About this file
This Statement of Work (SOW) details the United States National Arboretum's (USNA) requirement for a Radio Communications System Replacement. The project aims to replace an end-of-life VHF radio system across the organization's 450-acre campus, addressing critical communication challenges and operational risks. The contractor will conduct a site propagation study using Radio and Propagation Tools Repository (RAPTR), evaluate the current system's effectiveness, and recommend/implement a new radio communication system.
The period of performance is September 2025 to December 2025, with six key deliverables including initial planning/study, system procurement, configuration/installation, testing, final review, and project closeout. Contractor requirements include a minimum of five years' experience in radio communications systems engineering, ability to work on government facilities, staff qualified in engineering and installation, SAMs registration, and manufacturer certification. The project involves comprehensive services such as engineering, design, installation, programming, testing, and commissioning of a new radio communication system.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Construction wage determination 1232SA25Q0865.pdf | ||
| Solicitation clauses and provisions 1232SA25Q0865.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States National Arboretum (USNA)
Radio Communications System Replacement
3501 New York Avenue
Washington, DC 20002
Statement of work
Contents Project Title
General Information
1.0 Background and Purpose
2.0 Period of Performance
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Deliverable / Schedule
Project Title USNA Radio Communications System Replacement
General Information
1.0 Background and Purpose
The United States National Arboretum (USNA) current radio communications system has reached it End of Life (EOL) and End of Service (EOS) stages, which means that the system is no longer functioning properly and is no longer supported by the manufacturer. This presents significant challenges for the staff to communicate over the 450 acres on campus, presents operational risks for weather notifications, critical events, and safety protocol, is difficult to maintain/repair, and an absence of critical software updates and hardware replacements. The purpose is to contract services to access the current Very high Frequency (VHF) system coverage through a site Propagation study using Radio and Propagation Tools Repository (RAPTR). The goal of the study is to evaluate effectiveness of the VHF radio system accounting for environmental factors, topography, and other relevant parameters that could impact signal strength and coverage quality. Based on the study findings make recommendation for the purchase of a new radio communication system to include Radio equipment, programing and testing. The other services include Engineering, Design, Installation, Testing and Commissioning.
2.0 Period of Performance
The period of performance: September 2025 - December 2025
Contractor Requirements
3.0 Technical Requirements / Tasks
The contractor shall have the following:
1. A minimum of five (5) years’ experience in engineering and installing complex radio communications systems.
2. The ability to work on Government Facilities.
3. Have staff qualified in engineering, installation, programing, testing and commissioning of radio communication systems.
4. Registered in SAMs
5. Be certified by the system manufacturer for installation, testing, commissioning and repair.
4.0 Deliverable / Schedule
Key Deliverables
Item No. Deliverable Submitted To Due By
1 Initial Planning/ Study USNA PM, CO, COR, POC three weeks after award of contract
2 Procurement of System USNA PM CO, COR, POC Two weeks after completion of study
3 System Configuration, Setup and Installation
USNA PM CO, COR, POC Six weeks after Procurement of System Components
4 Testing and Commissioning
USNA PM, CO, COR, POC Two weeks after Installation
5 Final Review and Reporting
USNA PM, CO, COR, POC One Week after Testing and Commissioning is completed
6 Project Closeout USNA PM, CO, COR, POC One week after Final Review and Reporting phase.
Templates and directions will be provided During Kick-off Meeting.