)

Waste Water:

Best Management Practices (Table C4.T1) Protect fueling areas from rain and store spill response equipment nearby.

Construct sediment dams/silt fences around construction sites.

Perform corrosion control activities inside.

Store product drums/materials inside or under cover.

Capture sandblasting media, any paint waste and clean up materials (thinners, rinsates) for proper disposal.

Hazardous Materials (HMs):

HM containers and storage areas must be properly maintained. (C5.3.2)

Dispensing and storage areas for flammable liquids must have secondary containments.

(C5.3.2) All HMs must be labeled correctly. (C5.3.9) All persons who use, handle or store HMs must be appropriately trained. (C5.3.10) HMs must be in a locked cabinet/compartment when not in daily use. (C5.3.13.7 and C5.3.13.8.6.1) Non-fixed liquid petroleum gas (LPG) containers must be stored outdoors. (C5.3.13.1) Each HM must have a readily available Material Safety Data Sheet (MSDS) in English OR the predominant language. (C5.2.15)

Hazardous Waste (HW):

HW generated by the contractor will not be stored on Base, even temporarily, and must be disposed of at the cost of the contractor and by the contractor to an authorized facility outside of USAG Benelux.

HW should be segregated by the different hazardous characteristics (corrosive / flammable etc). (C6.3.2.1) All HW containers must be closed, in good condition and with no traces of corrosion, leaks or spills. (BFGS C6.3.4 -> C5.3.2) HW containers must be labeled correctly. (C6.3.4 ->C5.2.8)

Solid Waste:

Solid Waste must be disposed of at the cost of the contractor and by the contractor to an authorized facility outside USAG Benelux installations. It is recommended that the waste is recycled to the maximum extent possible.

Petroleum, Oil and Lubricants (POL):

At a minimum, all personnel handling (POL) shall be trained annually in the operation and maintenance of equipment to prevent discharges; discharge procedure protocols; general facility operations and the USAG Benelux (Belgian installations) Red Plan (updated regularly).

(C9.3.6) If the fueling of vehicles/machines is required on an installation it must take place on an impervious surface that drains to an oil-water separated. (C9.3.8.1.4.2)

Noise:

The contractor shall not cause sound levels in surrounding public place to exceed an established maximum level of 90dB (C10.3.1.)

Breaking and sieving activities shall neither be performed between 1900 and 0700 nor on Saturdays, Sundays or holidays. (C10.3.5.2.1)

Historic and Cultural Resources:

Any discovery of archeological resources shall be reported to the project COR within three business days. (C12.3.8.1)

Asbestos:

There are buildings and structures throughout USAG Benelux that contain asbestos. In particular asbestos can be found in cement piping, cement roofing, boiler gaskets, cement panels, cement chimney inspection holes and thermal system insulations. The identification of asbestos within a building and/or structure will be made within the work specific Environmental Review. Any asbestos that is removed due to work under this contract must be disposed of correctly, at the cost of the contractor, by the contractor and to an authorized facility outside of USAG Benelux.

Spill:

When using and/or storing HMs or POLs the contractor must have the ‘Red Plan’ readily available, in English AND the predominant working language. The Red Plan is different for the Walloon and Brussels regions and is updated regularly.

Work-Specific Environmental Reviews the contractor will receive an Environmental Review that is specific to the requested work The contractor must also respect and apply all environmental measures defined in the Environmental Review as it will mention site specific precautions that are not mentioned within this review. The review will be written by the USAG Benelux Environmental Division and communicated to the contractor through the COR.

The USAG Benelux Environmental Management System (EMS)

USAG Benelux Environmental Management System (EMS):

USAG Benelux implemented EMS IAW EO13423, ISO 14001:2004(E), DoD, and IMCOM requirements. An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. USAG Benelux and EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause a real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities, and authorities while supporting the Garrison’s mission.

Contractors and their personnel are required to be aware of, and comply with, the Garrison EMS policy and legal and other requirements when performing work at an installation.

The Garrison EMS is explained during the contractor pre-performance meeting and/or in the EMS manual, which may be requested from the Environmental Division.

G-09 : SITE MAINTENANCE AND FINAL CLEANING

During performance of works, all measures should be taken to avoid improper temporary storage of waste generated by works. In particular, emphasis will be put on POL(Petroleum, Oil and Lubricants) containing equipment or soiled waste/hazardous waste (scrap metal, contaminated soil) As soon as the work is finished, the contractor shall remove all his equipment, excess materials, debris, etc. generated by his work and will evacuate them outside US Government installations.

G-10 : COORDINATION IN MATTER OF SAFETY AND HEALTH

1. The law of 04 August 1996 related to the welfare of workers during the execution of their work and the royal decree of 25 January 2001 concerning temporary or mobile work sites are applicable for this project.

In accordance with article 71, §3, of above mentioned royal decree, a project-coordination as foreseen in section III, 1st sub section, of this royal decree has been set up during the elaboration of this project. Therefore, there is a safety and health plan related to this project for these specifications.

The contractor will comply with the recommendations of this safety and health plan (available upon request to the “Engineering Plans and Services Division”, Hangar # 6, Chievres Air Base (David Diricq, EPS Division, tel.068/27.54.46). These recommendations are part of this project.

In application of the same article 71, §3, an execution-coordinator will be designated by the COR for the coordination in matter of safety and health during the execution of this project.

Within 15 days after contract award, the contractor will submit at least 4 proposals of execution-coordinator to the COR’s approval with:

the necessary documents for the verification of the compliance with the conditions to exercise the coordinator function (art. 56 to 64 of R.D. dated 25.01.2001 completed by the royal decree of 19.12.2001)

No proposal may emanate from a coordinator working for the awarding firm or for an office on which the contractor has a supervisory position.

The COR has 10 calendar days to choose the execution-coordinator.

The coordinator’s fee is at the contractor’s charge.

2. The contractor has 15 days from the selection of the coordinator to make up and transmit to the C.O.R. and to the execution-coordinator a document with all the complementary elements to his bid that could be claimed by the coordinator.

3. The execution-coordinator does not act as a substitute for the COR. He plays the role of an advisor of the awarding party. His mission is the following:

3.1. General obligations from the law of 04 August 1996 and royal decree of 25 January 2001

1. to coordinate the implementation of the general prevention principles described at article 5 of the law of 04 August 1996, during the technical or planning selections, in order to schedule the various simultaneous or consecutive works or phases of work, as well as during the expectation of the duration of these various works or phases of work;

2. to coordinate the implementation of relevant provisions in order to ensure that the contractors properly implement the general prevention principles and execution principles described at articles 4, 5 and 15 of the law of 04 August 1996;

3. to draw up a coordination logbook comprising the elements described at article 33 of the royal decree of 25 January 2001, except for elements dealing with the design of the project, and to update it;

4. to write down the deficiencies of the various parties in the logbook and to notify the

COR;

5. to write down contractors’ remarks in the coordination logbook and leave them for information to the parties concerned;

6. to call and be the chairman of the coordination structure when such a structure has to be set up in accordance with article 37 of the royal decree of 25 January 2001;

7. to draw up an ulterior performance file whose content conforms with article 36 of the royal decree of 25 January 2001;

8. to organize the cooperation and coordination of activities between contractors, including those who follow one another, in order to ensure the protection of workers and the prevention of accidents and professional health hazards, as well as their mutual information;

9. to coordinate the supervision of the proper application of work procedures;

10. to take all necessary precautions so that only authorized people have access to the work site.

11. at the provisional acceptance of the work, to hand over the updated logbook and the ulterior performance file to the COR, and to notify this delivery in a record attached to the ulterior performance file.

3.2. Special obligations within the scope of this project

1. to read and understand these specifications related to the work to be executed, especially the article concerning the safety and health measures to be implemented on the work site in application of the law of 4 August 1996 about the welfare of workers during the execution of their work, and of R.D. of 25 January 2001 about temporary or mobile work sites;

2. to give advice to the COR and to make proposals in due time concerning the implementation and adaptations of the document described at item 2 of above mentioned article, during the previous phase described in that item 2 as well as during the execution of the work;

3. to participate in any meeting to which he is invited by the COR, and to set up himself any useful meeting with the COR, the contractor or any intervening party on the work site, for the execution of his mission;

4. to control the application of the hazards prevention measures described at item 3 of the above mentioned additional article;

5. to write down the contractor’s obligations deficiencies as foreseen in above mentioned item 3 in the logbook.

4. The contractor applies the hazards prevention measures foreseen in the document described at item 2, adapted if necessary. He has the sections of this document applied by the possible subcontractors if they apply to them.

5. During the execution of the work, the contractor updates the document described at item 2, either on his own initiative, when the progress of the work, the identification of unforeseen or insufficiently known hazards, the incoming or outgoing of some parties, or any modification brought to the project or the work justifies, or at the COR’s request. If some update occurs on his own initiative, he informs the awarding party and the execution-coordinator. He takes into account any possible remark expressed by the COR.

In particular, he also provides the following information to the COR with a copy to the execution-coordinator:

name of the subcontractor(s), the nature and cost of the work they are responsible for, the expected starting date and duration;

traffic rules and road signs for the work site, for the public traffic area (automobiles, bicycles, handicapped people…) and for the area reserved for the work and workers, and the access rules;

storage procedures and evacuation of materials and debris;

work planning.

6. The contractor must cooperate to the coordination as described above. To that purpose, he will give to the execution-coordinator, spontaneously or at his request, any information that is indispensable for the good execution of his mission. He will invite him at any meeting where his presence is necessary for the accomplishment of his task. He will participate in meetings where he is invited by the COR or the coordinator.

The contractor will have the obligations of previous paragraph applied by possible subcontractors.

7. The compliance with the obligations described in items 2, 5 and 6 above is an integral part of this project.

The application of hazards prevention measures described at item 4 is also an integral part of the project, provided that these measures do not exceed the general obligations that the law of 4 August 1996 and the R.D. of 25 January 2001 impose to contractors, in particular articles 7 and 15 of the law, and section VI, sub section IV of the decree.

8. The full text related to the coordination in matter of safety and health concerning this project can be consulted upon request to the “Engineering Division”, Hangar # 6, Chievres Air Base (David Diricq, tel.068/27.5446).

G-11 : ACCESS TO THE MILITARY INSTALLATION

See Clause CCE-225-4001 Installation Clearance Requirements in the administrative/contractual portion of this package.

G-12: ANTITERRORISM AND OPERATIONS SECURITY REQUIREMENT

Access and General Protection/Security Policy and Procedures.

1. The contractor and all associated subcontractor employees will comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor will also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

Contractor must receive written approval from PAO prior to taking any photos or making any sketches, and may not discuss layout of any infrastructure with anyone outside the USAG Benelux or not associated with the contract. Contractor must receive written approval from PAO prior to taking any photos or sketches. All photos, sketches, and designs must be returned to DPW upon completion of the contract

2. For Contract That Require Performance or Delivery in a Foreign Country.

DFARS 252.225-7043. The clause will be used in solicitations and contracts that require performance or delivery in a foreign country. This clause applies to both contingencies and non-contingency support. The key AT requirement is for non-local national contractor personnel to comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor’s compliance with combatant commander and subordinate task-force commander policy and directives.

G-13: FINAL ACCEPTANCE OF WORKS

The final acceptance of the work will be done in the presence of the COR and the contractor.

CHAPTER II

TECHNICAL PROVISIONS

SECTION 1

PRELIMINARY WORK, DISMOUNTING AND DEMOLITION

TP-1-01: Appropriate equipment

During the execution of the work, the contractor shall provide scaffoldings, ladders, elevators, etc… and all necessary equipment as well as the necessary workforce for a good execution of the work. He shall not ask or borrow equipment from the U.S. Government (ladder, scaffolding, lift machines…).

TP-1-02: Preparation of the work site, protection means and particular conditions

The contractor shall firmly fix panels or plastic sheets in order to fix boundaries to the work site area and to limit the spread of dust in the building. Additional protective measures shall be taken to protect the floor, walls and false ceiling.

Work shall only be performed during accurate periods of time determined by the building manager. All necessary protections means (plastic films, canvas, etc…) shall be used by the contractor to protect goods from dust and falling materials.

Any damage caused by the contractor will be at his cost.

The contractor shall clean the work site at the end of the work. The cleaning includes the removal of debris and dust, the cleaning with adequate products of glue marks, the cleaning with water of all surfaces and reinstalled equipment. The building manager shall inspect and approve the site before reusing it.

TP-1-03: Dismounting

Dismounted and demolished items mentioned below include the removal and evacuation out of the military area of all debris resulting from the work. All debris shall be evacuated to an authorized public dump at the contractor’s expense. All dismounted items become the property of the contractor, unless otherwise specified in these specifications or on the work site by the

COR.

Any damage caused by the contractor’s personnel during the demolition work shall be repaired at his cost.

All security protections as described in the "General Regulation of labor protection - RGPT" shall be complied with.

Important Remark: Building # 20004 remains occupied during the work phases!

For this reason, a close coordination between the contractor, the COR and the Building Manager is mandatory. A tight water and dust barrier shall be installed to separate the working areas and the occupied spaces. This barrier shall be submitted to the approval of the COR before installation.

The work will be performed by phases in order to grant access to fitness locker rooms (1 male and 1 female) at all time, the new appliances could not be connected on old pipe network.

The price for this barrier is included in the unit price of the item referring to these works.

Items to be removed:

- carefull dismounting of the sanitary equipment : washbasins, urinals, toilets, wall-fitted toilets, showers, mirror, soap dispenser and all other equipment in order to install and connect the new water pipes.

- Careful dismounting of the false ceiling panels

- Careful dismounting of light fixtures, ventilation ducts as necessary

- Dismounting of the heat plate exchanger

- Dismounting of the water softener

The appliances and equipment not reinstalled will be handed over to the COR.

Items to be demolished:

- removal of the wall tiles In shower: full removal of the wall tiling from floor to ceiling In toilet and locker: full walls from floor to ceiling where appliances are anchored.

- removal of all sanitary galvanized steel pipes and accessories.

- removal of all sanitary copper pipes and accessories.

- removal of the sanitary hot water loop between the heating room and the heating substation

- removal of required stainless steel pipes and accessories.

TP-1-04 : Cleaning

Cleaning during the performance of the work:

During the work, the Contractor shall be responsible for the cleaning and nice appearance of the work site. The debris generated by the work shall be removed daily.

The cost of the cleaning is included in the unit price of item TP-1-02.

SECTION 2

MISCELLANEOUS OPENINGS, CHASES, ROUTES AND RESSERRAGE

TP-2-01: Miscellaneous Openings, Chases and Routes

All miscellaneous openings, chases and routes shall be covered by the present contract.

Any openings in concrete structures must always be constructed via core drilling to avoid the lower spalling of the slab covering. Holes will be shaped and adapted to the diameter of the pipes (1 hole per pipe).

Under all circumstances, these openings must be submitted for the approval of the COR prior to their construction.

In cases where openings and routes may have been submitted in error, the Contractor shall be responsible for all consequences, such as, replugging the requested openings, creating other openings (where possible) and adapting the technical equipment. The same procedure shall apply if any required pocket, opening, chase or route cannot be constructed, taking into account the equipment and networks to be installed.

Chases must be constructed with an angle grinder, fitted with a dust intake system. The depth of a chase must not exceed one third of the thickness of the wall. Any chase in a wall or floor slab or roof shall be approved by the COR before starting the works.

In no case can the chase reduce the acoustical specifications.

Equipment to be embedded in false ceilings shall be supplied and fitted under the present work package.

The Contractor shall also provide and install all fire-protective elements in fire-resistant walls.

TP-2-02: Sealing of Ordinary Walls and Fire-Break Walls

Insofar as an opening or aperture is requested or supplied under the present contract or constructed by the Contractor, this opening in the wall must be sealed by the Contractor subsequent to the fitting of the pipes, using the same materials from which the wall with the opening has been constructed, or materials with equivalent properties.

Any other openings shall be sealed using special fireproof compound, resistant to atmospheric conditions, water, oil and the main corrosive agents.

The fire resistance of the walls shall be 2 hours, unless specified otherwise.

Prior to any operation, the projected sealing technique must be submitted to the approval of the COR, accompanied by test reports, in accordance with NBN 713.020 (Belgian standard). All fire-check sealings must comply with the ministerial circular of 15 April 2004 relating to the fire resistance of construction components.

Subsequent to the operations, all fire-check sealings must be subject to a report certifying their fire resistance, duly issued by the approved company which has effected the sealing operations.

All sealing techniques must also observe the acoustic properties of the wall crossed (cf. acoustic provisions of the present special specifications).

The cost of this section is included in the unit price of the pipe installation.

SECTION 3

WATER DISTRIBUTION SYSTEM

TP-3-01: COLD AND HOT WATER DISTRIBUTION SYSTEM

3-01-1: Distribution principles and limits of works

The purpose of the contract works is the replacement of the galvanized steel piping system used for the distribution of the hot and cold sanitary water in the building.

It includes the replacement of:

the domestic water distribution system for domestic use, the hot water distribution system to certain sanitary appliances, softened water production and distribution, With the execution engineering, testing and commissioning of the installation and other sundry work, the contractor shall be responsible for all work and supplies required for the water distribution facilities to meet the conditions imposed and comply with the Code of practice.

The characteristics and power ratings of the elements to be installed shall be defined on the current water distribution system.

These elements are provided to delimit the works and shall not dispense tenderers from establishing their bid on the basis of their own calculations and measurements.

The connection to the existing water piping is part of and shall be the starting point of the present scope works.

The contractor will have a new rate/pressure recorded and a measurement of flow & pressure prior to hardware selection, to control the network situation at the moment of works.

The constructor shall carry out at least the following work:

Supply and lay the cold water, hot water, softening.

Supply, fit and connect all sanitary appliances and their valves and fittings.

Supply fit and connect all materials needing water.

Drill all holes required.

Tightening of all drills used in the scope of the above work and those intended for it, and which have not been used.

Mark the piping system according to the standards NBN 69 / NEN 3050 color code for piping.

3-01-2: Applicable documents

Apart from the reference documents, the following documents shall apply in particular:

- The technical information memos published by the CSTC (Belgian Building Research Institute).

- Calculation method of DTU 60.11.

- Standard tender specification 105/90 of the “Régie des Bâtiments” (Buildings Agency).

- Water distribution company regulations.

- Ministerial and Royal Orders.

- Fire prevention service recommendations.

- BELGAQUA technical provisions and EN1717.

- NFPA code

- Data sheets developed by the US Army.

- NBN EN 671-1 and NBN S21-019.

3-01-3: Pipe dimensioning

Velocities must remain below 0.8 m/s for ND < 50 mm and 1 m/s beyond ND 50, out of peak periods.

During peak periods, the water velocities of main pipes may increase up to 2 m/sec temporarily.

However, the diameters cannot be less than those shown on drawings.

3-01-4: Description of the installation and fitting specifications

General A neutral material for potable water distribution shall be chosen.

For all the sanitary pipes, multi-layer pipe is required, type MEPLA (Aluminum – reinforced PE- Xe) from GEBERIT or similar.

This pipe will only be used up to ND 50. Stainless steel AISI 304 is required for the greatest sections > ND 50.

The domestic hot and cold pipe will be supplied from main pipes in the boiler room and the heating substation.

All domestic water pipes, except in the boiler room, will be laid preferably above the false ceiling and encased in walls to the appliances.

The base flow rates and minimum connection diameters are provided in the following table, in accordance with DTU 60.11.

Maximum design water consumption UFC1-200-02 requires compliance with ASHRAE 189.1, LEED-requirements impose maximum flow rates:

Name of appliance Design flow rate Kitchen faucet Sanitary faucet

1,9 l/min 1,9 l/min

Urinal flush WC flush

Showerhead

0.9 lpf Low flush : 2,0 lpf High flush: 4,0 lpf 5 l/min

Minimum connection diameters The minimum connection diameters are provided below, in accordance with DTU 60.11.

Name of appliance Nominal diameter (mm)

Kitchen sink Washbasin Shower Hand sink Double service tap (1/2") Double service tap (3/4") Mop sink Urinal WC (with water tank) Large dishwashing sink, mop sink

The potable water has calcium hardness around 40°Fr (French degrees). Therefore it is necessary to soften water before using it in machines with electrical heating and for sanitary hot water production.

3-01-4-1: Domestic cold water (not softened)

The Facility is supplied with cold water by means of a connection to the main existing distribution pipes. The interior cold water network shall be separated of the indoor fire protection network.

An anti-return system will be provided on the potable water piping at its connection point with the building, in accordance with NFPA-13 requirements, EN 1717 and the BELGAQUA code, to protect the outside network as to the building.

Another anti-return system is foreseen on the filling pipe of the heating water.

The potable water has calcium hardness of around 40°Fr (French degrees). Therefore it is necessary to soften water before using it in machines with electrical heating and for sanitary hot water production.

3-01-4-2: Domestic hot water (softened)

Hot water is produced by a solar water system and stored in three tanks (0,5 m³ per unit) located in the heating room.

Sanitary hot water is distributed at an average temperature of 60°C by a continuously circulating loop network.

A regular temperature increase cycle (anti-Legionnaire's disease treatment) is programmed.

This allows the user to control the temperature of the water distributed in loop and to program the periods for heat treatment.

The water shall be softened before heating up.

3-01-4-3: Softened cold water

The domestic cold water network, will be fed with softened water.

Softened water shall be produced by means of a duplex of ion exchangers. Each exchanger shall be equipped with its salt basin. A volumetric and chronometric regulator shall be provided in order to program the alternative regeneration of each unit. The system shall be designed so that the two units can work in parallel during high consumption periods.

Domestic water on site probably has a hardness around 40°French (to be checked by a water analysis in charge of the successful bidder to be supported by the present contractor).

A water softening system shall be installed for the water supply to sanitary installations and to fill up the heating installation. The capacity of the softeners will be calculated for the maximum water demand. Water will be softened to 12 – 13° Fr.

An automatic back flushing filter will also be provided

The hardness level of the water must be continuously controlled by a testomat 2000 after softening. The results must be sent to the BMS-system.

3-01-4-5: Laying specifications

Method of laying the cold water, softened water and hot water

The piping shall be protected wherever there is a risk of it being affected by cement, lime or any other corrosive product.

All precautions shall be taken to avoid noise due to the pipes rubbing against their brackets or building elements as they expand or contract.

All steps shall be taken to neutralize the effects of pipe expansion. The steps envisaged (curves, stainless steel bellows-type expansion joints with interior or exterior guides, loops, fixed points, etc.) will be presented before execution by a note and plans subject to COR’s approval.

All installations must be able to be drained at the start of the risers, at all low points and at the points shown in the plans to enable drainage of a particular part of the system.

Drain valves shall be fitted in accessible places.

After tapping into a main pipe, a shut-off valve must be fitted every time.

Up to and including ND 50, the valves will be full-flow ball valves. Over ND 50, butterfly valves will be used.

Control of legionnaires' disease

The system must be laid such that no water is allowed to stagnate and it must be fully lagged.

Thermometers on the output and return legs of the domestic hot water loop shall allow temperatures to be checked, especially during heat treatment phases.

A sampling point (plugged valve) must be provided after the public water meter and on the return leg of the domestic hot water loop.

Specific details for the domestic hot water system

The temperature of the hot water loop, kept in circulation, must be between 60°C and 65°C on output and higher to 55°C on return.

The temperature must be increased to 70°C at all points once every 24h. This procedure is directed and carried out by the maintenance division operating this installation.

Bypasses without a loop shall not exceed 5 m in length or 3 litres in capacity.

Protection of embedded piping

Built-in Polyethylene/alu/Polyethylene piping shall be used.

Such piping shall also withstand heat treatments, as they have the same properties as the visible pipes.

The contractor shall not embed pipe joints.

Piping support

All piping or pipe racks shall be fastened by means of hot-dip galvanized steel sections and rubber-lined clamps.

The supports will be designed to avoid the propagation of noise due to the expansion of the piping.

Metal-on-metal contact will therefore be prohibited.

A neoprene strip will be placed between the piping and the mounting clamp.

The supports will be studied taking account of the various fluids carried; individual supports for each fluid will not be accepted.

The supports will be fastened to the wall using expansion bolts sized according to the weight of the equipment.

Sufficient space will be left between the pipe and the support, between parallel pipes (wall or riser, for example) to enable the lagging to be fitted without crushing.

No pipe shall be hung from another pipe, except for small connections where no other means can be found.

Feed trough walls

Through walls, internal partitions and hollow floors, the pipework shall cross the steel expansion sleeves of a minimum tickness of 2 mm sealed into the walls.

The gap between the expansion sleeve and the pipework (or fire retardant accessories if it is a fire retardant wall) must be filled in with non-combustible insulating material that is not noisy during expansions (e.g. mineral wool).

The expansion sleeves extend at least 2 cm beyond the finished walls, ceilings and finished floors.

The "fire retardant" nature of any wall must be not be altered by the presence of pipework and expansion sleeves.

To this end, for any diameter, a fire retardant accessories shall be used :

Fire resistant flexible strip for Ø < 40 mm

Fire resistant collar for Ø ≥ 40 mm

Insulation of the domestic supply water systems

The pipes carrying cold domestic supply water (all accessories included) will be protected against the risk of condensation and excess heating up (> 25°C), by means of closed-cell synthetic foam lagging bonded to the entire surface.

Pipes carrying hot water (all accessories included) will be insulated against heat losses by means of rock wool tubes. There are to be no gaps in the lagging at the supports.

The thickness and quality shall be such that, at a nominal flow rate, the water shall not lose more than 5°C over the route of the domestic hot water loop following the longest circuit.

The tubes shall be supplied precut. Their inside diameters shall exactly match the outside diameters of the piping.

Fittings of hot potable water and cold potable networks must be insulated.

3-01-5: Tests

The network shall be completely washed and disinfected According to NBN EN 806 after the end of the works and tests, and before the commissioning.

TP-3-02: COMPONENTS AND ACCESSORIES

3-02-1: Mains water supply - Connection to the existing network – Inlet safety device

2 existing PEHD 50 conduits supply the building with sanitary water and water for the fire fighting networks.

The link between the connection to the distribution and the internal installation must be made in accordance with the provisions of the local water distribution company.

The contractor must provide before starting the performance,

- a report with :

* a record of static pressure during one week

* the pressure and the flow available downstream of the meter at peak hours of consumption on the private mains

- a data sheet for the safety system, approved by the company (S.W.D.E.)

Overall fixed amount for supplying, laying and connecting a complete system comprising valves and protection, from the distribution company supply (metering system) to the outlet column of the installation.

It must involve a tap connection for taking samples (plugged isolating valve).

3-02-2: Water meter

The water consumed is metered at certain points of the network using a axial/propeller flow meter.

The amount of water consumed must be shown in m³.

It must be possible to fit the meter as easily to a horizontal pipe as to a vertical pipe with an upward or downward flow.

Each meter must be followed by a draw-off point for taking samples (plugged insulation valve).

Properties

- water meter with axial propeller

- operating range: +0°C to +80°C

- maximum error level for a temperature of 20°C: 2 %

- cast iron body PN 16

- connections with flanges

- low frequency emettor

The water consumption will be sent to the BMS. All work to connect and configure the water meter on the BMS is included.

3-02-3: Water supply pipes

3-02-3-1: Polyethylene/Alu/Polyethylene hot or cold water supply pipes

1. General

These pipes constitute a hot or potable cold water distribution network to the tap connections.

This pipes and fittings are to be assembled by crimping.

The potable water distribution network shall be approved by the UBAtc.

2. Price Structure

- The price of…