Telecommunication Building Replacement, Cape Cod Canal, Sandwich, MA
Solicitation number
W912WJ24Q0073
Issued by

About this file

This document is a Request for Quotations (RFQ) for the replacement of the telecommunications building at the Cape Cod Canal in Sandwich, MA. The project consists of furnishing all labor, equipment, materials, and services to provide a new 12' x 14' precast concrete utility building, including a 24,000 BTU mini-split heat pump, electrical systems, and site work. The contractor will also be responsible for demolishing the existing building, foundation, generator, equipment pads, and underground utilities, and properly disposing of any hazardous materials. This procurement is set aside for small business vendors under NAICS code 236220 with a size standard of $45 million. Quotes are due by April 4, 2024, and award will be made based on price alone. The government will provide the disconnection of power to the existing building prior to demolition and reconnection of power to the new building upon completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CAPE COD CANAL

TRAVIS GERMANO

40 ACADEMY DRIVE

BUZZARDS BAY MA 02532-1555

TEL: 978-318-8550 FAX:

W13G86403734850001

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ24Q0073 19-Mar-2024 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

04-Apr-2024(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

978-318-8324JENNIFER M SAMELA

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ24Q0073

Section B - Supplies or Services and Prices

INSTRUCTIONS TO VENDORS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE 52.236-27

ALT I FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT QUESTIONS TO JENNIFER M. SAMELA AT (978) 318-8324 or

JENNIFER.M.SAMELA@USACE.ARMY.MIL. ANY INFORMATION RECEIVED AT THE SITE VISIT

WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE BROUGHT TO THE ATTENTION OF

JENNIFER M. SAMELA. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE

GOVERNING DOCUMENT IN ALL CASES.

** QUOTES CAN BE E-MAILED TO JENNIFER M. SAMELA AT

JENNIFER.M.SAMELA@USACE.ARMY.MIL.

NOTE 1: In accordance with FAR Part 28.101-1(c), the Contractor will NOT be required to provide a Bid Guarantee.

NOTE 2: In accordance with FAR Part 28.102-1(b), the Contractor will be required to provide the following payment protections for all construction contracts greater than $150,000.00.

(i) Payment Bond or

(ii) Irrevocable Letter of Credit and

(iii) Performance Bond

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

A Performance Bond shall be required if the total price of the quote is greater than $150,000.00. The penal amount of the Performance Bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall also be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 3: In accordance with FAR Part 28.102-1(c), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.

(i) Payment bond or

(ii) Irrevocable letter of credit

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 4:

QUOTATION INSTRUCTIONS:

1. If subcontractor will be used for this work, please provide company name:

2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit a quote (formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA)). Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website.

NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.

In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.

3. Provide business Unique Entity Identifier (UEI): _______________________________

4. Provide business CAGE code: __________________________________

5. Tax Identification Number: ___________________________________

6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above).

7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful Contractor will be required to submit this document at the direction of the Technical Point of Contact. The APP must be accepted by the Government Designated Authority prior to the commencement of work.

POTENTIAL VENDORS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS

PRICE ALONE.

ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST BE

CONSIDERED BY THE AGENCY.

INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Telecommunications Building Replacement

FFP

Contractor shall furnish all labor, materials, and equipment necessary to remove and replace the existing telecommunications building at the Cape Cod Canal, Sandwich, MA in accordance with the Statement of Work.

FOB: Destination

PURCHASE REQUEST NUMBER: W13G86403734850001

PSC CD: Y1JZ

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

PROVIDE and INSTALL

PRECAST UTILITY BUILDING AT SITE SANDWICH

U.S. ARMY CORPS OF ENGINEERS

CAPE COD CANAL PROJECT, SANDWICH, MA

STATEMENT OF WORK

I. General

1. Statement of Work

Contractor shall furnish all labor, equipment, tools, and materials to replace existing telecommunications utility building. Contractor shall provide (1) 12’ x 14’ precast concrete utility building, frost wall footing, site grading, structural backfill, underground conduits, and grounding ring. Contractor shall relocate existing propane tank, Cummins Quiet Connect RS36 Propane Generator, automatic transfer switch (ATS), and transformer onto new precast pads/vault. The new utility building shall include a commercial metal single door, 24,000 BTU mini-split heat pump, 200-amp main distribution panel, 100-amp electrical service panel, interior finished walls, outlets, lights, and a copper grounding system. Contractor shall deliver building pre-assembled to be placed on contractor’s prepared frost wall footing foundation. Work includes demolition, removal, and proper disposal of the existing building, foundation, Onan 35EK generator, equipment pads, and underground conduits. Contractor shall sequence the work and install temporary fencing as needed to protect the public and maintain physical security for the site. Work includes the proper handling and disposal of Lead-based paint hazardous materials. An Industrial Hygienist shall provide 100% onsite project monitoring/oversight during demolition activities. (See Figure 1, Photos 1-30, and attached Environmental Consulting and Management Survey Report dated 10/15/2021).

The Government will disconnect power to the existing building and will remove all active equipment, except the Onan 35EK generator, from the buildings prior to demolition. After installation of the new building and utilities, the Government will reconnect power to the new building.

2. Locations

The new utility building work site is located on federal property, adjacent to the Cape Cod Canal, at 12 Freezer Road, Sandwich, MA 02563.

3. Site Visits

A scheduled site visit for interested vendors will be listed in the Solicitation. Interested vendors should attend the site visit to confirm understanding of the scope, inspect field conditions, access, and existing utilities prior to bidding. No extra payment will be allowed for perceived additional work caused by unfamiliarity with site conditions and requirements.

After Contract award, the Technical Point of Contact (TPOC) for questions and site coordination is Travis Germano (978) 318-8550 or (Travis.J.Germano@usace.army.mil).

4. Schedule The work shall commence within 15 days after Notice to Proceed and shall be completed within 210 days of Notice to Proceed. The hours available for work are Monday to Friday 0700 through 1700 hours.

5. Safety Requirements A. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers

(USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

B. Accident Prevention Plan (APP):

The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.

The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf

A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Daily safety meetings shall be held and documented. Records shall be available to the

Technical Point of Contact upon request.

C. Activity Hazard Analysis (AHA):

An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard

Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf

D. Site Safety and Health Officer (SSHO) Requirements:

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A

Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the prime contractor’s SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf

E. First-Aid and CPR Personnel Requirements:

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employes work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

F. Additional Personnel Requirements:

Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1-1 and/or other sections of this Scope of Work, based on the definable features of work for this project.

G. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor and reported to the

Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.

The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Fo rm_3394_2021Aug.pdf

H. Employee Exposure Data:

The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.

I. Daily Reports: The contractor shall provide daily production and QC reports, employee work hours, and certified payrolls electronically to the Technical Point of Contact

J. Confined Space Entry Plan: A site-specific Confined Space Entry Plan is required to be submitted and accepted by the Technical Point of Contact (TPOC) prior to any work being completed in the electrical manhole vault. The plan shall contain and adequately address the Confined Space Program elements of 29 CFR 1910.146 and those defined in EM 385-1-1 Section 34.A.06-07.

K. Lead Based Paint (LBP): All LBP work activities, training, and submittals shall comply with EM 385-1-1, Section 06.C; 29 CFR 1910.1025; 29 CFR 1926.62; as well as State and local requirements.

L. Cranes: For any crane work, a Crane Lift Plan shall be prepared in accordance with EM

385-1-1, Section 16.H.03. All cranes shall have current inspection documents available.

All operators, signal persons, and riggers shall be trained and hold valid State licenses.

Provide proof of current qualifications.

6. Preconstruction Conference

Prior to the start of any work, the Contractor and Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel shall be physically present to attend this meeting. This conference will be scheduled for a time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the requirements in terms of safety, quality, submittals, communications, inspections, and payments.

7. Permits The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable federal, state, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security

The contractor will comply with all established security policies at Cape Cod Canal Field Office. Potential periods of heightened security may affect access to work areas. During periods of heightened security, the Government reserves the right, at any time, to close any property and reschedule work. The Contractor shall be given at least 24-hour notice of any such closure.

9. Contractor Conduct

The work area is located on Federal property. Contractor and employees must act in a safe and professional manner at all times. Alcohol and firearms are prohibited on project grounds.

10. Payment

Payment shall be made after final inspection and acceptance by the Government, the Contractor must submit an invoice, utilizing Form ENG 93, to the Technical Point of Contact. The invoice shall include the name of contractor (as per SAM registration), invoice date, contract number, description of work completed, and total amount due. For jobs greater than 30 days the contractor may request progress payments.

Invoices shall be emailed to:

US Army Corps of Engineers Cape Cod Canal Field Office P.O. Box 1555 Buzzards Bay, MA 02532 Attn: Travis Germano travis.j.germano@usace.army.mil.

II. Technical Requirements:

Part 1 General:

Contractor’s work and responsibility includes all job scheduling, personnel, equipment, materials, supervision, and quality control necessary to perform the work. Contractor shall provide bathroom and sanitation facilities for workers.

1. Requests for Information:

After contract award, questions concerning the work of this project should be directed to the Technical Point of Contact at the Cape Cod Canal Office at (978) 318-8550 or travis.j.germano@usace.army.mil.

2. Submittals:

Contractor shall provide submittals that show pertinent details of proposed materials that allows confirmation that materials are in accordance with requirements listed in the materials section of this statement of work. Although the Government technically reviews submittals, the Contractor’s work must be prosecuted using proper internal controls and review procedures. Contractor submittals must be reviewed and accepted by the government prior to the commencement of any field activities. Contractor shall provide required submittals to the Technical Point of Contact within 60 days of notice to proceed.

Required submittals include:

a. Accident Prevention Plan and Activity Hazard Analyses for all fieldwork.

b. Schedule

c. Site Work Plan and Traffic Control Plan – Provide a site plan with description of fence line, planned access points, storage of materials, soil stockpiles, dumpsters, signage, barriers, traffic control devices to protect the general public from hazards.

d. Excavation and Dewatering Work Plan

e. Crane Lift Plan

f. HVAC Refrigeration, Electrician, and Plumber State Licenses

g. Precast Utility Building: Engineering calculations, layout drawings that show all pertinent dimensions, penetrations, location HVAC equipment, door, frame, door hardware, electrical panel, lighting, and exact conduit layout.

h. Confined Space Entry Plan: A site-specific Confined Space Entry Plan is required to be submitted and accepted by the Technical Point of Contact (TPOC) prior to entering the primary electrical manhole vault.

i. Lead Compliance Plan: A site-specific Lead Compliance Plan is required to be submitted and accepted by the Technical Point of Contact (TPOC) prior to initiating lead abatement tasks.

j. Lead Final Clearance Sampling

k. For all materials to be used on the project, the contractor shall provide the following information:

i. Manufacturer’s name

ii. Catalog number

iii. Specifications

iv. Any other information necessary to approve the materials.

v. Safety Data Sheets (SDS) shall be submitted along with the product data for any potentially hazardous materials such as adhesives and flux materials. Use Low Volatile Organic Compound (VOC) materials wherever possible.

l. Operation and Maintenance Manuals for all installed equipment (Including Test Records) Operations and Maintenance Manuals – Provide (2) hard copy binders with drawings of building, approved submittals, asbuilts, manufacturers literature for equipment, and maintenance procedures.

m. Warranty

3. Government Resources:

The contractor is responsible for providing all resources to complete the project. The Government will not provide any equipment or services except which are explicitly stated within this statement of work.

4. Omissions:

This statement of work may not cover all specified activities, steps, and procedures required to supply the contract product. In cases where work is not specifically shown or specified, contract shall include miscellaneous items, appurtenances, devices, and materials obviously necessary for a sound, secure and complete installation. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

5. Quality Control and Quality Assurance:

The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract for Quality Assurance, to the extent practicable at all times and at all places during the term of the contract.

6. Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

7. Receiving and Storing Materials:

Storage areas for materials, equipment and dumpsters will be coordinated with the Technical Point of Contact. The contractor is responsible for protecting any stored material. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the contractor and will not be responsible for damage or theft of contractor equipment or material. All storage areas shall be restored to their pre-construction condition at the contractor’s expense and verified as such by the Government Technical Point of Contact (TPOC).

8. Clean Up:

Contractor shall inspect all equipment and materials used to prevent the release of any contaminants to the environment. The Contractor shall practice good housekeeping to maintain a safe job site. Remove rubbish and debris from the site daily, do not allow it to accumulate inside or outside of the building. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work, the contractor shall remove all tools, equipment, and materials that are not the property of the government and shall clean up the job site to the satisfaction of the Government.

9. Sustainability:

EPA Designated: Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.

Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

Part 2 Materials:

All materials shall be approved by the Technical Point of Contact prior to installation.

The contractor shall provide sufficient information on proposed materials and time to allow the Government to evaluate the products for adherence to specifications. Substitute materials will be evaluated in terms of quality, features, performance and expected service life. Substitute products must be accepted by the Government prior to installation.

The contractor shall submit engineering calculations, layout drawings that show pertinent dimensions, proposed layout, and a list of mechanical/hardware items to be installed in the building for approval by the Government.

1. New Building Requirements (Quantity:1):

Contractor shall provide (1) new precast concrete building suitable for electrical equipment. Walls of the building shall be a minimum of 4” thick and steel rebar reinforced high strength concrete. Building shall be weather-tight and vandal resistant with concrete walls, roof, and floor. All building joints shall be caulked with sealant on the exterior and interior surface of the joints. The finished interior walls shall be plywood over furring strips. Finished floor shall be concrete with a smooth steel form finish. Exterior finish of the building shall be architectural precast fine broom finish or similar. The color to be selected by the Government. Contractor shall deliver building pre-assembled to be placed on contractor’s prepared frost wall footing foundation. All exterior hardware shall be stainless steel, including all fasteners associated with heat pump, exterior light install, and exterior enclosure, etc. (For building layout, see photo 30.)

Exterior dimensions of new building shall be: 12’ x 14’ x 10’

Building shall be designed for the following:

Seismic Design Category ‘D’, Risk Design Category III Roof Live Load (Snow) – 50 PSF Floor Live Load – 150 PSF Wind Loading – 150 MPH

Concrete used in the building shall be steel-reinforced, 5000 PSI minimum 28-day compressive strength, air-entrained. Reinforcing steel shall be grade 60.

Building shall be fabricated in accordance with the following references:

ACI-318-11: Building Code Requirements for Structural Concrete and Commentary IBC 2012: International Building Code PCI Design Handbook, 7th Edition Concrete Reinforcing Institute, Manual of Standard Practice NFPA 70 – National Electrical Code, Current Edition 2020

Roof: Tapered roof style with pitch to shed water. Roof shall have overhanging eaves on all sides to prevent water migration into the building along top of wall panels.

Door: Building shall include one (1) 3070 Commercial Metal Single Door. Door and frame shall be fabricated from commercial grade galvannealed steel. Door shall be 18-gauge galvannealed steel, stiffened, insulated and sound deadened with honeycomb, polystyrene, or polyisocyanurate core. Welded flush door frame shall be 16-gauge galvannealed steel. Door and frame shall be painted one coat of rust inhibitive metal primer and two finish coats of pro industrial urethane alkyd enamel paint or similar; color shall match building.

a) Handle: Heavy duty commercial “Crash-bar” type opening mechanism on inside of door with heavy duty handle on outside.

b) Hinges: Three heavy duty commercial grade stainless steel hinges per door with non-removable hinge pins.

c) Lock Set: Heavy Duty Commercial Type Entry Mortise Lockset, Front Door Keyed (stainless steel finish). Contractor shall provide mortise housing to accept Medeco Large Format Interchangeable Core. A removable core will be provided by the Government.

d) Threshold: Raised interior, extruded aluminum bumper threshold with neoprene seal or equal.

e) Door Holder/Closer: Stainless Steel Heavy Duty Grade 1 with hold-open feature. ADA compliant; die cast aluminum alloy body; heavy duty forged steel main arm; full rack and pinion construction; captivated valves; capable of delayed action; provide 120o door opening and alternate mounting 180o door opening; comply with UL 10C Positive Pressure Fire Test

f) Door Kick Plate: Stainless Steel

g) Drip Cap: ANSI/BHMA A156.22 Certified; composed of aluminum alloy 6063;

slotted screw holes for adjustment; mechanical attachment via stainless steel screws; 2 ½” wide by 1 ½” tall.

h) Finish: Provide hardware in stainless steel.

i) Door Swing Handing: Right Hand Reverse (RHR) – Key Outside

j) Door Jamb Perimeter Weather Strip Set: Aluminum alloy 6063, T5 temper, Perimeter seal black neoprene, polyvinyl chloride (PVC), Nitrile rubber, and Chloroprene closed cell elastomeric foam sponge seal, installed with stainless steel sheet metal screws.

k) After installation, protect hardware from paint, stains, blemishes, and other damage until acceptance of work. Adjust hinges, locks, latches, holders, closers, and other items to operate properly. Demonstrate that keys operate locks.

Interior Wall Assembly:

a) 3/4” x 3” Furring Strip

b) 3/4” Plywood Sheathing (Painted white)

200 AMP Electrical Main Distribution Panel (MDP) (Quantity: 1):

Provide a surface mounted 200 Amp Electric Service Main Distribution Panel (MDP) Board Enclosure, Interior, and Cover, single phase (120/240 VAC), with 42 breaker spaces, with (2) 100 Amp breakers, (2) 30 Amp breakers, neutral bar, ground bar, and filler plates for all unused breaker spaces. Provide a typed panel board schedule, identifying all circuits.

MDP Breaker Schedule:

(1) 100 Amp Breaker – To feed the Generator/ATS and 100 Amp Electric Service Sub

Panel for the utility building.

(1) 100 Amp Breaker – To feed the comfort station. (Feed installed by Government)

(1) 30 AMP Breaker – To Feed Parking Lot Lighting (Feed installed by Government)

(1) 30 AMP Breaker – Spare

100 AMP Electric Service Sub Panel (Quantity: 1):

Provide a surface mounted 100 Amp Electric Service Sub Panel Board Enclosure, Interior, and Cover, single phase (120/240 VAC), with 30 breaker spaces, with (1) 100 Amp breaker, (10) 20 Amp breakers, (10)15 Amp breakers, neutral bar, ground bar, and filler plates for all unused breaker spaces. Provide a typed panel board schedule, identifying all circuits.

3R Wiring Trough, 6”x6”x72”, (Quantity: 1):

The 200 Amp main distribution panel, 100 Amp Service Sub-Panel, and the existing automatic transfer switch shall be connected via a surface mounted 6”x6”x72” 3R wiring trough under the panels (See photo 29). The primary main feed conduits shall directly enter the rear of the MDP. All other secondary feeds shall enter the surface mounted wiring trough.

Electric Outlets: Provide a total of (7) interior 20 Amp 120V specification grade duplex outlets, which shall be mounted 12” up from the floor located as shown on photo 30.

Installed utilizing surface mounted Electrical Metallic Tubing (EMT) conduits and steel boxes.

Lights: Provide (2) interior 4 ft LED lights which shall be mounted on the ceiling as depicted in Figure 1. The interior lights and conduits shall be surface mounted. Provide

(1) exterior LED light which shall be mounted above the door and shall be outfitted with a photocell for automatic activation after sunset. Both interior and exterior lights shall have individual manual light switches located inside the building next to the door on the left hand side as depicted in Figure 1.

Interior Conduits: In accordance with the National Electric Code, ground all exposed non-current-carrying metallic parts of electrical conduits and raceways. Conduit and fittings for all interior conduits shall be EMT at minimum size of 3/4”, unless otherwise stated herewithin. Provide conductors in accordance applicable requirements of NFPA 70 and UL. Minimum conductor size used for branch circuits shall be No. 12 AWG.

Interior switches shall be NEMA 1.

Building Penetrations/Entry Port Panel:

The Contractor shall coordinate with the Technical Point of Contact (TPOC) the size and locations of all penetrations needed to complete building installation to full functionality.

Building penetrations will be needed for all conduits, but not limited to, primary power feed, comfort station power feed, dock light power feed, range and tank light power feed, fiber line feed, traffic light feed, bank lighting, pre-wired relay, tide gauge, generator conductors, mini split HVAC equipment, exterior light over the door, canal bank lighting circuit, and for the grounding loop wires connection to interior plates.

Entry Port Panel, (Quantity: 2):

In addition, contractor shall provide (2) 1x4, 4” aluminum entry port panels, located approximately 8” down from the ceiling. One entry port shall be installed on the east and one on the south side of the building. Provide exterior weather tight boot kits for all entry panel openings. Install entry port panels in a bed of waterproof sealant. These entry port panels will be solely utilized by the Government during re-installation of telecom equipment after acceptance of the buildings (See Photos 26 and 27).

Ceiling Mounted Cable Trays: Buildings shall have a 12” wide, 4” deep powder coated wire basket type cable tray system along the two side walls and back wall, with an additional tray system along the center of the building. Photo 30 shows the general layout of the cable trays. The ceiling mounted cable trays shall be mounted using manufacturer recommended fasteners. Cable trays shall be a minimum of 7’6” off the floor. Cable tray shall be grounded and bonded to the building.

Grounding and Bonding.

Provide three interior copper grounding plates. A copper grounding plate, 4”H x 14”W x 0.25”D shall be mounted on both side walls and rear wall as depicted on photo 30. The copper grounding plate shall be mounted with standoffs from the wall.

Provide an exterior ground copper ring with four (4), ten (10) foot long by ¾” diameter rods driven into the soil located outside the new buildings near each corner. A copper No. 2/0 AWG or larger ground wire shall be connected to the rods and buried in a loop.

The copper No. 2/0 AWG wire shall be connected to interior grounding plates. All bonding and grounding connectors shall be submitted for the application. Install ground rods and loop approximately four (4) feet beyond the perimeter of the building. Adjust location of rods and loop at accessible locations around other subsurface tower foundations and utilities.

New Building shall include 24,000 BTU mini-split heat pumps (Quantity: 1):

a. Heat Pump Air Conditioner Condenser (Wall Mount):

i. Operating Mode: Heating and Cooling

ii. Capacity: 2 Tons (24000 BTU)

iii. Refrigerant Type: R-410A

iv. Installation Location: South Side of Building

v. Compressor Stages: Variable

vi. SEER: 20 (minimum)

vii. HSPF: 8.5 (minimum)

viii. Heavy-gauge galvanized-steel cabinet with powder paint finish.

ix. Coastal design unit which offers added protection against corrosive salt air and 500-hour salt-spray tested

x. Disconnect Switch: NEMA 4X, Stainless Steel non-fused

xi. Service Panel Breaker: 25 AMP (Per Manufacturer)

xii. Wall Mount: Heavy duty stainless steel wall

xiii. Bracket, rail, and anchors.

xiv. System shall be rated to provide heat down as low as -13°F as measured by the outdoor unit.

xv. Provide a hardwired programable thermostat with upper and lower temperature set points, to allow for automatic operation of system to maintain internal temperature within set parameters.

xvi. Provide pan heater.

xvii. Unit shall be installed on the south side of the building.

xviii. Provide power to/from new service panel.

b. Wall Mounted Indoor Heat Pump Unit:

i. Configuration: Wall Mounted

ii. Cooling Capacity: 24000 BTU

iii. Heating Capacity: 24000 BTU

iv. Connection: Rear, Thru Wall

Exterior Utilities

2. Existing Emergency Generator Relocation and Connection (Quantity: 1):

1. The contractor shall remove, store safely, and reinstall the existing Cummins Quiet Connect RS36 Propane Generator and existing automatic transfer switch. The contractor shall connect the generator to the ATS and 100 AMP breaker inside the new 200 amp MDP. The automatic transfer switch shall be installed inside the new building. The contractor shall install the Cummins RS36 Generator on a new raised 4’-6” x 10’-0” x 8” precast concrete equipment pad. Place pad on top of 6” crushed stone bed at grade level to maximize height. (See Photo 21)

2. Contractor shall provide all new 2” Schedule 80 PVC Conduits, conductors, and miscellaneous items to reconnect the Cummins Quiet Connect Propane Generator and ATS to be a fully functioning system.

3. Existing Propane Tank Relocation and Connection (Quantity: 1):

1. The contractor shall remove, store safely, and reinstall the existing propane tank on a new raised 4’-6” x 10’-0” x 8” precast concrete equipment pad. Place pad on top of 6” crushed stone bed at grade level to maximize height. (See Photo 21)

2. Contractor shall provide new gas pressure regulator, underground copper gas line, and grounding connections to the Cummins RS36 Propane Generator.

3. Gas line shall be installed below ground level shall have a minimum earth cover of 24” and shall be installed with at least 12” of clearance in any direction from any other underground utility system.

4. Existing Transformer Relocation and Connection (Quantity: 1):

1. The contractor shall remove, store safely, and reinstall the existing transformer on a new Single Phase Vault that is 45”x45”x48”. Place the vault on top of 6” crushed stone bed. (See Photo 22)

2. Contractor shall provide new load break elbow, conduits, conductors, and miscellaneous items to reconnect the transformer. Secondary conductors shall be 3/0 copper THHN or THHW for 200 amp service. The secondary lugs shall be rated for the purpose copper brass or bronze as recommended. No aluminum wire will be allowed.

3. Contractor shall provide two (2) 4” conduits from the underground electrical manhole vault to the transformer vault.

4. Contractor shall provide two (2) 4” conduits from transformer vault to the new precast building.

5. Contractor shall coordinate the placement of the vault to ensure the primary cable, which currently has minimal slack, has sufficient length to be reconnected with new load break elbow without requiring an extension or splice. This existing high voltage feeder shall remain unbroken from the utility pole behind the comfort station to the transformer.

6. Contractor personnel onsite responsible for electrical high voltage connections, must be qualified to terminate voltages above 1000 volts.

5. Electrical Handhole – (For Bank Lighting - See Photos 23-25):

1. Precast concrete HS-20 handhole with Electric Frame/Cover.

2. Size: 48” x 48” x 48” Square

3. From this new square electrical handhole, the Contractor shall install two (2) 2” conduits to the exterior lighting enclosure and one (1) 2” conduit directly into the building.

4. Reconnect/extend six (6) 2” existing conduits to this handhole.

6. Exterior Electrical Lighting Enclosure Stainless Steel (See Photo 28)

1. Rating NEMA 4X

2. Height 24”

3. Width 48”

4. Depth 11”

5. Material Stainless Steel

6. Number of Doors 2

7. Number of Keys/Locks 2

8. Closure Method Multipoint Latch

9. Features Concealed Hinge, Gasketed Cover, Mounting Feet

10. Lighting enclosure shall be mounted on the exterior of the building and house the transformer and relay for bank lighting.

7. Steel Panel for inside Electrical Lighting Enclosure Stainless Steel (See Photo 28):

1. Height 21”

2. Width 45”

3. Material Powder-Coated Steel, Color White

4. Gauge 11 ga

5. Panel Construction Solid

6. Steel panel shall be mounted inside the lighting enclosure to provide a surface to mount pre-wired relay coil and transformer in support of bank lighting.

8. Isolation Transformer, FAA-L-830-16 (Shall be installed inside the exterior enclosure to support bank lighting – High Voltage Side):

1. FAA Type L-830-16

2. Wattage 10/15W

3. Primary/Secondary AMPS 6.6/6.6

4. Design Frequency (Hz) 60

5. Weight (lb.) 3.6

9. Enclosed Pre-Wired Relay Coil: 10 A Rating, 120V AC, SPDT, 0.50 in NPT (Shall be installed inside the exterior enclosure to support bank lighting – Low Voltage Side):

1. Relay Mounting Style Surface

2. Electrical Connection Type Wire Lead

3. Current Rating 10 AMP

4. Coil Voltage 120V AC

5. Contact Form SPDT

6. Contact Rating (AC) 10 A @ 277V

7. Contact Rating (DC) 10 A @ 28V

8. Horsepower @ 120V AC 1 /6 hp

9. Horsepower @ 240V AC 1 /6 hp

10. Lead Length 16 inch

11. Nipple Size 0.50 in NPT

12. Response Time 20 msec

13. Status Indicator LED Indicator

10. Site Work Improvements:

1. Gravel Borrow Type B: Structural Back Fill Gravel Borrow Type B shall consist of inert material that is hard, durable stone and coarse sand, free from loam and clay, surface coatings, and deleterious materials. Maximum size of stone in gravel shall be three (3) inches largest dimension.

2. Stone: No 7 Stone Aggregate.

3. Stone: 3/8” Minus Aggregate (For Inside Building Frost Wall Footing Foundation).

4. Sand: Clean granular sand, free from organic matter and deleterious substances. (For

Backfill Around Underground Conduits – See Photo 20).

5. Frost wall Footing Foundation Concrete: 4,000 PSI with #4 Bar Reinforcement (See

Photo 19)

6. Topsoil - 3/8” Screened Loan Topsoil shall be from a local source that is clean, and free of weeds, litter, and brush with appropriate organic matter suited for growing grass.

7. Seed Mix – Provide seed mix for shoulder area in accordance with MassDOT Standard

Specifications Section M6.03.0.

11. Exterior Conduits:

1. Provide Schedule 80 PVC for all Underground Conduits and Fittings:

a. Provide 4” for Primary Feed and Secondary Feed to Building (vault, transformer, building)

b. Provide 2” for All Other Conduits

2. Aboveground Building Penetration Conduit Elbows - Schedule 80 PVC Type LB Access Fittings into new building for all conduits.

3. Underground Conduit Elbows – Long Sweep Radius Elbows for all conduits.

4. Conduit Spacers – Horizontal and vertical interlock type; polystyrene material

Part 3 Execution:

General:

1. All onsite work shall be coordinated with the Technical Point of Contact prior to start of mobilization. The work area is located within a public recreation area on federal property at the Cape Cod Canal Project.

2. Although work is not specifically shown or specified, contract shall include miscellaneous items, appurtenances, devices, and materials obviously necessary for a sound, secure and complete installation.

3. Contractor shall provide, erect, and maintain all necessary fencing, signs, and barriers for public safety. Work shall be performed in a safe manner that protects both workers and the public from hazards. The work area is used extensively by the public for recreational activities that occur 24 hours per day. At the end of each workday the Contractor shall ensure that the work area is left secured from public access. Contractor shall maintain at least one (1) single lane access on Freezer Road at all times.

4. The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time and be sequenced to minimize impacts on the public recreation area. Once power is shutoff by the government, contractor shall maintain an active daily presence onsite, prosecuting work continuously, without delay, and shall not demobilize nor vacate the work site until the project is complete. Contractor shall provide schedule which minimizes the duration of time from when the power is shutoff, the new building is installed, and all services returned to full operation.

5. All work areas are considered environmentally sensitive. Contractor shall inspect all equipment and materials used to prevent the release of any contaminants to the environment.

Prevent any sediment laden runoff from entering waterbodies, drainage inlets, and drainage areas from the pavement. Sediment controls may include, but are not limited to, entrenched staked straw bales, entrenched sediment (silt) fence, or catch basin sediment filter socks.

Remove all temporary sediment controls during final clean-up and prior to demobilization.

6. Existing Conditions: Contractor shall verify that actual site conditions are consistent with the existing conditions depicted within this statement of work. Discrepancies, omissions, and errors shall be reported to the government prior to the start of construction. Contractor shall be responsible for the protection of all existing structures, equipment, and areas from damage during construction. Any items that are damaged or altered during construction shall be restored to their pre-construction condition at the contractor’s expense and verified as such by the Government TPOC. Any disturbed areas at the work site, to include Freezer Roads, shall be restored to the minimum of pre-existing conditions.

7. Location of underground utilities shown are approximate only and not all underground utilities may be shown. The contractor shall protect all underground utilities from damage throughout the duration of construction and be fully responsible for any and all damages.

The contractor shall call Dig Safe at 811 or 1-888-dig-safe not less than 72 hours prior to the start of any excavation for verification of underground utility locations. Contractor shall "Dig Safe" the work area prior to any subsurface work. Physically verify underground utility locations, including utility depth, by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within 3 feet of the underground system. The government will disconnect power to the existing building and be available to confirm the disposition of any underground utilities found.

8. There is an existing tower located next to the building work area. There are existing underground grounding rods, rings, and connections around the existing tower. Contractor shall take care when excavating in these areas. Any damage caused to the existing grounding system shall be repaired by the contractor.

Demolition:

9. The existing black security fence shall be removed as necessary to complete the work. Any portion of security fence removed, shall be safely stored, and reinstalled to pre-existing condition at the completion of the project.

10. Prior to the contractor demolishing the building, the government will remove all active and salvageable equipment. All remaining miscellaneous items shall be demolished and disposed of by the contractor.

11. Contractor shall demolish the existing building, frost wall footing foundation, tree, interior existing nonfunctioning Propane Onan 35EK emergency generator, remaining miscellaneous wall mounted equipment, electrical service connections, service panels, disconnect switches, air conditioner, mini-split heat pump unit, equipment pads, light pole foundation base, and associated exterior underground conduits and conductors. The government will remove the existing light pole.

12. Lead-Based Paint Building Demolition: The existing building wall and roof construction is metal clad with internal insulation on a frost wall foundation. The building’s exterior wall white paint, exterior wall mauve paint, interior grey floor paint, teal interior wall paint, interior grey door paint was found to be positive for lead based paint. Contractor shall provide a site-specific Lead Compliance Plan to be submitted and accepted by the TPOC prior to initiating the demolition tasks involving any of these materials. An Industrial Hygienist shall provide 100% onsite project monitoring/oversight during demolition activities. Prior to disposal, construction waste suspected to contain lead must undergo Toxic Characteristic Leaching Procedure (TCLP) sampling for lead. Since the building is slated for demolition and much of this building is painted metal, the structure should be considered recyclable and the building with the painted components can be safely recycled without requiring lead remediation. Worker protection shall be used to be compliant with the OSHA requirements. Note, in 2021 the exterior asbestos grey caulking material on the electrical LB’s was abated. There are no known asbestos materials on this project. (See attached Environmental Consulting and Management Survey Report dated 10/15/2021).

Site Work Improvements:

13. Contractor shall provide and maintain erosion prevention and sedimentation control measures.

14. All fill required under this contract, beyond what is available from onsite excavation, shall be obtained from an approved source and furnished by the contractor. Onsite suitable fill shall be reused to the greatest extent possible. Outside the building frost wall foundation footprint, suitable onsite soil may be reused as backfill, compacted at 6” lifts. Any excess soils shall be removed and relocated by the contractor to an onsite designated area approximately 4 miles from the work site. Inside the new building frost wall foundation footprint, contractor shall provide all new gravel borrow/crushed stone backfill. Finish grade material shall be level to the surrounding area with slope for positive drainage. All disturbed grass areas outside the fence shall receive min. 6 inches of topsoil and seed. All disturbed areas inside the fence line shall receive top layer of 6” crushed stone bed. Provide a 3% slope away from the new and existing building to ensure a well-drained and graded area, to prevent the retention of standing water.

Building:

15. Frost Wall Footing: Contractor shall provide a frost wall footing for the new precast building (See Photo 19). After demolition and removal of existing frost wall footing, contractor shall compact in situ soil prior to installing new frost wall footing. Contractor shall install new concrete frost wall foundation on top of 6” crushed stone. Inside the wall, backfill with gravel borrow, compacted at 6” lifts and provide a top 6” thick layer of 3/8” minus aggregate crushed stone base compacted at 3” lifts. Clean crushed stone shall be 3/8" or smaller and must be screeded level within ¼" in both directions.